Monthly Local Let Maintenance Report For Houston District As Of Nov 13, 2018 Page 8 Of 14

Last Update: Tuesday, November 13, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH0010
FromHOUSTON AVENUE_BRIDGE
ToOVER IH 10 EASTBOUND
CSJ6310-57-001
Proj IDEMC - 631057001
Work TypeEMC BRIDGE AND SLAB REPAIR
 
0.001394393.45556012.38100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-04-17
Work Completed06-13-17
Time Computed00-00-00
Contract Working Days24
Addl Days Granted0
Working Days Charged19
Percent Time Used79
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161240
Totals394393.450.00556012.38100.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6310-76-001
Proj IDSUP - 631076001
Work TypeLITTER REMOVAL
 
0.001159282.11144540.24100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-17
Work Completed03-01-18
Time Computed03-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6310-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171230
Totals159282.110.00144540.24100.0

CountyMONTGOMERY
HighwaySH0099
FromFRTG RD APPOX .78 MI. E/BIRNHAM WOODS DR
ToFRTG BETWEEN KUYKENDAHL RD & HILDEBRAND
CSJ6311-46-001
Proj IDRMC - 631146001
Work TypeDRIVEWAY INSTALLATION
 
0.001131468.50131468.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-08-18
Work Began01-08-18
Work Completed
Time Computed01-08-18
Contract Working Days45
Addl Days Granted0
Working Days Charged37
Percent Time Used82
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171201
Totals131468.500.00131468.5099.9

CountyBRAZORIA
HighwaySH0332
FromSH332\END MNT
ToSH332\END MNT
CSJ6311-72-001
Proj IDEMC - 631172001
Work TypeCULVERT REPLACEMENT
 
0.001445912.00441432.4998.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-30-16
Work Began12-05-16
Work Completed
Time Computed12-05-16
Contract Working Days63
Addl Days Granted0
Working Days Charged34
Percent Time Used53
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161241
Totals445912.000.00441432.4998.9

CountyGALVESTON
HighwaySH0006
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6312-09-001
Proj IDSUP - 631209001
Work TypeLITTER REMOVAL
 
0.001102099.3588483.32100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-29-16
Work Began01-02-17
Work Completed01-03-18
Time Computed01-02-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6312-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161230
Totals102099.350.0088483.32100.0

CountyWALLER
HighwayUS0290
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6312-14-001
Proj IDRMC - 631214001
Work TypeDITCH CLEANING AND RESHAPING
 
0.001259600.00316797.4499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-12-17
Work Completed
Time Computed06-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged343
Percent Time Used93
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04171202
Totals259600.000.00316797.4499.9

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6312-40-001
Proj IDRMC - 631240001
Work TypeROADSIDE MOWING
 
0.001256507.28129202.4250.3
Work Order00-00-00
Work Began07-19-17
Work Completed
Time Computed07-15-17
Contract Working Days137
Addl Days Granted0
Working Days Charged47
Percent Time Used34
Contractor(s)
ANGEL LADY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6312-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171202
Totals256507.284704.33129202.4250.3

CountyBRAZORIA
HighwaySH0288
FromBRAZORIA MAINTENANCE OFFICE
ToBRAZORIA MAINTENANCE OFFICE
CSJ6312-89-001
Proj IDSUP - 631289001
Work TypeJANITORIAL MAINTENANCE
 
0.00128290.0027600.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-02-17
Work Began01-02-17
Work Completed01-02-18
Time Computed01-02-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6312-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161232
Totals28290.000.0027600.00100.0

CountyFORT BEND
HighwaySH0036
FromFORT BEND AREA OFFICE
ToFORT BEND AREA OFFICE
CSJ6313-07-001
Proj IDSUP - 631307001
Work TypeJANITORIAL MAINTENANCE
 
0.00126980.0026370.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-17
Work Completed01-01-18
Time Computed01-02-17
Contract Working Days365
Addl Days Granted0
Working Days Charged351
Percent Time Used96
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6313-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161231
Totals26980.000.0026370.00100.0

CountyHARRIS
HighwayUS0059
FromUS 59 HOV W RAMP AT EDLOE
ToUS 59 SB TO 610 NL EB
CSJ6313-20-001
Proj IDBPM - 631320001
Work TypeBRIDGE REPAIRS
 
0.001171880.00189234.82100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-17
Work Completed01-30-18
Time Computed08-01-17
Contract Working Days38
Addl Days Granted0
Working Days Charged45
Percent Time Used118
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171201
Totals171880.000.00189234.82100.0

CountyHARRIS
HighwaySH0249
FromSB FRONTAGE RD BRIDGE OVER CYPRESS CREEK
ToSB FRONTAGE RD BRIDGE OVER CYPRESS CREEK
CSJ6313-22-001
Proj IDBPM - 631322001
Work TypeRIPRAP & SCOUR REPAIR
 
0.001160886.69232771.74100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-06-17
Work Began06-13-17
Work Completed02-06-18
Time Computed06-13-17
Contract Working Days40
Addl Days Granted0
Working Days Charged25
Percent Time Used62
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6313-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04171203
Totals160886.690.00232771.74100.0

CountyHARRIS
HighwayIH0069
FromGARNERS BAYOU AT IH 69
ToTOWNSEN BLVD AT SAN JAC.REL. CHANNEL
CSJ6313-23-001
Proj IDBPM - 631323001
Work TypeREPAIR WINGWALL AND EROSION CONTROL
 
0.00187191.90124070.48100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-02-17
Work Began05-08-17
Work Completed02-06-18
Time Computed05-08-17
Contract Working Days60
Addl Days Granted0
Working Days Charged24
Percent Time Used40
Contractor(s)
PLANT FUEL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171205
Totals87191.900.00124070.48100.0

CountyWALLER
HighwayIH0010
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6313-25-001
Proj IDSUP - 631325001
Work TypeLITTER REMOVAL
 
0.001115486.02111723.9096.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged362
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6313-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171232
Totals115486.020.00111723.9096.7

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6313-26-001
Proj IDRMC - 631326001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001264040.00387708.8499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-14-17
Work Completed
Time Computed06-14-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04171204
Totals264040.000.00387708.8499.9

CountyHARRIS
HighwayIH0069
FromNORTH HARRIS AREA OFFICE
ToNORTH HARRIS AREA OFFICE
CSJ6313-47-001
Proj IDSUP - 631347001
Work TypeJANITORIAL MAINTENANE
 
0.00121920.2420785.18100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-17
Work Began07-03-17
Work Completed07-03-18
Time Computed07-03-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
LENDING HELPING HANDS TO OTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171230
Totals21920.240.0020785.18100.0

CountyMONTGOMERY
HighwayIH0069
FromVARIOUS HWYS IN MONTGOMERY COUNTY
ToVARIOUS HWYS IN MONTGOMERY COUNTY
CSJ6313-50-001
Proj IDRMC - 631350001
Work TypeREFL PAV MRKGS (GRAPHICS)
 
0.001194948.50247994.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-06-17
Work Began07-06-17
Work Completed
Time Computed07-06-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171202
Totals194948.500.00247994.6499.9

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGNWAYS IN WEST HARRIS CO.
To.
CSJ6313-59-001
Proj IDRMC - 631359001
Work TypeBRIDGE DECK REPAIR
 
0.001133700.0083393.6362.3
Work Order00-00-00
Work Began08-01-17
Work Completed
Time Computed08-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged450
Percent Time Used61
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171206
Totals133700.0029287.6983393.6362.3

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGNWAYS IN WEST HARRIS CO.
To.
CSJ6313-61-001
Proj IDRMC - 631361001
Work TypeHERBICIDE
 
0.00181300.000.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-18
Work Completed06-06-18
Time Computed01-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged144
Percent Time Used39
Contractor(s)
CROSBY RD CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6313-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171207
Totals81300.000.000.00100.0

CountyGALVESTON
HighwaySH0087
FromGALVESTON FERRY LANDING
ToBOLIVAR FERRY LANDING
CSJ6313-73-001
Proj IDRMC - 631373001
Work TypeLANDSCAPE MAINTENANCE SERVICE
 
0.01091900.00102300.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-25-17
Work Completed08-13-18
Time Computed05-01-17
Contract Working Days365
Addl Days Granted92
Working Days Charged451
Percent Time Used98
Contractor(s)
CROSBY RD CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6313-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171208
Totals91900.000.00102300.00100.0

CountyHARRIS
HighwayIH0069
FromNORTH HARRIS AREA OFFICE
ToNORTH HARRIS AREA OFFICE
CSJ6313-82-001
Proj IDSUP - 631382001
Work TypeLANDSCAPE MAINTENANCE
 
0.00123475.0023475.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-17
Work Began00-00-00
Work Completed08-01-18
Time Computed08-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged354
Percent Time Used96
Contractor(s)
TIBH INDUSTRIES, INC.
THE TEXAS HOUSE
SUBCONTRACTOR(S) FOR CCSJ: 6313-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171230
Totals23475.000.0023475.00100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14