Monthly Local Let Maintenance Report For Lufkin District As Of Aug 23, 2019 Page 1 Of 6

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN AUGUSTINE
HighwayUS0096
FromUS 96 & VARIOUS LOCATIONS WITHIN
ToSAN AUGUSTINE MAINT SECTION
CSJ6243-02-001
Proj IDSUP - 624302001
Work TypePICNIC/GROUNDS/CURB AND GUTTER MAINT
 
0.01086588.8057479.6066.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-17-12
Work Began07-01-12
Work Completed
Time Computed07-01-12
Contract Working Days250
Addl Days Granted0
Working Days Charged151
Percent Time Used60
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6243-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04121131
Totals86588.800.0057479.6066.3

CountySAN AUGUSTINE
HighwayUS0096
FromUS 96 & VARIOUS LOCATINS WITHIN
ToSAN AUGUSTINE MAINT SECTION
CSJ6243-89-001
Proj IDSUP - 624389001
Work TypeLITTER PICKUP MAINTENANCE
 
0.010261391.74257418.6398.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-07-12
Work Began08-01-12
Work Completed
Time Computed08-01-12
Contract Working Days190
Addl Days Granted0
Working Days Charged109
Percent Time Used57
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6243-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05121136
Totals261391.740.00257418.6398.4

CountyNACOGDOCHES
HighwayUS0059
FromUS 59 & VARIOUS LOCATIONS WITHIN
ToNACOGDOCHES MAINT SECTION
CSJ6244-23-001
Proj IDSUP - 624423001
Work TypeLITTER PICKUP MAINTENANCE
 
0.010208704.36151515.7872.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-12
Work Began08-01-12
Work Completed
Time Computed08-01-12
Contract Working Days190
Addl Days Granted0
Working Days Charged115
Percent Time Used60
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6244-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05121138
Totals208704.360.00151515.7872.5

CountyTRINITY
HighwaySH0019
FromSH 19 AND VARIOUS ROADWAYS
ToIN TRINITY COUNTY
CSJ6261-02-001
Proj IDSUP - 626102001
Work TypeLITTER PICKUP
 
0.01058785.2835917.2761.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-13
Work Began08-01-13
Work Completed
Time Computed08-01-13
Contract Working Days190
Addl Days Granted0
Working Days Charged52
Percent Time Used27
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6261-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07131132
Totals58785.280.0035917.2761.0

CountySAN JACINTO
HighwayUS0059
FromUS 59 AND VARIOUS ROADWAYS
ToIN SAN JACINTO COUNTY
CSJ6261-11-001
Proj IDSUP - 626111001
Work TypeLITTER PICKUP
 
0.010141236.34110183.5578.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-13
Work Began08-01-13
Work Completed
Time Computed08-01-13
Contract Working Days190
Addl Days Granted0
Working Days Charged118
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6261-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07131134
Totals141236.340.00110183.5578.0

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS IN
ToSAN AUGUSTINE COUNTY
CSJ6261-33-001
Proj IDSUP - 626133001
Work TypeREM/REPL DEL POST/OBJ MRK, MAILBOX UGRD/
 
0.100100000.0097002.0097.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-13
Work Began07-01-13
Work Completed
Time Computed07-01-13
Contract Working Days150
Addl Days Granted0
Working Days Charged100
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06131141
Totals100000.000.0097002.0097.0

CountyANGELINA
HighwayBU0059
From1805 N. TIMBERLAND DR.
ToLUFKIN, TX
CSJ6261-53-001
Proj IDSUP - 626153001
Work TypeGROUNDS MAINT AT LUFKIN DIST. COMPLEX
 
0.01025400.0013335.0052.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-13
Work Began07-01-13
Work Completed
Time Computed07-01-13
Contract Working Days150
Addl Days Granted0
Working Days Charged21
Percent Time Used14
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06131132
Totals25400.000.0013335.0052.5

CountyANGELINA
HighwayUS0069
FromLOCATED WITHIN THE LUFKIN STATE
ToSUPPORTED LIVING CENTER ON US 69
CSJ6273-13-001
Proj IDRMC - 627313001
Work TypeSEAL COAT, REHAB & MISC. CONSTRUCTION
 
0.010164328.00157822.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-17-15
Work Completed09-21-15
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged24
Percent Time Used60
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151104
Totals164328.000.00157822.00100.0

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS WITHIN
ToSHELBY COUNTY
CSJ6275-22-001
Proj IDSUP - 627522001
Work TypeMAILBOX AND DELINEATOR MAINTENANCE
 
0.0100.0056420.130.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-14
Work Began07-01-14
Work Completed06-30-15
Time Computed07-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged343
Percent Time Used93
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06141139
Totals0.000.0056420.130.0

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToPOLK COUNTY
CSJ6288-65-001
Proj IDRMC - 628865001
Work TypeGUARD FENCE, ATTENUATOR & MTL RAIL REPR
 
0.010199473.00390748.3099.9
Work Order05-09-16
Work Began05-16-16
Work Completed
Time Computed05-16-16
Contract Working Days200
Addl Days Granted200
Working Days Charged104
Percent Time Used26
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6288-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161101
Totals199473.001790.00390748.3099.9

CountySHELBY
HighwayFM0414
From0.89 MILES NORTHEAST OF SH 87 ON THE
ToSOUTH SIDE OF FM 414
CSJ6301-55-001
Proj IDRMC - 630155001
Work TypeCULVERT INSTALLATION
 
0.010109175.00120789.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began07-26-16
Work Completed01-31-17
Time Computed07-18-16
Contract Working Days25
Addl Days Granted0
Working Days Charged25
Percent Time Used100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161101
Totals109175.000.00120789.00100.0

CountyNACOGDOCHES
HighwaySH0007
FromVARIOUS LOCATIONS WITHIN_THE
ToNACOGDOCHES COUNTY MAINTENANCE SECTION
CSJ6301-57-001
Proj IDRMC - 630157001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010190750.00341263.0099.9
Work Order11-30-16
Work Began12-02-16
Work Completed
Time Computed12-02-16
Contract Working Days200
Addl Days Granted0
Working Days Charged51
Percent Time Used25
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161106
Totals190750.0012736.00341263.0099.9

CountyANGELINA
HighwayUS0069
FromVARIOUS LOCATIONS THROUGHOUT ANGELINA
ToCOUNTY
CSJ6304-03-001
Proj IDRMC - 630403001
Work TypeANGELINA COUNTY MBGF
 
0.010272863.30528065.0099.9
Work Order07-29-16
Work Began08-11-16
Work Completed
Time Computed08-01-16
Contract Working Days200
Addl Days Granted200
Working Days Charged71
Percent Time Used17
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161104
Totals272863.3029107.50528065.0099.9

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN NACOGDOCHES
ToCOUNTY
CSJ6304-40-001
Proj IDRMC - 630440001
Work TypeTREE REMOVAL
 
0.010108750.00438800.0099.9
Work Order08-16-16
Work Began09-06-16
Work Completed
Time Computed09-06-16
Contract Working Days200
Addl Days Granted200
Working Days Charged143
Percent Time Used35
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6304-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161105
Totals108750.000.00438800.0099.9

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN THE
ToSAN AUGUSTINE COUNTY MAINTENANCE SECTION
CSJ6309-68-001
Proj IDRMC - 630968001
Work TypeGUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010146806.0077516.5052.8
Work Order00-00-00
Work Began01-26-17
Work Completed
Time Computed01-26-17
Contract Working Days200
Addl Days Granted0
Working Days Charged16
Percent Time Used8
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161109
Totals146806.0012118.5077516.5052.8

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK COUNTY
ToMAINTENANCE SECTION
CSJ6315-48-001
Proj IDRMC - 631548001
Work TypeTREE & BRUSH REMOVAL AND TREE TRIMMING
 
0.010217735.00299791.0099.9
Work Order12-04-17
Work Began12-01-17
Work Completed
Time Computed12-01-17
Contract Working Days200
Addl Days Granted200
Working Days Charged157
Percent Time Used39
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6315-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171103
Totals217735.0010465.00299791.0099.9

CountySAN AUGUSTINE
HighwaySH0103
FromVARIOUS LOCATIONS IN SAN AUGUSTINE
ToCOUNTY MAINTENANCE SECTION
CSJ6315-93-001
Proj IDRMC - 631593001
Work TypeTREE & BRUSH REMOVAL
 
0.010209120.0083795.0040.0
Work Order00-00-00
Work Began01-01-18
Work Completed
Time Computed01-01-18
Contract Working Days200
Addl Days Granted0
Working Days Charged30
Percent Time Used15
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6315-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171101
Totals209120.000.0083795.0040.0

CountySABINE
HighwaySH0021
FromVARIOUS LOCATIONS IN SABINE COUNTY
ToMAINTENANCE SECTION
CSJ6316-67-001
Proj IDRMC - 631667001
Work TypeTREE & BRUSH REMOVAL AND TREE TRIMMING
 
0.010251150.00259849.0099.9
Work Order10-06-17
Work Began11-06-17
Work Completed
Time Computed11-01-17
Contract Working Days200
Addl Days Granted0
Working Days Charged143
Percent Time Used71
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6316-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171102
Totals251150.0010881.00259849.0099.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN ANGELINA COUNTY
ToMAINTENANCE SECTION
CSJ6318-76-001
Proj IDRMC - 631876001
Work TypeHIGH EDGE REMOVAL
 
0.010197500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171105
Totals197500.000.000.000.0

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN THE SAN JACINTO
ToCOUNTY MAINTENANCE SECTION
CSJ6318-77-001
Proj IDRMC - 631877001
Work TypeCULVERT AND DITCH CLEANING
 
0.010222810.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&S EXCAVATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171107
Totals222810.000.000.000.0