Monthly State Let Construction Report For Houston District As Of Apr 12, 2024 Page 7 Of 13

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZORIA
HighwaySH 288
FromAT CR 48 (IOWA COLONY BLVD)
To.
CSJ0598-02-112
Proj IDC 598-2-112
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
0.05038504600.1523310411.2060.5
Work Order08-02-22
Work Began11-08-22
Work Completed
Time Computed09-01-22
Contract Working Days409
Addl Days Granted0
Working Days Charged395
Percent Time Used96
Contractor(s)
GRANITE CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-112
HB FARMER FOUNDATION, LLC (2.16)
REPUBLIC TRAFFIC SAFETY, INC. (0.41)
QUALITY TURF FARMS, L.C. (1.88)
C.G. ANTHONY DELIVERIES, LLC (0.37)
DUSTROL, INC. (3.84)
PROFESSIONAL TRAFFIC CONTROL LLC (0.30)
A&J REBAR LLC (0.11)
MILSTEAD HIGHWAY SERVICES, LLC (0.55)
ANTIGO CONSTRUCTION, INC. (0.10)
A&J REBAR LLC (0.58)
CREACOM, INC. (1.22)
JAMES CONSTRUCTION GROUP, LLC (5.53)
JRB ENGINEERING, LLC (0.15)
SB FLEET - LUBE, LLC (0.22)
PRIMATE CONSTRUCTION, LP (0.20)
ROMAR UNLIMITED, INC. (0.82)
CURB PLANET INC. (0.02)
FORDE CONSTRUCTION COMPANY, INC. (0.27)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.32)
DORAN STEEL, INC. (0.13)
AARON CONCRETE CONTRACTORS, LLC (1.09)
Contract #06223404
Totals38504600.15667377.6323310411.2060.5

CountyBRAZORIA
HighwaySH 288
FromAT CR 57 (CEDAR RAPIDS PARKWAY)
To.
CSJ0598-02-113
Proj IDC 598-2-113
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.08521548238.4810228037.4647.4
CountyBRAZORIA
HighwaySH 288
FromAT CR 64 (DAVENPORT PARKWAY)
To.
CSJ0598-02-114
Proj IDC 598-2-114
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
0.98721418853.4913005604.0260.7
CountyBRAZORIA
HighwaySH 288
FromAT CR 56 (MERIDIANA PARKWAY)
To.
CSJ0598-02-125
Proj IDF 2022(574)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
1.02014519659.3312102513.9283.3
Work Order09-15-22
Work Began11-14-22
Work Completed
Time Computed11-14-22
Contract Working Days796
Addl Days Granted0
Working Days Charged408
Percent Time Used51
Contractor(s)
GRANITE CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-113
HB FARMER FOUNDATION, LLC (4.39)
QUALITY TURF FARMS, L.C. (2.89)
REPUBLIC TRAFFIC SAFETY, INC. (0.56)
C.G. ANTHONY DELIVERIES, LLC (0.95)
PROFESSIONAL TRAFFIC CONTROL LLC (0.72)
A&J REBAR LLC (0.21)
MILSTEAD HIGHWAY SERVICES, LLC (0.74)
A BROTHERS MILLING, LLC (0.42)
A&J REBAR LLC (0.82)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (2.74)
BLS SERVICES (0.14)
KLP COMMERCIAL, L.L.C. (3.92)
JAMES CONSTRUCTION GROUP, LLC (3.32)
JRB ENGINEERING, LLC (0.10)
SB FLEET - LUBE, LLC (0.00)
PRIMATE CONSTRUCTION, LP (0.19)
ROMAR UNLIMITED, INC. (0.53)
CURB PLANET INC. (0.02)
SB FLEET - LUBE, LLC (0.21)
AARON CONCRETE CONTRACTORS, LLC (0.43)
Contract #08223004
Totals57486751.301355700.5535336155.4061.4

CountyBRAZORIA
HighwaySH 288
FromAT CR 63 (DUBUQUE PARKWAY)
To.
CSJ0598-02-115
Proj IDC 598-2-115
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.38222518415.3915819505.7070.2
CountyBRAZORIA
HighwaySH 288
FromAT CR 60
To.
CSJ0598-02-116
Proj IDF 2022(929)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.60526850064.0213752004.8951.2
Work Order09-15-22
Work Began11-14-22
Work Completed
Time Computed11-14-22
Contract Working Days629
Addl Days Granted0
Working Days Charged408
Percent Time Used64
Contractor(s)
GRANITE CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-115
HB FARMER FOUNDATION, LLC (2.94)
QUALITY TURF FARMS, L.C. (2.38)
REPUBLIC TRAFFIC SAFETY, INC. (0.39)
C.G. ANTHONY DELIVERIES, LLC (1.73)
PROFESSIONAL TRAFFIC CONTROL LLC (0.91)
A&J REBAR LLC (0.12)
MILSTEAD HIGHWAY SERVICES, LLC (0.99)
ANTIGO CONSTRUCTION, INC. (0.05)
A BROTHERS MILLING, LLC (0.59)
A&J REBAR LLC (0.69)
CREACOM, INC. (0.43)
BLS SERVICES (0.27)
KLP COMMERCIAL, L.L.C. (0.82)
JAMES CONSTRUCTION GROUP, LLC (6.89)
JRB ENGINEERING, LLC (0.11)
SB FLEET - LUBE, LLC (0.00)
PRIMATE CONSTRUCTION, LP (0.22)
ROMAR UNLIMITED, INC. (0.77)
FORDE CONSTRUCTION COMPANY, INC. (0.29)
SB FLEET - LUBE, LLC (0.32)
AARON CONCRETE CONTRACTORS, LLC (0.63)
Contract #08223205
Totals49368479.412662118.4729571510.5959.8

CountyMONTGOMERY
HighwayIH 45
FromLEAGUE LINE ROAD
ToWALKER COUNTY LINE
CSJ0675-08-111
Proj IDNH 2020(596)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
10.1512147330.782410015.4199.9
Work Order06-09-20
Work Began04-12-21
Work Completed
Time Computed07-09-20
Contract Working Days270
Addl Days Granted0
Working Days Charged269
Percent Time Used99
Contractor(s)
SICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-111
USA AMTECH, INC. (11.35)
ODUM SERVICES, LLC (3.80)
THIRD COAST SERVICES LLC (2.12)
MCA COMMUNICATIONS, INC. (4.32)
GROUND HOG FOUNDATION DRILLING (1.80)
Contract #04203231
Totals2147330.780.002410015.4199.9

CountyMONTGOMERY
HighwayIH 45
FromFM 830
ToFM 1097
CSJ0675-08-114
Proj IDCC 675-8-114
Work TypeNEW LOCATION NON-FREEWAY
 
7473853.327550458.5099.9
Work Order07-20-22
Work Began09-26-22
Work Completed
Time Computed08-19-22
Contract Working Days252
Addl Days Granted0
Working Days Charged251
Percent Time Used99
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-114
BROCK CONSTRUCTION, LLC (0.71)
HIGHWAY 1 LLC (0.45)
THIRD COAST SERVICES LLC (0.77)
LONESTAR TRAFFIC SAFETY, LLC (0.07)
WILLOW CITY SIGN & RAIL, INC. (0.87)
CEN TEX HYDROSEED, INC. (0.63)
A&J REBAR LLC (0.66)
PRIMATE CONSTRUCTION, LP (0.31)
QUALITY TURF FARMS, L.C. (0.00)
J.KRU LAND SERVICES, LLC (0.05)
SOUTHEAST GRINDING AND GROOVING LLC (0.12)
CURB PLANET INC. (0.01)
Contract #06223411
Totals7473853.322917.497550458.5099.9

CountyMONTGOMERY
HighwayIH 45
FromN OF FM 830
ToS OF FM 1097
CSJ0675-08-120
Proj IDCC 675-8-120
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.5233167865.710.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days151
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243226
Totals3167865.710.000.000.0

CountyGALVESTON
HighwayFM 1765
FromIH 45
ToVAUTHIER RD
CSJ0686-02-029
Proj IDSTP 2023(549)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8051425058.661412850.8299.1
Work Order05-17-23
Work Began08-21-23
Work Completed
Time Computed08-15-23
Contract Working Days60
Addl Days Granted0
Working Days Charged59
Percent Time Used98
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0686-02-029
GMJ PAVING COMPANY LLC (2.41)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (2.70)
GEORGE MEEKS LANDPRO, INC. (0.82)
STRIPE LINES, INC. (0.77)
DARKHORSE INDUSTRIES, L.L.C. (0.12)
Contract #04233220
Totals1425058.6617082.581412850.8299.1

CountyMONTGOMERY
HighwayFM 149
FromAT SH 105
To.
CSJ0720-02-097
Proj IDF 2021(493)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.085272609.79406135.4199.9
Work Order05-27-21
Work Began08-02-21
Work Completed
Time Computed08-02-21
Contract Working Days53
Addl Days Granted0
Working Days Charged45
Percent Time Used84
Contractor(s)
CITYLYNX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-097
SEMPER STRIPING LLC (2.13)
ALLY GENERAL SOLUTIONS, LLC (32.58)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC (78.24)
CEN TEX HYDROSEED, INC. (2.89)
Contract #04213014
Totals272609.790.00406135.4199.9

CountyHARRIS ETC
HighwaySH 249 ETC
FromSPRING CYPRESS
ToGRANT/SCHROEDER
CSJ0720-03-143
Proj IDSTP 1802(437)HES
Work TypeINTERCONNECT SIGNALS
 
17.9453528350.324166931.8199.9
Work Order01-11-19
Work Began06-06-19
Work Completed
Time Computed04-11-19
Contract Working Days362
Addl Days Granted90
Working Days Charged448
Percent Time Used99
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-143
LONESTAR TRAFFIC SAFETY, LLC (1.14)
TCH DIRECTIONAL DRILLING (13.68)
CHIRON COMMUNICATION SERVICES, LLC (6.11)
Contract #08183016
Totals3528350.320.004166931.8199.9

CountyHARRIS
HighwaySH 249
FromAT ALICE ROAD
To.
CSJ0720-06-002
Proj IDSTP 2022(209)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200375697.38405850.7199.9
Work Order02-15-22
Work Began06-15-22
Work Completed
Time Computed06-15-22
Contract Working Days78
Addl Days Granted0
Working Days Charged67
Percent Time Used85
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0720-06-002
LONESTAR TRAFFIC SAFETY, LLC (0.63)
HIGHWAY 1 LLC (4.26)
Contract #01223030
Totals375697.380.00405850.7199.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-511
Proj IDSTP 2017(158)
Work TypeNEW TRAFFIC SIGNALS
 
0.5081718929.722399324.4399.9
Work Order01-04-17
Work Began07-10-17
Work Completed
Time Computed07-10-17
Contract Working Days199
Addl Days Granted190
Working Days Charged305
Percent Time Used78
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-511
GLOBE ELECTRIC SUPPLY COMPANY, INC. (5.90)
STRIPE LINES, INC. (1.74)
MENADE, INC. (12.49)
ALLY GENERAL SOLUTIONS, LLC (0.34)
Contract #10163215
Totals1718929.720.002399324.4399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-523
Proj IDNH 2018(110)
Work TypeINST TS
 
0.0011468618.081895029.0999.9
Work Order01-10-18
Work Began03-19-18
Work Completed
Time Computed04-10-18
Contract Working Days260
Addl Days Granted0
Working Days Charged227
Percent Time Used87
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-523
AAA ASPHALT PAVING, INC. (4.43)
HIGHWAY 1 LLC (5.13)
Contract #12173014
Totals1468618.086922.001895029.0999.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-526
Proj IDC 912-00-526
Work TypeTRAFFIC CONTROL DEVICES
 
0.002291372.001294488.5199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-19-20
Work Began08-17-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged76
Percent Time Used63
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-526
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10203013
Totals291372.0040476.171294488.5199.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-531
Proj IDC 912-0-531
Work TypeINSTALL NEW TRAFFIC SIGNALS
 
0.0011999535.002075326.3399.9
Work Order08-16-18
Work Began01-18-19
Work Completed
Time Computed12-14-18
Contract Working Days160
Addl Days Granted200
Working Days Charged353
Percent Time Used98
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-531
SPECIALTY DRILLING, LLC (0.45)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (2.24)
STRIPE LINES, INC. (1.97)
MLH CONCRETE (0.67)
SEMPER STRIPING LLC (1.18)
Contract #07183028
Totals1999535.001656.002075326.3399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-532
Proj IDC 912-00-532
Work TypeINSTALL NEW TRAFFIC SIGNALS
 
0.0011896973.001936689.4799.9
Work Order01-07-19
Work Began05-07-19
Work Completed
Time Computed05-07-19
Contract Working Days167
Addl Days Granted220
Working Days Charged295
Percent Time Used76
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-532
AAA ASPHALT PAVING, INC. (7.43)
STRIPE LINES, INC. (1.51)
Contract #12183218
Totals1896973.001060.001936689.4799.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-577
Proj IDSTP 2020(504)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011438222.501676751.8099.9
Work Order02-13-20
Work Began09-20-21
Work Completed
Time Computed06-12-20
Contract Working Days201
Addl Days Granted0
Working Days Charged170
Percent Time Used84
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-577
STRIPE LINES, INC. (1.65)
L&M INFRASTRUCTURE, LLC. (7.30)
BATTERSON, LLP (36.50)
SPARTAN SPECIALTY COMPANIES, LLC (3.47)
Contract #01203020
Totals1438222.501000.001676751.8099.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-578
Proj IDSTP 2020(597)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011780190.001899903.3999.9
Work Order03-11-20
Work Began10-18-21
Work Completed
Time Computed07-09-20
Contract Working Days216
Addl Days Granted0
Working Days Charged105
Percent Time Used48
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-578
STRIPE LINES, INC. (1.97)
L&M INFRASTRUCTURE, LLC. (5.90)
BATTERSON, LLP (0.56)
Contract #02203018
Totals1780190.000.001899903.3999.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-587
Proj IDF 2022(143)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012915576.65125128.804.2
Work Order01-12-22
Work Began00-00-00
Work Completed
Time Computed05-12-22
Contract Working Days418
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-587
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12213217
Totals2915576.650.00125128.804.2

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-588
Proj IDC 912-00-588
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011328813.9016750.001.2
Work Order03-24-22
Work Began00-00-00
Work Completed
Time Computed07-30-22
Contract Working Days213
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-588
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02223013
Totals1328813.900.0016750.001.2

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To,
CSJ0912-00-590
Proj IDC 912-00-590
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012193801.201659446.3275.6
Work Order01-08-21
Work Began07-18-22
Work Completed
Time Computed05-08-21
Contract Working Days236
Addl Days Granted0
Working Days Charged69
Percent Time Used29
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-590
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11203020
Totals2193801.200.001659446.3275.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13