Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | HARRIS |
Highway | US0290 |
From | VARIOUS HIGHWAYS IN THE WEST HARRIS CO. |
To | VARIOUS HIGHWAYS IN THE WEST HARRIS CO. |
CSJ | 6445-29-001 |
Proj ID | RMC - 644529001 |
Work Type | SWEEPING AND DEBRIS REMOVAL |
|
| 0.010 | 2399332.00 | | 471562.26 | 19.6 |
Work Order | 00-00-00 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 12-01-23 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 87 |
Percent Time Used | 11 |
Contractor(s) |
T & M LAWN-FENCE SERVICE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6445-29-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09234022 |
| Totals | 2399332.00 | 166527.51 | 471562.26 | 19.6 |
|
County | WALLER |
Highway | US0290 |
From | VARIOUS HIGHWAYS IN WALLER COUNTY |
To | VARIOUS HIGHWAYS IN WALLER COUNTY |
CSJ | 6448-17-001 |
Proj ID | RMC - 644817001 |
Work Type | CLEANING AND SWEEPING HIGHWAYS |
|
| 0.010 | 290978.32 | | 11604.51 | 3.9 |
Work Order | 00-00-00 |
Work Began | 02-14-24 |
Work Completed | |
Time Computed | 02-14-24 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 12 |
Percent Time Used | 3 |
Contractor(s) |
EXPERT MAINTENANCE & CONSTRUCTION SERVICES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6448-17-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234212 |
| Totals | 290978.32 | 11604.51 | 11604.51 | 3.9 |
|
County | MONTGOMERY |
Highway | IH0045 |
From | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
To | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
CSJ | 6449-13-001 |
Proj ID | RMC - 644913001 |
Work Type | DRAINAGE SYSTEM CLEANING |
|
| 0.010 | 2428750.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 03-01-24 |
Work Began | 03-01-24 |
Work Completed | |
Time Computed | 03-01-24 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
SHALOM SERVICES CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 6449-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234209 |
| Totals | 2428750.00 | 0.00 | 0.00 | 0.0 |
|
County | WALLER |
Highway | US0290 |
From | VARIOUS HIGHWAYS IN WALLER COUNTY |
To | VARIOUS HIGHWAYS IN WALLER COUNTY |
CSJ | 6449-33-001 |
Proj ID | RMC - 644933001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 385249.00 | | 47327.00 | 12.2 |
Work Order | 00-00-00 |
Work Began | 12-27-23 |
Work Completed | |
Time Computed | 12-11-23 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 79 |
Percent Time Used | 21 |
Contractor(s) |
ABOVE ALL CONSTRUCTION |
SUBCONTRACTOR(S) FOR CCSJ: 6449-33-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10234020 |
| Totals | 385249.00 | 47326.00 | 47327.00 | 12.2 |
|
County | FORT BEND |
Highway | US0059 |
From | VARIOUS HIGHWAYS IN FORT BEND COUNTY |
To | VARIOUS HIGHWAYS IN FORT BEND COUNTY |
CSJ | 6449-37-001 |
Proj ID | RMC - 644937001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 799234.00 | | 29273.00 | 3.6 |
Work Order | 00-00-00 |
Work Began | 02-01-24 |
Work Completed | |
Time Computed | 02-01-24 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 25 |
Percent Time Used | 6 |
Contractor(s) |
ROSS SA ENTERPRISE LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6449-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234213 |
| Totals | 799234.00 | 29273.00 | 29273.00 | 3.6 |
|
County | FORT BEND |
Highway | US0059 |
From | VARIOUS HIGHWAYS IN FORT BEND COUNTY |
To | VARIOUS HIGHWAYS IN FORT BEND COUNTY |
CSJ | 6449-75-001 |
Proj ID | RMC - 644975001 |
Work Type | CLEANING AND SWEEPING HIGHWAYS |
|
| 0.010 | 1148521.20 | | 67017.50 | 5.8 |
Work Order | 00-00-00 |
Work Began | 02-01-24 |
Work Completed | |
Time Computed | 02-01-24 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 25 |
Percent Time Used | 6 |
Contractor(s) |
SWEEPING CORPORATION OF AMERICA, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6449-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234020 |
| Totals | 1148521.20 | 67017.50 | 67017.50 | 5.8 |
|
County | MONTGOMERY |
Highway | IH0045 |
From | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
To | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
CSJ | 6450-17-001 |
Proj ID | RMC - 645017001 |
Work Type | DELINEATOR, OBJ MRK & MAILBOX MAINT |
|
| 0.010 | 653818.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6450-17-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244013 |
| Totals | 653818.00 | 0.00 | 0.00 | 0.0 |
|
County | MONTGOMERY |
Highway | IH0045 |
From | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
To | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
CSJ | 6450-19-001 |
Proj ID | RMC - 645019001 |
Work Type | ASPHALT PAVEMENT REPAIR |
|
| 0.010 | 1525300.00 | | 66748.46 | 4.3 |
Work Order | 02-01-24 |
Work Began | 02-01-24 |
Work Completed | |
Time Computed | 02-01-24 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 25 |
Percent Time Used | 3 |
Contractor(s) |
FORDE CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6450-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234021 |
| Totals | 1525300.00 | 66748.46 | 66748.46 | 4.3 |
|
County | MONTGOMERY |
Highway | IH0045 |
From | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
To | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
CSJ | 6450-21-001 |
Proj ID | RMC - 645021001 |
Work Type | SMALL SIGN REPLACEMENT |
|
| 0.010 | 1335530.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 03-01-24 |
Work Began | 03-01-24 |
Work Completed | |
Time Computed | 03-01-24 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
HAZMAT INTERNATIONAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6450-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244021 |
| Totals | 1335530.00 | 0.00 | 0.00 | 0.0 |
|
County | MONTGOMERY |
Highway | IH0045 |
From | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
To | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
CSJ | 6450-27-001 |
Proj ID | RMC - 645027001 |
Work Type | TREE TRIMMING AND BRUSH REMOVAL |
|
| 0.010 | 818950.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 03-01-24 |
Work Began | 03-01-24 |
Work Completed | |
Time Computed | 03-01-24 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
SHALOM SERVICES CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 6450-27-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234034 |
| Totals | 818950.00 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | SH0249 |
From | SH 249 ETC VARIOUS LOCATIONS |
To | SH 249 ETC VARIOUS LOCATIONS |
CSJ | 6450-37-001 |
Proj ID | RMC - 645037001 |
Work Type | FULL DEPTH CONCRETE REPAIR |
|
| 0.010 | 3156875.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MC2 CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6450-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244211 |
| Totals | 3156875.00 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | IH0069 |
From | VARIOUS LOCATIONS IN N. HARRIS COUNTY |
To | VARIOUS LOCATIONS IN N. HARRIS COUNTY |
CSJ | 6452-11-001 |
Proj ID | RMC - 645211001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 484669.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-21-24 |
Work Completed | |
Time Computed | 02-21-24 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6452-11-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234214 |
| Totals | 484669.00 | 0.00 | 0.00 | 0.0 |
|
County | GALVESTON |
Highway | FM1764 |
From | VARIOUS HWYS IN GALVESTON COUNTY |
To | VARIOUS HWYS IN GALVESTON COUNTY |
CSJ | 6454-15-001 |
Proj ID | RMC - 645415001 |
Work Type | CLEANING AND SWEEPING HIGHWAYS |
|
| 0.010 | 1195115.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
SWEEPING CORPORATION OF AMERICA, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6454-15-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244014 |
| Totals | 1195115.00 | 0.00 | 0.00 | 0.0 |
|
County | FORT BEND |
Highway | US0059 |
From | VARIOUS HIGHWAYS IN FORT BEND COUNTY |
To | VARIOUS HIGHWAYS IN FORT BEND COUNTY |
CSJ | 6454-76-001 |
Proj ID | RMC - 645476001 |
Work Type | BRIDGE DECK REPAIR |
|
| 0.010 | 368000.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 03-01-24 |
Work Completed | |
Time Computed | 03-01-24 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6454-76-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244023 |
| Totals | 368000.00 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | SL0008 |
From | VARIOUS HWYS IN SOUTHEAST HARRIS COUNTY |
To | VARIOUS HWYS IN SOUTHEAST HARRIS COUNTY |
CSJ | 6455-75-001 |
Proj ID | RMC - 645575001 |
Work Type | PUMP STATION & DRAINAGE SYSTEM CLEANING |
|
| 0.010 | 292130.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
AIMS COMPANIES |
SUBCONTRACTOR(S) FOR CCSJ: 6455-75-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244024 |
| Totals | 292130.00 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | SL0008 |
From | VARIOUS HWYS IN SOUTHEAST HARRIS COUNTY |
To | VARIOUS HWYS IN SOUTHEAST HARRIS COUNTY |
CSJ | 6456-47-001 |
Proj ID | RMC - 645647001 |
Work Type | REFLECTIVE PAVEMENT MARKINGS (GRAPHICS) |
|
| 0.010 | 1085389.90 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6456-47-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244212 |
| Totals | 1085389.90 | 0.00 | 0.00 | 0.0 |
|
County | HARRIS |
Highway | IH0069 |
From | IH 69, ETC. VARIOUS ROADWAYS N. HARRIS |
To | IH 69, ETC. VARIOUS ROADWAYS N. HARRIS |
CSJ | 6457-09-001 |
Proj ID | RMC - 645709001 |
Work Type | SWEEPING AND DEBRIS REMOVAL |
|
| 0.010 | 1835440.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MBN ENTERPRISES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6457-09-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244209 |
| Totals | 1835440.00 | 0.00 | 0.00 | 0.0 |
|
County | MONTGOMERY |
Highway | IH0045 |
From | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
To | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
CSJ | 6457-33-001 |
Proj ID | RMC - 645733001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 1336286.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
HAZMAT INTERNATIONAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6457-33-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244015 |
| Totals | 1336286.00 | 0.00 | 0.00 | 0.0 |
|
County | MONTGOMERY |
Highway | IH0045 |
From | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
To | VARIOUS HIGHWAYS IN MONTGOMERY COUNTY |
CSJ | 6457-37-001 |
Proj ID | RMC - 645737001 |
Work Type | CLEANING AND SWEEPING HIGHWAYS |
|
| 0.010 | 659840.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
PROFESSIONAL TRAFFIC CONTROL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6457-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244215 |
| Totals | 659840.00 | 0.00 | 0.00 | 0.0 |
|
County | GALVESTON |
Highway | FM0518 |
From | VARIOUS HWYS IN GALVESTON COUNTY |
To | VARIOUS HWYS IN GALVESTON COUNTY |
CSJ | 6459-43-001 |
Proj ID | RMC - 645943001 |
Work Type | FULL DEPTH CONCRETE REPAIR |
|
| 0.010 | 394005.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 03-04-24 |
Contract Working Days | 366 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6459-43-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244213 |
| Totals | 394005.00 | 0.00 | 0.00 | 0.0 |
|