Monthly State Let Maintenance Report For Lubbock District As Of Mar 13, 2024 Page 1 Of 3

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLUBBOCK
Highway0000000
From135 E SLATON RD
ToLUBBOCK TX
CSJ4704-01-553
Proj IDCBC - 470401553
Work TypeRENOVATION OR REPAIR
 
0.001246439.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLYNN SOUTHWEST LP
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-553
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164218
Totals246439.000.000.000.0

CountyLAMB
Highway0000000
From1600 WEST DELANO
ToLITTLEFIELD TX 79339
CSJ4704-01-774
Proj IDCBC - 470401774
Work TypeRENOVATION OR REPAIR
 
0.001273550.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLYNN SOUTHWEST LP
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-774
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164229
Totals273550.000.000.000.0

CountyLUBBOCK
HighwaySL0289
FromVARIOUS
ToVARIOUS
CSJ6267-07-001
Proj IDRMC - 626707001
Work TypeHOT MIX MILL AND INLAY
 
0.5001999567.710.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06144201
Totals1999567.710.000.000.0

CountyFLOYD
HighwayUS0062
FromVARIOUS LOCATIONS IN
ToTHE LUBBOCK DISTRICT
CSJ6271-00-001
Proj IDRMC - 627100001
Work TypePAVEMENT TEXTURING
 
0.001102387.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days123
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04140501
Totals102387.900.000.000.0

CountyLUBBOCK
HighwaySL0289
FromVARIOUS LOCATIONS
ToIN LUBBOCK COUNTY
CSJ6277-62-001
Proj IDRMC - 627762001
Work TypePM
 
0.5001371551.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10144004
Totals1371551.120.000.000.0

CountyLAMB
HighwayFM0037
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6380-18-001
Proj IDRMC - 638018001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010467330.80794729.7399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-26-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted730
Working Days Charged805
Percent Time Used55
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6380-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05214015
Totals467330.800.00794729.7399.9

CountyBAILEY
HighwayFM0037
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6380-19-001
Proj IDRMC - 638019001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010490776.32633418.5199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-19-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted730
Working Days Charged811
Percent Time Used55
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6380-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05214016
Totals490776.320.00633418.5199.9

CountyLUBBOCK
HighwayIH0027
FromVARIOUS
ToVARIOUS
CSJ6389-47-001
Proj IDRMC - 638947001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010409444.00402844.0098.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted730
Working Days Charged759
Percent Time Used51
Contractor(s)
GORMAN OUTDOOR, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6389-47-001
TEXAS BLACKTOPS LLC (0.00)
Contract #11214021
Totals409444.000.00402844.0098.3

CountyLUBBOCK
HighwaySL0289
FromVARIOUS
ToVARIOUS
CSJ6389-48-001
Proj IDRMC - 638948001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010261944.00252444.0096.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted730
Working Days Charged759
Percent Time Used51
Contractor(s)
GORMAN OUTDOOR, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6389-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11214022
Totals261944.000.00252444.0096.3

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6390-58-001
Proj IDRMC - 639058001
Work TypePAVEMENT MARKINGS
 
0.0101031724.001171911.2999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-16-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted730
Working Days Charged734
Percent Time Used50
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6390-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214018
Totals1031724.000.001171911.2999.9

CountyGARZA
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6393-21-001
Proj IDRMC - 639321001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010807756.00810603.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-19-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted730
Working Days Charged652
Percent Time Used44
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6393-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224013
Totals807756.000.00810603.0099.9

CountyPARMER
HighwayUS0060
FromVARIOUS
ToVARIOUS
CSJ6393-22-001
Proj IDRMC - 639322001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010774676.00756242.5697.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6393-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224014
Totals774676.000.00756242.5697.6

CountyCROSBY
HighwayUS0062
FromVARIOUS
ToVARIOUS
CSJ6396-18-001
Proj IDRMC - 639618001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010816252.00588989.0072.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged547
Percent Time Used74
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224214
Totals816252.000.00588989.0072.1

CountySWISHER
HighwayIH0027
FromVARIOUS
ToVARIOUS
CSJ6396-19-001
Proj IDRMC - 639619001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010566152.00424234.0074.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged549
Percent Time Used75
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224215
Totals566152.000.00424234.0074.9

CountyGARZA
HighwayUS0084
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6404-94-001
Proj IDRMC - 640494001
Work TypeREHABILITATION OF EXISTING ROADWAY
 
0.010748760.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6404-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244001
Totals748760.500.000.000.0

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6410-72-001
Proj IDBPM - 641072001
Work TypeBRIDGE REPAIR
 
0.0101197424.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days279
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6410-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234215
Totals1197424.000.000.000.0

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6413-05-001
Proj IDMMC - 641305001
Work TypeHOT MIX
 
0.010694694.00687465.69100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-22
Work Completed10-26-23
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged359
Percent Time Used99
Contractor(s)
WEST TEXAS PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224032
Totals694694.000.00687465.69100.0

CountyTERRY
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6432-26-001
Proj IDRMC - 643226001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101154459.00905419.0078.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-17-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged319
Percent Time Used87
Contractor(s)
FC TRAFFIC CONTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6432-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234042
Totals1154459.0060880.00905419.0078.4

CountyLAMB
HighwayUS0084
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6432-28-001
Proj IDRMC - 643228001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010450436.00187030.0041.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-17-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged319
Percent Time Used87
Contractor(s)
FC TRAFFIC CONTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6432-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234043
Totals450436.006530.00187030.0041.5

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6432-30-001
Proj IDRMC - 643230001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101485576.001441578.2097.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-17-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged319
Percent Time Used43
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6432-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234227
Totals1485576.00127328.441441578.2097.0

page 1 | page 2 | page 3