Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | LUBBOCK |
Highway | 0000000 |
From | 135 E SLATON RD |
To | LUBBOCK TX |
CSJ | 4704-01-553 |
Proj ID | CBC - 470401553 |
Work Type | RENOVATION OR REPAIR |
|
| 0.001 | 246439.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 90 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
FLYNN SOUTHWEST LP |
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-553 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08164218 |
| Totals | 246439.00 | 0.00 | 0.00 | 0.0 |
|
County | LAMB |
Highway | 0000000 |
From | 1600 WEST DELANO |
To | LITTLEFIELD TX 79339 |
CSJ | 4704-01-774 |
Proj ID | CBC - 470401774 |
Work Type | RENOVATION OR REPAIR |
|
| 0.001 | 273550.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 90 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
FLYNN SOUTHWEST LP |
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-774 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10164229 |
| Totals | 273550.00 | 0.00 | 0.00 | 0.0 |
|
County | LUBBOCK |
Highway | SL0289 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6267-07-001 |
Proj ID | RMC - 626707001 |
Work Type | HOT MIX MILL AND INLAY |
|
| 0.500 | 1999567.71 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 67 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ALLEN BUTLER CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6267-07-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06144201 |
| Totals | 1999567.71 | 0.00 | 0.00 | 0.0 |
|
County | FLOYD |
Highway | US0062 |
From | VARIOUS LOCATIONS IN |
To | THE LUBBOCK DISTRICT |
CSJ | 6271-00-001 |
Proj ID | RMC - 627100001 |
Work Type | PAVEMENT TEXTURING |
|
| 0.001 | 102387.90 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 123 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TOTAL HIGHWAY MAINTENANCE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6271-00-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04140501 |
| Totals | 102387.90 | 0.00 | 0.00 | 0.0 |
|
County | LUBBOCK |
Highway | SL0289 |
From | VARIOUS LOCATIONS |
To | IN LUBBOCK COUNTY |
CSJ | 6277-62-001 |
Proj ID | RMC - 627762001 |
Work Type | PM |
|
| 0.500 | 1371551.12 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 51 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ALLEN BUTLER CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6277-62-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10144004 |
| Totals | 1371551.12 | 0.00 | 0.00 | 0.0 |
|
County | LAMB |
Highway | FM0037 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6380-18-001 |
Proj ID | RMC - 638018001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 467330.80 | | 794729.73 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 07-26-21 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 805 |
Percent Time Used | 55 |
Contractor(s) |
BERT WHITAKER |
SUBCONTRACTOR(S) FOR CCSJ: 6380-18-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05214015 |
| Totals | 467330.80 | 0.00 | 794729.73 | 99.9 |
|
County | BAILEY |
Highway | FM0037 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6380-19-001 |
Proj ID | RMC - 638019001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 490776.32 | | 633418.51 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-19-21 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 811 |
Percent Time Used | 55 |
Contractor(s) |
CM COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 6380-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05214016 |
| Totals | 490776.32 | 0.00 | 633418.51 | 99.9 |
|
County | LUBBOCK |
Highway | IH0027 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6389-47-001 |
Proj ID | RMC - 638947001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 409444.00 | | 402844.00 | 98.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 759 |
Percent Time Used | 51 |
Contractor(s) |
GORMAN OUTDOOR, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6389-47-001 TEXAS BLACKTOPS LLC (0.00)
|
Contract # | 11214021 |
| Totals | 409444.00 | 0.00 | 402844.00 | 98.3 |
|
County | LUBBOCK |
Highway | SL0289 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6389-48-001 |
Proj ID | RMC - 638948001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 261944.00 | | 252444.00 | 96.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 759 |
Percent Time Used | 51 |
Contractor(s) |
GORMAN OUTDOOR, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6389-48-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11214022 |
| Totals | 261944.00 | 0.00 | 252444.00 | 96.3 |
|
County | LUBBOCK |
Highway | IH0027 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6390-58-001 |
Proj ID | RMC - 639058001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 1031724.00 | | 1171911.29 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-16-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 734 |
Percent Time Used | 50 |
Contractor(s) |
TEXAS PANHANDLE CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6390-58-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10214018 |
| Totals | 1031724.00 | 0.00 | 1171911.29 | 99.9 |
|
County | GARZA |
Highway | US0084 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6393-21-001 |
Proj ID | RMC - 639321001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 807756.00 | | 810603.00 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-19-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 652 |
Percent Time Used | 44 |
Contractor(s) |
TEXAS BLACKTOPS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6393-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02224013 |
| Totals | 807756.00 | 0.00 | 810603.00 | 99.9 |
|
County | PARMER |
Highway | US0060 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6393-22-001 |
Proj ID | RMC - 639322001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 774676.00 | | 756242.56 | 97.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 639 |
Percent Time Used | 87 |
Contractor(s) |
CM COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 6393-22-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02224014 |
| Totals | 774676.00 | 0.00 | 756242.56 | 97.6 |
|
County | CROSBY |
Highway | US0062 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6396-18-001 |
Proj ID | RMC - 639618001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 816252.00 | | 588989.00 | 72.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 547 |
Percent Time Used | 74 |
Contractor(s) |
CROSS PLUS CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6396-18-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03224214 |
| Totals | 816252.00 | 0.00 | 588989.00 | 72.1 |
|
County | SWISHER |
Highway | IH0027 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6396-19-001 |
Proj ID | RMC - 639619001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 566152.00 | | 424234.00 | 74.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 549 |
Percent Time Used | 75 |
Contractor(s) |
CROSS PLUS CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6396-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03224215 |
| Totals | 566152.00 | 0.00 | 424234.00 | 74.9 |
|
County | GARZA |
Highway | US0084 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6404-94-001 |
Proj ID | RMC - 640494001 |
Work Type | REHABILITATION OF EXISTING ROADWAY |
|
| 0.010 | 748760.50 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 60 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
DIGG COMMERCIAL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6404-94-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244001 |
| Totals | 748760.50 | 0.00 | 0.00 | 0.0 |
|
County | LUBBOCK |
Highway | IH0027 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6410-72-001 |
Proj ID | BPM - 641072001 |
Work Type | BRIDGE REPAIR |
|
| 0.010 | 1197424.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 279 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TI-ZACK CONCRETE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6410-72-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234215 |
| Totals | 1197424.00 | 0.00 | 0.00 | 0.0 |
|
County | LUBBOCK |
Highway | IH0027 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6413-05-001 |
Proj ID | MMC - 641305001 |
Work Type | HOT MIX |
|
| 0.010 | 694694.00 | | 687465.69 | 100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 11-01-22 |
Work Completed | 10-26-23 |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 240 |
Working Days Charged | 359 |
Percent Time Used | 99 |
Contractor(s) |
WEST TEXAS PAVING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6413-05-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08224032 |
| Totals | 694694.00 | 0.00 | 687465.69 | 100.0 |
|
County | TERRY |
Highway | US0062 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6432-26-001 |
Proj ID | RMC - 643226001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 1154459.00 | | 905419.00 | 78.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-17-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 319 |
Percent Time Used | 87 |
Contractor(s) |
FC TRAFFIC CONTROL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6432-26-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02234042 |
| Totals | 1154459.00 | 60880.00 | 905419.00 | 78.4 |
|
County | LAMB |
Highway | US0084 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6432-28-001 |
Proj ID | RMC - 643228001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 450436.00 | | 187030.00 | 41.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-17-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 319 |
Percent Time Used | 87 |
Contractor(s) |
FC TRAFFIC CONTROL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6432-28-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02234043 |
| Totals | 450436.00 | 6530.00 | 187030.00 | 41.5 |
|
County | LUBBOCK |
Highway | IH0027 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6432-30-001 |
Proj ID | RMC - 643230001 |
Work Type | TRAFFIC CONTROL SERVICES |
|
| 0.010 | 1485576.00 | | 1441578.20 | 97.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-17-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 319 |
Percent Time Used | 43 |
Contractor(s) |
BARRICADES UNLIMITED |
SUBCONTRACTOR(S) FOR CCSJ: 6432-30-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02234227 |
| Totals | 1485576.00 | 127328.44 | 1441578.20 | 97.0 |
|