Monthly State Let Maintenance Report For Lufkin District As Of Aug 23, 2019 Page 1 Of 1

Last Update: Friday, August 23, 2019
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPOLK
HighwayUS0059
FromVARIOUS ROADWAYS IN POLK AND
ToSAN JACINTO MAINTENANCE SECTIONS
CSJ6328-44-001
Proj IDRMC - 632844001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001804600.00279295.0034.7
Work Order07-12-18
Work Began07-12-18
Work Completed
Time Computed07-12-18
Contract Working Days365
Addl Days Granted117
Working Days Charged385
Percent Time Used79
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6328-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184209
Totals804600.0023225.00279295.0034.7

CountyANGELINA
HighwayUS0059
FromVARIOUS ROADWAYS IN ANGELINA,
ToHOUSTON AND TRINITY MAINT_SECTIONS
CSJ6328-45-001
Proj IDRMC - 632845001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.0011082969.021262359.4299.9
Work Order06-04-18
Work Began06-15-18
Work Completed
Time Computed07-01-18
Contract Working Days365
Addl Days Granted365
Working Days Charged412
Percent Time Used56
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6328-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184210
Totals1082969.02159953.051262359.4299.9

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS ROADWAYS IN NACOGDOCHES,SABINE,
ToSAN AUGUSTINE AND SHELBY MAINT SECTIONS
CSJ6328-46-001
Proj IDRMC - 632846001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.0011083773.08868282.90100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-18
Work Completed07-01-19
Time Computed07-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6328-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184008
Totals1083773.080.00868282.90100.0

CountyTRINITY
HighwaySH0019
FromVARIOUS LOCATIONS IN ANGELINA,
ToTRINITY AND SHELBY COUNTIES
CSJ6333-93-001
Proj IDRMC - 633393001
Work TypeMILL AND INLAY
 
0.0101470447.621343254.1892.2
Work Order03-07-19
Work Began03-18-19
Work Completed
Time Computed03-18-19
Contract Working Days30
Addl Days Granted0
Working Days Charged49
Percent Time Used163
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6333-93-001
MOORE BROTHERS CONSTRUCTION COMPANY (41.19)
DUSTROL, INC. (3.05)
TEXOP CONSTRUCTION (3.26)
BATTERSON,LLP (3.73)
Contract #10184007
Totals1470447.6212900.001343254.1892.2

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN HOUSTON, POLK
ToAND SAN JACINTO COUNTIES
CSJ6333-94-001
Proj IDRMC - 633394001
Work TypeMILL AND INLAY
 
0.0101388699.481254381.0390.3
Work Order00-00-00
Work Began03-15-19
Work Completed
Time Computed03-15-19
Contract Working Days30
Addl Days Granted0
Working Days Charged24
Percent Time Used80
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6333-94-001
SMITH & COMPANY (19.29)
TEXOP CONSTRUCTION (1.38)
STRIPING TECHNOLOGY, L.P. (3.81)
DUSTROL, INC. (6.73)
Contract #10184204
Totals1388699.480.001254381.0390.3

CountySABINE
HighwayFM0001
FromVARIOUS LOCATIONS
ToWITHIN THE LUFKIN DISTRICT
CSJ6337-96-001
Proj IDBPM - 633796001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010717347.00652175.6492.2
Work Order02-20-19
Work Began03-29-19
Work Completed
Time Computed03-04-19
Contract Working Days40
Addl Days Granted10
Working Days Charged66
Percent Time Used132
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6337-96-001
DRS CONSTRUCTION, INC. (0.00)
Contract #12184215
Totals717347.008443.14652175.6492.2

CountyNACOGDOCHES
HighwaySH0007
FromLOCATIONS ALONG SH 7 IN NACOGDOCHES
ToMAINTENANCE SECTION
CSJ6339-31-001
Proj IDRMC - 633931001
Work TypeUPGRADING MBGF
 
0.010413947.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6339-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08194207
Totals413947.000.000.000.0

CountySHELBY
HighwayUS0059
FromVARIOUS LOACTIONS IN ANGELINA
ToNACOGDOCHES AND SHELBY COUNTIES
CSJ6347-64-001
Proj IDRMC - 634764001
Work TypeMILL AND INLAY
 
0.010939778.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6347-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08194211
Totals939778.320.000.000.0

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN SAN JACINTO
ToHOUSTON, POLK AND TRINITY COUNTIES
CSJ6347-65-001
Proj IDRMC - 634765001
Work TypeMILL AND INLAY
 
0.0101998581.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6347-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08194209
Totals1998581.240.000.000.0

page 1