Monthly State Let Maintenance Report For Lufkin District As Of Jan 16, 2020 Page 1 Of 1

Last Update: Friday, January 17, 2020
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANGELINA
HighwayUS0059
FromVARIOUS ROADWAYS IN ANGELINA,
ToHOUSTON AND TRINITY MAINT_SECTIONS
CSJ6328-45-001
Proj IDRMC - 632845001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.0011082969.021810748.8999.9
Work Order06-04-18
Work Began06-15-18
Work Completed
Time Computed07-01-18
Contract Working Days365
Addl Days Granted365
Working Days Charged565
Percent Time Used77
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6328-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184210
Totals1082969.0286082.891810748.8999.9

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS
ToWITHIN THE LUFKIN DISTRICT
CSJ6337-05-001
Proj IDBPM - 633705001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010718542.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6337-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194216
Totals718542.000.000.000.0

CountyNACOGDOCHES
HighwaySH0007
FromLOCATIONS ALONG SH 7 IN NACOGDOCHES
ToMAINTENANCE SECTION
CSJ6339-31-001
Proj IDRMC - 633931001
Work TypeUPGRADING MBGF
 
0.010413947.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-08-20
Work Began00-00-00
Work Completed
Time Computed01-08-20
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6339-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08194207
Totals413947.000.000.000.0

CountyPOLK
HighwayUS0059
From0.445 MILES N OF FM 1988
To1.507 S OF US 190 & US 59 LOOP S
CSJ6346-17-001
Proj IDRMC - 634617001
Work TypeEROSION REPAIR
 
0.010466419.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AAD CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6346-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11194010
Totals466419.500.000.000.0

CountySAN JACINTO
HighwayUS0059
From2.885 MILES N OF FM 1127
To2.766 MILES S OF FM 2665 N
CSJ6346-18-001
Proj IDRMC - 634618001
Work TypeEROSION REPAIR
 
0.0101582884.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6346-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11194208
Totals1582884.500.000.000.0

CountySHELBY
HighwayUS0059
FromVARIOUS LOACTIONS IN ANGELINA
ToNACOGDOCHES AND SHELBY COUNTIES
CSJ6347-64-001
Proj IDRMC - 634764001
Work TypeMILL AND INLAY
 
0.010939778.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6347-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08194211
Totals939778.320.000.000.0

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN SAN JACINTO
ToHOUSTON, POLK AND TRINITY COUNTIES
CSJ6347-65-001
Proj IDRMC - 634765001
Work TypeMILL AND INLAY
 
0.0101998581.24960232.6748.0
Work Order11-18-19
Work Began11-25-19
Work Completed
Time Computed11-20-19
Contract Working Days50
Addl Days Granted4
Working Days Charged11
Percent Time Used20
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6347-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08194209
Totals1998581.24632774.95960232.6748.0

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS ROADWAYS IN NACOGDOCHES,SABINE,
ToSAN AUGUSTINE AND SHELBY MAINT SECTIONS
CSJ6349-12-001
Proj IDRMC - 634912001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.0101293555.24143711.9711.1
Work Order10-31-19
Work Began11-01-19
Work Completed
Time Computed11-01-19
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6349-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194214
Totals1293555.2478206.17143711.9711.1

CountyPOLK
HighwayUS0059
FromVARIOUS ROADWAYS IN POLK AND
ToSAN JACINTO MAINTENANCE SECTIONS
CSJ6349-13-001
Proj IDRMC - 634913001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.010520270.2824655.544.7
Work Order00-00-00
Work Began11-15-19
Work Completed
Time Computed11-15-19
Contract Working Days365
Addl Days Granted0
Working Days Charged47
Percent Time Used12
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6349-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194215
Totals520270.2821166.7624655.544.7

page 1