Monthly Local Let Maintenance Report For Paris District As Of Sep 10, 2018 Page 5 Of 6

Last Update: Monday, September 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGRAYSON
HighwayUS0082
FromVARIOUS LOCATIONS IN GRAYSON,
ToFANNIN, HOPKINS, AND HUNT COUNTY
CSJ6326-09-001
Proj IDBPM - 632609001
Work TypeBPM-ABUTMENT EROSION REPAIR
 
0.00195594.0074596.4481.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-25-18
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged30
Percent Time Used120
Contractor(s)
HARTBEAT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6326-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180103
Totals95594.002132.0074596.4481.0

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS
ToIN HOPKINS COUNTY
CSJ6326-10-001
Proj IDSUP - 632610001
Work TypePICNIC AREA MAINTENANCE
 
0.00130236.0017766.5058.7
Work Order01-12-18
Work Began01-15-18
Work Completed
Time Computed01-15-18
Contract Working Days365
Addl Days Granted0
Working Days Charged229
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6326-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11170131
Totals30236.002587.0017766.5058.7

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN LAMAR, DELTA,
ToRED RIVER, FANNIN, AND GRAYSON COUNTIES
CSJ6326-37-001
Proj IDRMC - 632637001
Work TypeON CALL TY II STRIPING
 
0.001267150.00120010.2844.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-07-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged86
Percent Time Used23
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6326-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04180102
Totals267150.0059773.66120010.2844.9

CountyHOPKINS
HighwaySH0019
FromVARIOUS LOCATIONS IN HOPKINS AND
ToFRANKLIN COUNTY
CSJ6327-52-001
Proj IDRMC - 632752001
Work TypeON CALL TREE TRIMMING
 
0.001242945.0048320.0419.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180104
Totals242945.000.0048320.0419.8

CountyGRAYSON
HighwayUS0075
FromGRAYSON CO AREA OFFICE
ToAND MAINTENANCE COMPLEX
CSJ6327-89-001
Proj IDSUP - 632789001
Work TypeJANITORIAL MAINTENANCE
 
0.00133404.0315150.2345.3
Work Order01-26-18
Work Began03-01-18
Work Completed
Time Computed03-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6327-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170131
Totals33404.031886.7815150.2345.3

CountyHOPKINS
HighwayIH0030
FromHOPKINS COUNTY MAINENANCE OFFICE
ToAREA OFFICE AN MAINTENANCE OFFICES
CSJ6327-90-001
Proj IDSUP - 632790001
Work TypeJANITORIAL MAINTENANCE
 
0.00118810.509405.2550.0
Work Order01-26-18
Work Began03-01-18
Work Completed
Time Computed03-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170132
Totals18810.501380.809405.2550.0

CountyRED RIVER
HighwayUS0082
FromRED RIVER COUNTY
ToMAINTENANCE COMPLEX
CSJ6328-83-001
Proj IDSUP - 632883001
Work TypeJANITORIAL MAINTENANCE
 
0.0018751.843448.6739.4
Work Order02-23-18
Work Began04-01-18
Work Completed
Time Computed04-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6328-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180105
Totals8751.841641.753448.6739.4

CountyDELTA
HighwaySH0019
FromDELTA COUNTY
ToMAINTENANCE COMPLEX
CSJ6329-00-001
Proj IDSUP - 632900001
Work TypeGROUNDS MAINTENANCE
 
0.0015425.001530.0028.2
Work Order02-27-18
Work Began04-01-18
Work Completed
Time Computed04-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6329-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180106
Totals5425.00170.001530.0028.2

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN HOPKINS AND
ToFRANKLIN COUNTIES
CSJ6329-05-001
Proj IDRMC - 632905001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.00168219.0027173.5039.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
MORTON ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6329-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180101
Totals68219.006712.0027173.5039.8

CountyHOPKINS
HighwaySH0019
FromVARIOUS LOCATIONS IN HOPKINS AND
ToFRANKLIN COUNTIES
CSJ6329-06-001
Proj IDRMC - 632906001
Work TypeON CALL DITCH AND CULVERT CLEANING
 
0.001246510.0054646.8022.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
ANCHOR CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6329-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180102
Totals246510.000.0054646.8022.1

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS IN GRAYSON
ToAND FANNIN COUNTY
CSJ6329-36-001
Proj IDRMC - 632936001
Work TypeCRACK SEAL
 
0.001200055.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6329-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07180101
Totals200055.000.000.000.0

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN HOPKINS AND
ToFRANKLIN COUNTY
CSJ6329-37-001
Proj IDRMC - 632937001
Work TypeCRACK SEAL
 
0.001111708.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days24
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6329-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07180102
Totals111708.000.000.000.0

CountyLAMAR
HighwayUS0271
FromVARIOUS LOCATIONS IN
ToLAMAR COUNTY
CSJ6330-17-001
Proj IDRMC - 633017001
Work TypePICNIC AREA MAINTENANCE
 
0.00192000.009200.0010.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
WILLIAM CURTIS SMITH
SUBCONTRACTOR(S) FOR CCSJ: 6330-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06180102
Totals92000.009200.009200.0010.0

CountyGRAYSON
HighwayUS0082
FromVARIOUS LOCATIONS IN GRAYSON AND
ToFANNIN COUNTY
CSJ6330-38-001
Proj IDRMC - 633038001
Work TypeON CALL TREE TRIMMING AND REMOVAL
 
0.001258500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NATURAL COLORS PAINTING LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05180101
Totals258500.000.000.000.0

CountyFRANKLIN
HighwayIH0030
FromFRANKLIN COUNTY MAINTENANCE
ToCOMPLEX
CSJ6330-52-001
Proj IDSUP - 633052001
Work TypeGROUNDS MAINTENANCE
 
0.0016525.002175.0033.3
Work Order04-06-18
Work Began05-01-18
Work Completed
Time Computed05-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6330-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180135
Totals6525.00652.502175.0033.3

CountyHOPKINS
HighwaySH0011
FromHOPKINS COUNTY MAINTENANCE
ToOFFICE COMPLEX
CSJ6330-59-001
Proj IDSUP - 633059001
Work TypeGROUNDS MAINTENANCE
 
0.00112134.003620.0029.8
Work Order04-10-18
Work Began05-06-18
Work Completed
Time Computed05-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged118
Percent Time Used32
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6330-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180136
Totals12134.00724.003620.0029.8

CountyHUNT
HighwayIH0030
FromHUNT COUNTY AREA OFFICE AND
ToMAINTENANCE COMPLEX
CSJ6330-62-001
Proj IDSUP - 633062001
Work TypeGROUNDS MAINTENANCE
 
0.00114370.005655.0039.3
Work Order04-13-18
Work Began05-08-18
Work Completed
Time Computed05-08-18
Contract Working Days365
Addl Days Granted0
Working Days Charged116
Percent Time Used31
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6330-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180137
Totals14370.001740.005655.0039.3

CountyRAINS
HighwayUS0069
FromVARIOUS ROADWAYS IN
ToRAINS COUNTY
CSJ6330-63-001
Proj IDSUP - 633063001
Work TypePICNIC AREA MAINTENANCE
 
0.00128200.007775.0027.5
Work Order04-17-18
Work Began05-11-18
Work Completed
Time Computed05-11-18
Contract Working Days365
Addl Days Granted0
Working Days Charged113
Percent Time Used30
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6330-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180138
Totals28200.002075.007775.0027.5

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN LAMAR, DELTA, AND
ToRED RIVER COUNTIES
CSJ6330-89-001
Proj IDRMC - 633089001
Work TypeON CALL DITCH AND CULVERT CLEANING
 
0.001191950.0015290.507.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-23-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged40
Percent Time Used10
Contractor(s)
ANCHOR CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6330-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06180103
Totals191950.0015190.5015290.507.9

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS
ToIN FANNIN AND GRAYSON COUNTIES
CSJ6331-11-001
Proj IDSUP - 633111001
Work TypeREM/REPL/INSTALL DEL POST/OBJ MRK, MAILB
 
0.00170000.0014546.0020.7
Work Order05-02-18
Work Began05-15-18
Work Completed
Time Computed05-15-18
Contract Working Days365
Addl Days Granted0
Working Days Charged109
Percent Time Used29
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6331-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03180139
Totals70000.004920.0014546.0020.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6