Monthly State Let Construction Report For Paris District As Of Aug 23, 2019 Page 1 Of 5

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHUNT
HighwaySH 66
From0.167 MI N OF FM 2642
To0.122 MI N OF FM 6
CSJ0009-06-051
Proj IDSTP 2019(512)HES
Work TypeSAFETY RELATED PROJECTS
 
4.7652841097.841204721.2242.4
Work Order03-25-19
Work Began05-06-19
Work Completed
Time Computed04-24-19
Contract Working Days95
Addl Days Granted0
Working Days Charged39
Percent Time Used41
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-06-051
WEST TEXAS ROCK RESOURCES, LLC (0.29)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (38.80)
A. E. MOORE CONSTRUCTION, INC. (2.25)
MURRAY CONSTRUCTION (1.07)
CATOCON, INC. (1.92)
STRIPING TECHNOLOGY, L.P. (1.55)
DIIBS SPECIALISTS (1.89)
HIGHWAY 19 CONSTRUCTION LLC (9.57)
AREA WIDE PROTECTIVE, INC. (0.19)
Contract #02193212
Totals2841097.84886336.911204721.2242.4

CountyHUNT ETC
HighwaySH 24 ETC
FromFM 499
ToIH 30
CSJ0009-08-031
Proj IDC 9-8-31
Work TypeSEAL COAT
 
228.29011452320.534079968.7035.6
Work Order01-07-19
Work Began05-03-19
Work Completed
Time Computed05-15-19
Contract Working Days60
Addl Days Granted0
Working Days Charged21
Percent Time Used35
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0009-08-031
CENTERLINE TECHNOLOGIES, LLC (5.92)
INNOVATIVE ROADWAY SOLUTIONS LLC (9.58)
RED SIXTEEN CONSTRUCTION, INC (0.86)
CDM HOLDINGS, LLC (15.75)
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. (9.55)
Contract #12183003
Totals11452320.532672416.234079968.7035.6

CountyHOPKINS
HighwayIH 30
FromON IH 30, 1 MILE EAST OF CUMBY
To.
CSJ0009-09-081
Proj IDSTP 2000(825)TE
Work TypeMISCELLANEOUS CONSTRUCTION
 
1.36323690539.5126652602.9399.9
Work Order07-01-16
Work Began08-08-16
Work Completed
Time Computed08-01-16
Contract Working Days368
Addl Days Granted73
Working Days Charged437
Percent Time Used99
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-081
EROSION CONTROL MANAGEMENT SERVICES (1.00)
THELIN RECYCLING COMPANY, L.P. (0.54)
DALLAS LITE AND BARRICADE INC. (0.53)
GAY AND SONS MASONRY (3.79)
TOTAL HIGHWAY MAINTENANCE, LLC (0.39)
PREMIER PAVING, LTD. (12.00)
RK HALL, LLC (2.28)
W.O.E. CONSTRUCTION (0.45)
J.R. POPE COMPANY, INC. (7.00)
TEX OP CONSTRUCTION, LP (0.30)
PANTHER CREEK TRANSPORTATION, INC. (0.00)
TEXAS YARD PRO INC. (3.13)
K & A STEEL, LLC (0.46)
CHIENER, LLC (0.83)
RELIANCE PLUMBING GROUP, INC. DBA RELIANCE MECHANICAL CONTR (3.73)
HUMPHREY & ASSOCIATES, INC. (4.80)
PEST FORCE (0.01)
SYNERGY SIGNS & SERVICES, LLC (0.54)
CNC CONSTRUCTION (0.59)
F&P CONSTRUCTION, LLC (2.87)
TBS SPECIALTIES DIRECT, INC. (0.10)
EASTEX GLASS & MIRROR DBA TYLER GLASS & MIRROR (1.55)
SAN ANTONIO TILE, INC. (1.67)
SCHNEIDER ELECTRIC (0.29)
AMERITEX FLAG & FLAGPOLE, LLC (0.05)
BLIND DEPOT (0.00)
T-BAR FENCE, INC. (0.00)
SIGN INTERNATIONAL, INC. (0.08)
HEARTLAND PARK AND RECREATION, LLC (0.36)
BECO METAL WORKS (4.03)
SHEET METAL PROFESSIONALS, LLC (2.64)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (0.79)
LEGENDS UNDERGROUND UTILITIES, INC. (3.84)
SCOTT PAVING, INC. (1.02)
SOUTHWEST CABINET CORP DBA ANTON CABINETRY (0.42)
TRI COUNTY WASTEWATER SYSTEMS, LLC (2.37)
QUALITY LABOR MANAGEMENT, LLC (0.01)
WEBBER, LLC (0.94)
STONESMITH, INC. (0.29)
MAR-ZAP CONSTRUCTION, LLC (0.03)
SIMPLY FLOOR IT, LLC (0.10)
Contract #04163201
Totals23690539.510.0026652602.9399.9

CountyHOPKINS
HighwayIH 30
FromHUNT COUNTY LINE
ToTEXAS STREET
CSJ0009-09-106
Proj IDSTP 1902(034)HES
Work TypeSFT
 
14.8041555777.000.000.0
CountyHOPKINS
HighwayIH 30
FromTEXAS STREET
ToCANEY CREEK
CSJ0010-02-099
Proj IDSTP 1902(034)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.7021169023.000.000.0
CountyHOPKINS
HighwayIH 30
FromCANEY CREEK
ToFRANKLIN COUNTY LINE
CSJ0610-01-046
Proj IDSTP 1902(034)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.055369910.250.000.0
CountyFRANKLIN
HighwayIH 30
FromHOPKINS COUNTY LINE
ToTITUS COUNTY LINE
CSJ0610-02-057
Proj IDSTP 1902(034)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.597857829.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-106
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193221
Totals3952539.250.000.000.0

CountyHUNT
HighwayIH 30
FromROCKWALL COUNTY LINE
ToFM 1565 NORTH
CSJ0009-13-159
Proj IDBR 1602(330)
Work TypeBRIDGE REPLACEMENT
 
5.77822304844.4422678833.8699.9
CountyHUNT
HighwayCR
FromIH 30 EASTBOUND FRONTAGE ROAD
ToFM 2642
CSJ0901-22-115
Proj IDCC 901-22-115
Work TypeREHABILITATION OF EXISTING ROAD
 
1.249859715.871064048.8599.9
Work Order10-26-16
Work Began03-13-17
Work Completed
Time Computed11-25-16
Contract Working Days493
Addl Days Granted27
Working Days Charged494
Percent Time Used95
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-159
TOTAL HIGHWAY MAINTENANCE, LLC (0.28)
BOWMAN ENGINEERING & CONSULTING, INC (0.72)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.15)
W.O.E. CONSTRUCTION (0.81)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.15)
TEX OP CONSTRUCTION, LP (0.79)
K & S UTILITY CONTRACTORS, INC. (6.45)
FREIGHT OPERATION SERVICES, LLC, DBA FOS BROKERAGE SERVICES (0.00)
CARRASCO TRUCKING (0.00)
WITHERS CONSTRUCTION, LLC (0.24)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.40)
HOUSTON SAWING & DRILLING (0.02)
RAMBO CONTRACTING, INC. (2.42)
OSCAR ORDUNO, INC. (1.21)
SOUTHERN CROSS CONTRACTORS, LLC (0.43)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.89)
PANIOLO CONSTRUCTION SERVICES, LLC (2.85)
STRIPING TECHNOLOGY, L.P. (0.77)
NE-TEX CONSTRUCTION, LTD. (1.67)
PENHALL COMPANY (0.01)
BIG DOG DRILLING, LLC (0.01)
MCMAHON CONTRACTING, L.P. (2.13)
TEXAS SCORPION HAULERS LLC, DBA TEXAS PRIDE HAULERS (0.00)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.00)
RUSSO CORPORATION (0.90)
ANTIGO CONSTRUCTION, INC. (0.08)
MCL CONTRACTING, LLC (0.05)
J. RUEDAS TRUCKING, LLC (0.00)
DALLAS LITE AND BARRICADE, INC. (0.02)
INSITUFORM TECHNOLOGIES, LLC (0.10)
Contract #08163005
Totals23164560.31742905.0623742882.7199.9

CountyHUNT
HighwayIH 30
FromFM 499
ToHOPKINS COUNTY LINE
CSJ0009-13-171
Proj IDSTP 2019(938)HES
Work TypeSAFETY
 
10.641446990.50177307.5039.6
CountyHUNT
HighwayUS 380
FromCOUNTY ROAD 1158
ToBU 380 J (W)
CSJ0135-06-029
Proj IDSTP 2019(938)HES
Work TypeSAFETY
 
0.37957145.000.000.0
CountyHUNT
HighwayUS 69
From0.1 MI N OF COUNTY ROAD 1040
ToCOUNTY ROAD 1040
CSJ0202-05-051
Proj IDSTP 2019(938)HES
Work TypeSAFETY
 
0.10038592.000.000.0
Work Order06-17-19
Work Began07-08-19
Work Completed
Time Computed07-17-19
Contract Working Days59
Addl Days Granted0
Working Days Charged9
Percent Time Used15
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-171
FORTSON CONTRACTING, INC. (39.40)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.62)
DALLAS LITE AND BARRICADE, INC. (2.54)
Contract #05193028
Totals542727.50177307.50177307.5032.6

CountyHUNT
HighwayUS 69
FromSH 66
ToO'NEIL STREET
CSJ0009-15-027
Proj IDSTP 2018(367)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.5361500993.551217002.3283.1
CountyHUNT
HighwayUS 69
FromUS 380
ToSH 66
CSJ0202-10-020
Proj IDSTP 2018(367)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.9651830598.721570606.7885.7
Work Order03-12-18
Work Began04-23-18
Work Completed
Time Computed04-11-18
Contract Working Days111
Addl Days Granted2
Working Days Charged145
Percent Time Used128
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0009-15-027
ALTUS TRAFFIC MANAGEMENT LLC (0.30)
TRP CONSTRUCTION GROUP, LLC (1.07)
SOUTHWEST ENVIRONMENT SERIVES, LLC (1.34)
FORTSON CONTRACTING, INC. (5.04)
DUSTROL, INC. (2.46)
A.E. MOORE CONSTRUCTION, INC. DBA (1.83)
O. TREVINO CONSTRUCTION, LLC (15.69)
J & M CONTRACTING COMPANY (17.70)
W.O.E. CONSTRUCTION (0.84)
JM YANEZ CONSTRUCTION, INC. (1.75)
TEXAS CURB CUT, INC.(HUB) (0.21)
PENHALL COMPANY (6.82)
Contract #12173020
Totals3331592.2740749.702787609.1084.6

CountyGRAYSON
HighwaySH 56
FromBU 377 B
ToCOLLINSVILLE STREET
CSJ0045-02-034
Proj IDSTP 2018(769)
Work TypeLANDSCAPE AND SCENIC ENHANCEMENT
 
0.104153070.94158909.0299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-18
Work Began07-05-18
Work Completed
Time Computed06-13-18
Contract Working Days30
Addl Days Granted5
Working Days Charged35
Percent Time Used100
Contractor(s)
OLD FIREHOUSE GYM LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-02-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183015
Totals153070.940.00158909.0299.9

CountyGRAYSON
HighwaySH 56 ETC
FromFM 1417
ToTRAVIS STREET
CSJ0045-03-051
Proj IDSTP 1902(035)HES
Work TypeTRAFFIC CONTROL DEVICES
 
36.818995080.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0045-03-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193041
Totals995080.000.000.000.0

CountyFANNIN
HighwaySH 56
FromAT SH 78
To.
CSJ0045-05-048
Proj IDSTP 2019(502)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.20020596.0070366.3099.9
CountyFANNIN
HighwayUS 82
FromAT SH 78
To.
CSJ0045-20-022
Proj IDSTP 2019(502)HES
Work TypeSAFETY RELATED PROJECT - HSIP
 
0.200156834.503318.002.1
CountyGRAYSON
HighwayFM 691
FromAT FM 1417
To.
CSJ0666-01-030
Proj IDSTP 2019(502)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.20028422.5024490.5086.1
Work Order03-18-19
Work Began07-16-19
Work Completed
Time Computed07-16-19
Contract Working Days50
Addl Days Granted0
Working Days Charged8
Percent Time Used16
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0045-05-048
FLEX SUPPLY, LLC (5.82)
TOTAL HIGHWAY MAINTENANCE, LLC (5.58)
Contract #02193032
Totals205853.0049027.8098174.8047.6

CountyLAMAR ETC
HighwayUS 82 ETC
FromAT FM 38
To.
CSJ0045-08-038
Proj IDSTP 2018(808)HES
Work TypeSAFETY RELATED PROJECT - HSIP
 
1.100200076.1693615.5046.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-21-18
Work Began04-25-19
Work Completed
Time Computed12-10-18
Contract Working Days100
Addl Days Granted0
Working Days Charged41
Percent Time Used41
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-08-038
WG ENGINEERING & CONSTRUCTION, LLC (69.52)
Contract #07183248
Totals200076.160.0093615.5046.7

CountyLAMAR ETC
HighwayUS 82 ETC
From0.148 MI N OF BU 82H
To0.86 MI W OF FM 196
CSJ0045-09-101
Proj IDSTP 2019(939)HES
Work TypeSAFETY
 
66.0961229691.600.000.0
Work Order06-18-19
Work Began08-19-19
Work Completed
Time Computed07-18-19
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-09-101
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193244
Totals1229691.600.000.000.0

CountyLAMAR
HighwayUS 82
FromDIVISION STREET
To0.2 MI E OF FM 194
CSJ0045-11-038
Proj IDSTP 1702(741)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
1.146461134.73486645.7199.9
CountyLAMAR
HighwayFM 1500
From0.1 MILE N OF FM 1499
ToEND OF STATE MAINTENANCE
CSJ1455-02-009
Proj IDSTP 1702(742)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
4.407995832.79953508.5195.7
CountyLAMAR
HighwayFM 1500
From4.4 MI N OF FM 1499
ToFM 1499
CSJ1455-02-010
Proj IDSTP 1702(743)HESG
Work TypeHAZARD ELIMINATION & SAFETY
 
4.40066972.6939910.4359.5
CountyLAMAR
HighwayFM 1500
FromEND OF STATE MANINTENANCE
To0.1 MILE N OF FM 1499
CSJ1455-02-011
Proj IDSTP 1702(744)
Work TypeSEAL COAT
 
4.309167164.48170034.5999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began10-14-17
Work Completed
Time Computed10-16-17
Contract Working Days157
Addl Days Granted0
Working Days Charged83
Percent Time Used52
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-11-038
LYON BARRICADE AND CONSTRUCTION CO. (0.89)
WITHERS CONSTRUCTION, LLC (4.95)
A. E. MOORE CONSTRUCTION, INC. (4.32)
BAHENA CONSTRUCTION CO.,INC. (9.62)
SOUTHWEST ENVIRONMENT SERIVES, LLC (12.31)
DUSTROL, INC. (3.01)
TOTAL HIGHWAY MAINTENANCE, LLC (5.31)
Contract #08173213
Totals1691104.690.001650099.2497.5

CountyGRAYSON
HighwayUS 82
FromFM 901
ToFM 1417 WEST
CSJ0045-18-038
Proj IDNH 2019(723)
Work TypeOVERLAY
 
11.8087390532.53506679.736.8
Work Order05-14-19
Work Began07-08-19
Work Completed
Time Computed06-14-19
Contract Working Days93
Addl Days Granted0
Working Days Charged14
Percent Time Used15
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0045-18-038
XROADS, L.P. (0.31)
DUSTROL, INC. (0.56)
J. H. ODEN CONTRACTING COMPANY (0.92)
TEXOP CONSTRUCTION (6.40)
JM YANEZ CONSTRUCTION, INC. (0.51)
COMEN ENTERPRISE LLC (0.26)
STRIPING TECHNOLOGY, L.P. (2.94)
Contract #04193215
Totals7390532.53506679.73506679.736.8

CountyGRAYSON
HighwayUS 82
FromFM 131
ToFM 1897
CSJ0045-19-053
Proj IDSTP 1802(488)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
12.5721489216.50672127.8745.1
CountyGRAYSON
HighwayUS 69
FromUS 75
To0.148 MI N OF FM 120
CSJ0047-01-062
Proj IDSTP 1802(489)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
2.954317399.00188652.5059.4
CountyGRAYSON
HighwayUS 69
FromSS 503
ToUS 82
CSJ0410-01-029
Proj IDSTP 1802(489)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
10.1331369065.001117541.5081.6
CountyGRAYSON
HighwayUS 69
FromUS 82
ToSH 56
CSJ0410-02-032
Proj IDSTP 1802(489)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
1.700285764.50224507.5078.5
Work Order01-02-19
Work Began02-04-19
Work Completed
Time Computed02-04-19
Contract Working Days140
Addl Days Granted0
Working Days Charged89
Percent Time Used63
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-053
LYNCO CONSTRUCTION (9.15)
JR WEST TEXAS CONCRETE LLC (7.44)
COMEN ENTERPRISE LLC (2.82)
WEBBER, LLC (4.71)
Contract #08183023
Totals3461445.00209557.082202829.3763.6

CountyFANNIN
HighwayUS 82
From0.5 MILES WEST OF SH 121
ToSH 78 (0.478 MI EAST OF SH 78)
CSJ0045-20-018
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
2.03112156062.248445020.1469.4
CountyFANNIN
HighwayUS 82
From0.478 MI E OF SH 78
ToFM 100
CSJ0045-21-011
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
14.48749116732.238695812.9217.7
CountyFANNIN
HighwayUS 82
FromFM 100
To0.5 MILES EAST OF SH 56
CSJ0045-21-012
Proj IDNH 1802(395)
Work TypeWIDEN NON-FREEWAY
 
2.63610365091.264236322.2140.8
Work Order08-24-18
Work Began10-18-18
Work Completed
Time Computed09-24-18
Contract Working Days928
Addl Days Granted0
Working Days Charged230
Percent Time Used24
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0045-20-018
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.13)
W.O.E. CONSTRUCTION (0.70)
STRIPING TECHNOLOGY, L.P. (0.83)
LYON BARRICADE AND CONSTRUCTION CO. (0.20)
HAMMETT EXCAVATION, INC. (23.92)
TEXAS SHAFTS, INC. (0.93)
BOWMAN ENGINEERING & CONSULTING, INC. (0.16)
MCL CONTRACTING, LLC (0.06)
RAMBO CONTRACTING, INC. (3.95)
CDM HOLDINGS, LLC (3.64)
GANT CONTRACTORS, INC. (0.11)
SOUTHERN CROSS CONTRACTORS, LLC (0.61)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.50)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.05)
Contract #07183002
Totals71637885.732469106.1521377155.2729.8

CountyFANNIN
HighwayUS 82
FromAT FM 898
To.
CSJ0045-20-019
Proj IDSTP 1602(438)
Work TypeINTERCHANGE IMPROVEMENT
 
0.7592147616.852020509.8995.1
CountyFANNIN
HighwayFM 898
From@ US 82
To.
CSJ0510-05-015
Proj IDSTP 1602(438)
Work TypeINTERCHANGE MODIFICATION
 
0.5004699617.764871834.1799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-16
Work Began11-08-16
Work Completed
Time Computed11-04-16
Contract Working Days223
Addl Days Granted0
Working Days Charged243
Percent Time Used108
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-20-019
WYLIE DRILLING & DRAINAGE, INC. (2.10)
TEXOP CONSTRUCTION (1.10)
WEST TEXAS RUMBLE STRIP (0.05)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (11.39)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.69)
AARON CONCRETE CONTRACTORS, L.P. (0.95)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.13)
A. E. MOORE CONSTRUCTION, INC. (3.28)
TOTAL HIGHWAY MAINTENANCE, LLC (1.09)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (0.42)
PENHALL COMPANY (0.00)
Contract #08163223
Totals6847234.610.006892344.0699.9

CountyRED RIVER
HighwayUS 82
From@ KICKAPOO CREEK
To.
CSJ0046-01-061
Proj IDBR 1502(210)
Work TypeBRIDGE REPLACEMENT
 
0.5152651371.112756535.1699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-31-15
Work Began10-02-15
Work Completed
Time Computed08-30-15
Contract Working Days200
Addl Days Granted11
Working Days Charged228
Percent Time Used108
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0046-01-061
TOTAL HIGHWAY MAINTENANCE, LLC (0.34)
RK HALL, LLC (8.77)
DUSTIN ALLEN, INC. (1.93)
A. E. MOORE CONSTRUCTION, INC. (2.23)
TEX OP CONSTRUCTION, LP (0.66)
PENHALL COMPANY (0.24)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.03)
WITHERS CONSTRUCTION, LLC (0.16)
STRIPING TECHNOLOGY, L.P. (0.36)
WEST TEXAS RUMBLE STRIP (0.22)
MCL CONTRACTING, LLC (0.17)
STRIPING SYSTEMS, INC. (0.03)
Contract #06153246
Totals2651371.110.002756535.1699.9

CountyRED RIVER
HighwayUS 82
FromBU 82 J
ToBOWIE COUNTY LINE
CSJ0046-01-064
Proj IDNH 2019(724)
Work TypeWIDEN NON-FREEWAY
 
16.88513814948.610.000.0
CountyRED RIVER
HighwayUS 82
FromFM 1159
ToBU 82 J
CSJ0046-10-001
Proj IDNH 2019(724)
Work TypeWIDEN NON-FREEWAY
 
0.855387212.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days367
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0046-01-064
J. H. ODEN CONTRACTING COMPANY (0.83)
WITHERS CONSTRUCTION, LLC (1.85)
JM YANEZ CONSTRUCTION, INC. (5.41)
DUSTIN ALLEN, INC. (1.92)
FARR FOUNDATION, INC. (0.76)
D. L. LENNON INCORPORATED - CONTRACTOR (10.73)
TEX OP CONSTRUCTION, LP (2.35)
LYON BARRICADE & CONSTRUCTION CO. (0.34)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.31)
SOUTHERN CROSS CONTRACTORS, LLC (0.16)
STRIPING TECHNOLOGY, L.P. (1.34)
Contract #04193007
Totals14202161.560.000.000.0

CountyGRAYSON
HighwayUS 75
FromUS 69
ToRED RIVER
CSJ0047-01-069
Proj IDNH 2018(371)
Work TypeFULL DEPTH REPAIR
 
25.5721374640.001390221.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began02-05-18
Work Completed
Time Computed02-09-18
Contract Working Days105
Addl Days Granted0
Working Days Charged85
Percent Time Used80
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-01-069
URETEK USA, INC. (15.64)
Contract #12173226
Totals1374640.000.001390221.6099.9

page 1 | page 2 | page 3 | page 4 | page 5