Monthly State Let Maintenance Report For Paris District As Of Nov 12, 2021 Page 1 Of 3

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLAMAR
HighwayUS0082
FromUS 82 W
ToUS 271 N
CSJ6203-38-001
Proj IDRMC - 620338001
Work TypeSEAL COAT SHOULDERS/CLEAN & SEAL JOINTS
 
3.560372768.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6203-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05104002
Totals372768.260.000.000.0

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT
ToPARIS DISTRICT
CSJ6344-26-001
Proj IDRMC - 634426001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.001352440.00526847.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-03-19
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted455
Working Days Charged790
Percent Time Used96
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6344-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194217
Totals352440.000.00526847.5099.9

CountyGRAYSON
HighwayUS0075
FromVARIOUS ROADWAYS IN
ToGRAYSON COUNTY
CSJ6345-41-001
Proj IDRMC - 634541001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001380150.00577140.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-19
Work Completed09-30-21
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6345-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194016
Totals380150.000.00577140.50100.0

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATION IN PARIS DISTRICT
ToNORTHERN COUNTIES
CSJ6345-61-001
Proj IDRMC - 634561001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.0011112787.501930732.5699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-12-20
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted254
Working Days Charged265
Percent Time Used52
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6345-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03204010
Totals1112787.5054440.441930732.5699.9

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT
ToENTIRE PARIS DISTRICT
CSJ6345-63-001
Proj IDRMC - 634563001
Work TypeON CALL TRAFFIC CONTROL SERVICES
 
0.0012865009.507084062.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-19
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6345-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194017
Totals2865009.50237047.957084062.6499.9

CountyGRAYSON
HighwayUS0082
FromVARIOUS LOCATIONS IN GRAYSON AND
ToFANNIN COUNTIES
CSJ6346-95-001
Proj IDRMC - 634695001
Work TypeON CALL METAL BEAM GUARD FENCE REPAIR
 
0.001613137.001447868.7099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-19
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6346-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194014
Totals613137.0049651.001447868.7099.9

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN HUNT, RAINS,
ToHOPKINS AND FRANKLIN COUNTIES
CSJ6351-53-001
Proj IDRMC - 635153001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.001691675.001229985.5599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-12-20
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted254
Working Days Charged224
Percent Time Used44
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6351-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03204218
Totals691675.005534.951229985.5599.9

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN LAMAR, DELTA,
ToRED RIVER, FANNIN, AND GRAYSON COUNTIES
CSJ6351-55-001
Proj IDRMC - 635155001
Work TypeON CALL TY-II STRIPING
 
0.001311250.00332933.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-12-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged536
Percent Time Used73
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6351-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03204011
Totals311250.0019702.02332933.5099.9

CountyHOPKINS
HighwayIH0030
FromIH 30 IN HOPKINS, FRANKLIN,
ToAND HUNT COUNTIES
CSJ6352-54-001
Proj IDRMC - 635254001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001291141.55582282.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted54
Working Days Charged81
Percent Time Used75
Contractor(s)
EASTGATE SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6352-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204019
Totals291141.5587579.00582282.0099.9

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN HUNT, RAINS,
ToHOPKINS AND FRANKLIN COUNTIES
CSJ6354-88-001
Proj IDRMC - 635488001
Work TypeON CALL METAL BEAM GUARD FENCE REPAIR
 
0.001611418.00546104.8089.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged304
Percent Time Used83
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6354-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06204017
Totals611418.0058073.80546104.8089.3

CountyHUNT
HighwayUS0069
FromVARIOUS LOCATIONS IN HUNT AND
ToRAINS COUNTY
CSJ6355-91-001
Proj IDRMC - 635591001
Work TypeDITCH CLEANING AND RESHAPING_PROJECT
 
0.010324125.00107233.3233.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6355-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214017
Totals324125.000.00107233.3233.0

CountyGRAYSON
HighwayUS0075
FromVARIOUS COUNTIES IN THE
ToPARIS DISTRICT
CSJ6361-47-001
Proj IDMMC - 636147001
Work TypeAGGREGATE - MATERIALS ONLY
 
0.0011138554.00776278.92100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-20
Work Completed09-29-21
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged360
Percent Time Used100
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6361-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05204220
Totals1138554.0061368.17776278.92100.0

CountyGRAYSON
HighwayFM0697
FromVARIOUS LOCATION IN
ToPARIS DISTRICT
CSJ6363-01-001
Proj IDRMC - 636301001
Work TypeSITE SPECIFIC FLEXIBLE PAVEMENT REPAIR
 
0.0012960212.512940384.8099.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days335
Addl Days Granted0
Working Days Charged325
Percent Time Used97
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 6363-01-001
TOTAL HIGHWAY MAINTENANCE, LLC (0.81)
PEACHTREE CONSTRUCTION, LTD. (29.02)
Contract #07204013
Totals2960212.5134350.002940384.8099.3

CountyFANNIN
HighwaySH0056
FromVARIOUS ROADWAYS IN
ToFANNIN COUNTY
CSJ6368-42-001
Proj IDRMC - 636842001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001241303.88163602.0967.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-07-21
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged59
Percent Time Used77
Contractor(s)
PRESLEY LAND MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6368-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204219
Totals241303.8854276.50163602.0967.7

CountyGRAYSON
HighwayUS0075
FromUS 75 AND US 82 IN GRAYSON AND
ToFANNIN COUNTIES
CSJ6368-46-001
Proj IDRMC - 636846001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001233623.20203125.4486.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-21
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged36
Percent Time Used70
Contractor(s)
PRESLEY LAND MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6368-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204220
Totals233623.2061421.24203125.4486.9

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN PARIS
ToDISTRICT
CSJ6369-87-001
Proj IDRMC - 636987001
Work TypeILLUMINATION MAINTENANCE
 
0.001314750.0077696.4024.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted0
Working Days Charged159
Percent Time Used62
Contractor(s)
SIEMENS MOBILITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6369-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204019
Totals314750.008215.0077696.4024.6

CountyGRAYSON
HighwayFM0121
FromVARIOUS LOCATIONS IN GRAYSON_AND
ToRED RIVER COUNTIES
CSJ6371-22-001
Proj IDRMC - 637122001
Work TypeROUTINE MAINTENANCE PROJECT - SEALED
 
652334.00516736.6379.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged90
Percent Time Used75
Contractor(s)
WG ENGINEERING & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6371-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01214219
Totals652334.0055357.20516736.6379.2

CountyHUNT
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToPARIS DISTRICT
CSJ6372-80-001
Proj IDRMC - 637280001
Work TypeSITE SPECIFIC TY I STRIPING
 
0.001904562.06980204.7399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged94
Percent Time Used156
Contractor(s)
CENTERLINE TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6372-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01214019
Totals904562.0627777.60980204.7399.9

CountyGRAYSON
HighwayUS0082
FromVARIOUS ROADWAYS IN
ToGRAYSON COUNTY
CSJ6373-28-001
Proj IDMMC - 637328001
Work TypeD-GR HOT MIX - MATERIALS ONLY
 
0.001578000.001200881.4599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged243
Percent Time Used67
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6373-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204018
Totals578000.00131705.821200881.4599.9

CountyRAINS
HighwayUS0069
FromVARIOUS ROADWAYS IN
ToRAINS COUNTY
CSJ6373-63-001
Proj IDMMC - 637363001
Work TypeDENSE GRADE HOT MIX - MATERIALS ONLY
 
0.001511875.00248040.9848.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-21
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged153
Percent Time Used42
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6373-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204020
Totals511875.0080558.04248040.9848.4