Monthly State Let Maintenance Report For Lubbock District As Of Apr 12, 2024 Page 3 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHALE
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6448-13-001
Proj IDRMC - 644813001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010249070.00280568.2099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6448-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234212
Totals249070.0064284.40280568.2099.9

CountyLUBBOCK
HighwayIH0027
FromVARIOUS
ToVARIOUS
CSJ6451-53-001
Proj IDRMC - 645153001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010372420.0059070.0015.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-18-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged105
Percent Time Used14
Contractor(s)
MARLANE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6451-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234213
Totals372420.000.0059070.0015.8

CountyLUBBOCK
HighwayFM2255
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6451-55-001
Proj IDRMC - 645155001
Work TypeCULVERT REPAIR
 
0.010258006.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6451-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244008
Totals258006.800.000.000.0

CountyTERRY
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6455-63-001
Proj IDMMC - 645563001
Work TypeAGGREGATE
 
0.010506000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged60
Percent Time Used33
Contractor(s)
WEST TEXAS PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234210
Totals506000.000.000.000.0

CountyLAMB
HighwayUS0084
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6455-65-001
Proj IDMMC - 645565001
Work TypeAGGREGATE
 
0.01092000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged60
Percent Time Used33
Contractor(s)
WEST TEXAS PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234211
Totals92000.000.000.000.0

CountyHALE
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6455-67-001
Proj IDMMC - 645567001
Work TypeAGGREGATE
 
0.010399280.00187412.4546.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged60
Percent Time Used33
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234212
Totals399280.00187412.45187412.4546.9

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6458-39-001
Proj IDMMC - 645839001
Work TypeHOT MIX
 
0.010704000.00943578.8599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged60
Percent Time Used33
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6458-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234035
Totals704000.00943578.85943578.8599.9

CountyTERRY
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6458-75-001
Proj IDRMC - 645875001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010312124.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6458-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244214
Totals312124.320.000.000.0

CountyDAWSON
HighwayUS0087
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6458-77-001
Proj IDRMC - 645877001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010319620.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6458-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244215
Totals319620.000.000.000.0

CountyGAINES
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6458-79-001
Proj IDRMC - 645879001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010569820.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6458-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244216
Totals569820.000.000.000.0

CountyGARZA
HighwayUS0084
FromRDC
ToRDC
CSJ6462-87-001
Proj IDMMC - 646287001
Work TypeDE-ICING SALT
 
0.010255645.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244217
Totals255645.000.000.000.0

CountyTERRY
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6464-97-001
Proj IDMMC - 646497001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010911200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6464-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244031
Totals911200.000.000.000.0

CountyLAMB
HighwayUS0084
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6464-98-001
Proj IDMMC - 646498001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010845995.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6464-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244032
Totals845995.000.000.000.0

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6464-99-001
Proj IDMMC - 646499001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010307910.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6464-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244033
Totals307910.000.000.000.0

CountyHALE
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6465-00-001
Proj IDMMC - 646500001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010818740.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6465-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244034
Totals818740.000.000.000.0

CountyLUBBOCK
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6465-04-001
Proj IDMMC - 646504001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010173840.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6465-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244219
Totals173840.000.000.000.0

CountyLAMB
HighwayUS0084
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6465-05-001
Proj IDMMC - 646505001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010433600.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6465-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244220
Totals433600.000.000.000.0

CountyHALE
HighwayIH0027
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6465-06-001
Proj IDMMC - 646506001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010416025.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6465-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244221
Totals416025.000.000.000.0