Monthly State Let Maintenance Report For Houston District As Of Oct 16, 2017 Page 4 Of 9

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH0010
FromVARIOUS HWYS IN EAST HARRIS COUNTY
ToVARIOUS HWYS IN EAST HARRIS COUNTY
CSJ6287-70-001
Proj IDRMC - 628770001
Work TypeCONCRETE PAVEMENT, RIPRAP AND JOINT REPA
 
0.001943700.001002238.95100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-19-15
Work Completed04-04-17
Time Computed10-19-15
Contract Working Days731
Addl Days Granted0
Working Days Charged532
Percent Time Used72
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154202
Totals943700.000.001002238.95100.0

CountyHARRIS
HighwayIH0045
FromIH45
ToSH146
CSJ6287-97-001
Proj IDRMC - 628797001
Work TypeHIGH MAST REPAIR AND OR REPLACEMENT
 
0.001881503.37269577.7030.5
Work Order00-00-00
Work Began11-07-16
Work Completed
Time Computed11-17-16
Contract Working Days160
Addl Days Granted0
Working Days Charged85
Percent Time Used53
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164005
Totals881503.370.00269577.7030.5

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS CO.
To.
CSJ6288-34-001
Proj IDRMC - 628834001
Work TypeCRACK & SPALL REPAIR
 
0.001505500.00380834.4675.3
Work Order00-00-00
Work Began01-07-16
Work Completed
Time Computed01-07-16
Contract Working Days731
Addl Days Granted0
Working Days Charged628
Percent Time Used85
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154212
Totals505500.000.00380834.4675.3

CountyMONTGOMERY
HighwayUS0059
FromVARIOUS HWYS IN MONTGOMERY
ToVARIOUS HWYS IN MONTGOMERY
CSJ6288-41-001
Proj IDRMC - 628841001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001425500.00433381.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-11-15
Work Began09-14-15
Work Completed08-19-16
Time Computed09-14-15
Contract Working Days366
Addl Days Granted0
Working Days Charged343
Percent Time Used93
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6288-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07154003
Totals425500.000.00433381.00100.0

CountyWALLER
HighwayUS0290
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6289-90-001
Proj IDRMC - 628990001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001510500.00621438.8399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-18-15
Work Began02-16-16
Work Completed
Time Computed12-01-15
Contract Working Days366
Addl Days Granted0
Working Days Charged358
Percent Time Used97
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6289-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09154204
Totals510500.000.00621438.8399.9

CountyFORT BEND
HighwayFM2759
FromFM 762
To0.536 MI EAST OF FM 762
CSJ6290-40-001
Proj IDRMC - 629040001
Work TypeBASE REPAIR,WIDENING,OVERLAY,PAV MRKS
 
0.536594812.49562147.27100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-14-16
Work Completed07-05-16
Time Computed04-14-16
Contract Working Days30
Addl Days Granted0
Working Days Charged21
Percent Time Used70
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6290-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164005
Totals594812.490.00562147.27100.0

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6290-46-001
Proj IDRMC - 629046001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.0011166962.90958468.80100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-16-15
Work Completed11-15-16
Time Computed11-16-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6290-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09154202
Totals1166962.900.00958468.80100.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HWYS DISTRICTWIDE (WITHIN BW 8)
ToVARIOUS HWYS DISTRICTWIDE_(WITHIN BW 8)
CSJ6290-58-001
Proj IDRMC - 629058001
Work TypeDISTRICTWIDE PAVEMENT GRAPHICS REFRESH
 
1.0001486714.001599292.9599.9
Work Order00-00-00
Work Began04-11-16
Work Completed
Time Computed04-11-16
Contract Working Days360
Addl Days Granted0
Working Days Charged195
Percent Time Used54
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154004
Totals1486714.000.001599292.9599.9

CountyHARRIS
HighwaySH0249
FromVARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
ToVARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
CSJ6290-69-001
Proj IDRMC - 629069001
Work TypeFULL DEPTH CONC & ASPHALT REPAIR
 
0.001657255.00625102.15100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-22-16
Work Began02-24-16
Work Completed03-31-17
Time Computed02-01-16
Contract Working Days366
Addl Days Granted60
Working Days Charged424
Percent Time Used99
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6290-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154008
Totals657255.000.00625102.15100.0

CountyWALLER
HighwayUS0290
FromVARIOUS HIGHWAYS IN WALLER COUNTY
ToVARIOUS HIGHWAYS IN WALLWER COUNTY
CSJ6290-93-001
Proj IDRMC - 629093001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
0.001477950.00495535.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-15
Work Began01-04-16
Work Completed
Time Computed01-04-16
Contract Working Days366
Addl Days Granted0
Working Days Charged360
Percent Time Used98
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154214
Totals477950.000.00495535.0099.9

CountyGALVESTON
HighwaySH0146
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6290-95-001
Proj IDRMC - 629095001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001510500.00619272.12100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-09-15
Work Began01-28-16
Work Completed12-14-16
Time Computed12-14-15
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6290-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09154203
Totals510500.000.00619272.12100.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6291-18-001
Proj IDRMC - 629118001
Work TypeREFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.001690373.00620885.0389.9
Work Order12-16-15
Work Began01-04-16
Work Completed
Time Computed01-04-16
Contract Working Days731
Addl Days Granted0
Working Days Charged632
Percent Time Used86
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154013
Totals690373.000.00620885.0389.9

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN BRAZORIA COUNTY
ToVARIOUS HWYS IN BRAZORIA COUNTY
CSJ6291-30-001
Proj IDRMC - 629130001
Work TypeSPALL REPAIR
 
0.001477762.00453751.40100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-04-16
Work Completed04-04-17
Time Computed04-04-16
Contract Working Days366
Addl Days Granted0
Working Days Charged354
Percent Time Used96
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154005
Totals477762.000.00453751.40100.0

CountyGALVESTON
HighwayFM1764
FromFM 2004 FRONTAGE ROAD ONLY
ToSH 146 FRONTAGE ROAD ONLY
CSJ6292-70-001
Proj IDRMC - 629270001
Work TypeMILLING,SEAL COAT,1.5" ACP OVERLAY
 
4.5992363014.512582286.84100.0
Work Order02-17-17
Work Began03-20-17
Work Completed10-03-17
Time Computed03-06-17
Contract Working Days90
Addl Days Granted0
Working Days Charged89
Percent Time Used98
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6292-70-001
ROADSAFE TRAFFIC SYSTEMS, INC. (7.60)
THIRD COAST SERVICES LLC (3.71)
PROFFESSIONAL TRAFFIC CONTROL, LLC. (1.56)
Contract #11164203
Totals2363014.510.002582286.84100.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS CONTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6293-15-001
Proj IDRMC - 629315001
Work TypeLONG LINE PAVEMENT MARKINGS
 
0.001450057.50504795.37100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-05-16
Work Began02-23-16
Work Completed02-01-17
Time Computed02-16-16
Contract Working Days366
Addl Days Granted0
Working Days Charged352
Percent Time Used96
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154006
Totals450057.500.00504795.37100.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HWYS IN EAST HARRIS COUNTY
ToVARIOUS HWYS IN EAST HARRIS COUNTY
CSJ6293-36-001
Proj IDRMC - 629336001
Work TypePUMP STATION & DRAINAGE SYSTEM CLEANING
 
0.001422800.00158883.0037.5
Work Order00-00-00
Work Began04-01-16
Work Completed
Time Computed04-01-16
Contract Working Days731
Addl Days Granted0
Working Days Charged540
Percent Time Used73
Contractor(s)
CLEAN SERVE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6293-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154205
Totals422800.000.00158883.0037.5

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6293-69-001
Proj IDRMC - 629369001
Work TypeGUARDRAIL REPAIR
 
0.001439210.00303142.5369.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-25-16
Work Began05-26-16
Work Completed
Time Computed05-26-16
Contract Working Days366
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164203
Totals439210.000.00303142.5369.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS CO.
To.
CSJ6294-83-001
Proj IDRMC - 629483001
Work TypePAVEMENT MARKINGS
 
0.0011250080.00415291.6133.2
Work Order00-00-00
Work Began05-06-16
Work Completed
Time Computed05-06-16
Contract Working Days730
Addl Days Granted0
Working Days Charged508
Percent Time Used69
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164006
Totals1250080.000.00415291.6133.2

CountyHARRIS
HighwaySL0008
FromSL 8 FRTG RD BETWEEN BUFFALO BAYOU
ToAND MIGNON LN
CSJ6295-26-001
Proj IDRMC - 629526001
Work TypeWIDEN FRTG RDWY TO ADD LEFT TURN LANE
 
0.001476060.45562244.66100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-21-16
Work Completed08-16-16
Time Computed03-17-16
Contract Working Days72
Addl Days Granted0
Working Days Charged69
Percent Time Used95
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154007
Totals476060.450.00562244.66100.0

CountyGALVESTON
HighwaySH0087
FromBOLIVAR FERRY LANDING
ToBOLIVAR FERRY LANDING
CSJ6295-36-001
Proj IDRMC - 629536001
Work TypeDREDGING
 
0.0101010000.001005609.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-31-16
Work Completed08-01-16
Time Computed06-01-16
Contract Working Days40
Addl Days Granted4
Working Days Charged52
Percent Time Used118
Contractor(s)
CALLAN MARINE LTD
SUBCONTRACTOR(S) FOR CCSJ: 6295-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164007
Totals1010000.000.001005609.00100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9