Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | RED RIVER |
Highway | SH0037 |
From | 0.001 |
To | RED RIVER COUNTY |
CSJ | 6432-38-001 |
Proj ID | MMC - 643238001 |
Work Type | EMULSION |
|
| 0.010 | 309760.00 | | 354551.43 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 182 |
Working Days Charged | 303 |
Percent Time Used | 83 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6432-38-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03234232 |
| Totals | 309760.00 | 6098.04 | 354551.43 | 99.9 |
|
County | LAMAR |
Highway | US0082 |
From | VARIOUS LOCATIONS IN |
To | PARIS DISTRICT |
CSJ | 6433-52-001 |
Proj ID | RMC - 643352001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 471520.00 | | 120208.73 | 25.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 274 |
Percent Time Used | 75 |
Contractor(s) |
REYNOLDS & KAY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6433-52-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03234030 |
| Totals | 471520.00 | 0.00 | 120208.73 | 25.4 |
|
County | HOPKINS |
Highway | IH0030 |
From | VARIOUS LOCATIONS IN |
To | PARIS DISTRICT |
CSJ | 6433-54-001 |
Proj ID | RMC - 643354001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 461060.50 | | 69486.82 | 15.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 07-05-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 240 |
Percent Time Used | 65 |
Contractor(s) |
TRAFFIC HIGHWAY MAINTENANCE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6433-54-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03234231 |
| Totals | 461060.50 | 0.00 | 69486.82 | 15.0 |
|
County | FANNIN |
Highway | SH0078 |
From | 0.001 |
To | FANNIN COUNTY |
CSJ | 6433-76-001 |
Proj ID | MMC - 643376001 |
Work Type | EMULSION |
|
| 0.010 | 437700.00 | | 342012.32 | 78.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-22-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 120 |
Working Days Charged | 284 |
Percent Time Used | 94 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6433-76-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04234016 |
| Totals | 437700.00 | 0.00 | 342012.32 | 78.1 |
|
County | HOPKINS |
Highway | IH0030 |
From | 0.001 |
To | HOPKINS COUNTY |
CSJ | 6433-80-001 |
Proj ID | MMC - 643380001 |
Work Type | EMULSION |
|
| 0.010 | 273750.00 | | 86998.60 | 31.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 08-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 182 |
Working Days Charged | 274 |
Percent Time Used | 75 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6433-80-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04234214 |
| Totals | 273750.00 | 0.00 | 86998.60 | 31.7 |
|
County | HOPKINS |
Highway | IH0030 |
From | 0.001 |
To | HOPKINS COUNTY |
CSJ | 6433-82-001 |
Proj ID | MMC - 643382001 |
Work Type | DENSE GRADED HOT MIX |
|
| 0.010 | 685000.00 | | 563918.70 | 82.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 240 |
Working Days Charged | 272 |
Percent Time Used | 75 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6433-82-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04234017 |
| Totals | 685000.00 | 0.00 | 563918.70 | 82.3 |
|
County | HUNT |
Highway | IH0030 |
From | 0.001 |
To | HUNT COUNTY |
CSJ | 6433-86-001 |
Proj ID | MMC - 643386001 |
Work Type | DENSE GRADED HOT MIX |
|
| 0.010 | 620500.00 | | 276624.85 | 44.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-28-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 240 |
Working Days Charged | 278 |
Percent Time Used | 77 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6433-86-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04234215 |
| Totals | 620500.00 | 42106.45 | 276624.85 | 44.5 |
|
County | HUNT |
Highway | IH0030 |
From | 0.001 |
To | HUNT COUNTY |
CSJ | 6434-10-001 |
Proj ID | MMC - 643410001 |
Work Type | EMULSION |
|
| 0.010 | 263970.00 | | 347020.74 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-22-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 182 |
Working Days Charged | 284 |
Percent Time Used | 78 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6434-10-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04234018 |
| Totals | 263970.00 | 0.00 | 347020.74 | 99.9 |
|
County | RAINS |
Highway | US0069 |
From | 0.001 |
To | RAINS COUNTY |
CSJ | 6434-12-001 |
Proj ID | MMC - 643412001 |
Work Type | EMULSION |
|
| 0.010 | 273750.00 | | 120509.38 | 44.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-22-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 182 |
Working Days Charged | 284 |
Percent Time Used | 78 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6434-12-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04234216 |
| Totals | 273750.00 | 0.00 | 120509.38 | 44.0 |
|
County | LAMAR |
Highway | US0082 |
From | VARIOUS LOCATIONS IN |
To | PARIS DISTRICT |
CSJ | 6434-84-001 |
Proj ID | RMC - 643484001 |
Work Type | ILLUMINATION MAINTENANCE |
|
| 0.010 | 439885.30 | | 79372.92 | 18.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 254 |
Addl Days Granted | 0 |
Working Days Charged | 63 |
Percent Time Used | 24 |
Contractor(s) |
YUNEX LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6434-84-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234035 |
| Totals | 439885.30 | 24114.72 | 79372.92 | 18.0 |
|
County | LAMAR |
Highway | US0082 |
From | 0.001 |
To | PARIS DISTRICT |
CSJ | 6435-78-001 |
Proj ID | MMC - 643578001 |
Work Type | FLEXIBLE BASE |
|
| 0.010 | 1533000.00 | | 754533.20 | 49.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 07-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 244 |
Working Days Charged | 244 |
Percent Time Used | 67 |
Contractor(s) |
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6435-78-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05234023 |
| Totals | 1533000.00 | 167765.81 | 754533.20 | 49.2 |
|
County | GRAYSON |
Highway | US0075 |
From | 0.001 |
To | GRAYSON COUNTY |
CSJ | 6436-45-001 |
Proj ID | MMC - 643645001 |
Work Type | EMULSION |
|
| 0.010 | 297490.00 | | 107364.83 | 36.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-29-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 120 |
Working Days Charged | 246 |
Percent Time Used | 81 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6436-45-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05234024 |
| Totals | 297490.00 | 0.00 | 107364.83 | 36.0 |
|
County | GRAYSON |
Highway | US0075 |
From | VARIOUS LOCATIONS |
To | ALONG US75 |
CSJ | 6437-37-001 |
Proj ID | RMC - 643737001 |
Work Type | FULL DEPTH CONCRETE REPAIR |
|
| 0.010 | 872711.00 | | 825222.63 | 94.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-09-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 65 |
Addl Days Granted | 0 |
Working Days Charged | 57 |
Percent Time Used | 87 |
Contractor(s) |
WINDING ROAD CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6437-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234424 |
| Totals | 872711.00 | 54127.23 | 825222.63 | 94.5 |
|
County | HOPKINS |
Highway | IH0030 |
From | VARIOUS LOCATIONS IN |
To | PARIS DISTRICT |
CSJ | 6440-51-001 |
Proj ID | RMC - 644051001 |
Work Type | FULL DEPTH CONCRETE REPAIR |
|
| 0.010 | 2947460.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-29-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 138 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
WINDING ROAD CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6440-51-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234032 |
| Totals | 2947460.00 | 0.00 | 0.00 | 0.0 |
|
County | GRAYSON |
Highway | US0069 |
From | VARIOUS LOCATIONS IN |
To | PARIS DISTRICT |
CSJ | 6441-62-001 |
Proj ID | RMC - 644162001 |
Work Type | FLEXIBLE PAVEMENT STRUCTURE REPAIR |
|
| 0.010 | 4219509.82 | | 28560.00 | 0.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 254 |
Addl Days Granted | 0 |
Working Days Charged | 121 |
Percent Time Used | 47 |
Contractor(s) |
D. L. LENNON INCORPORATED - CONTRACTOR |
SUBCONTRACTOR(S) FOR CCSJ: 6441-62-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234623 |
| Totals | 4219509.82 | 0.00 | 28560.00 | 0.6 |
|
County | HUNT |
Highway | IH0030 |
From | VARIOUS LOCATIONS IN |
To | HUNT, RAINS, HOPKINS, AND FRANKLIN CO. |
CSJ | 6441-97-001 |
Proj ID | RMC - 644197001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 719833.00 | | 240697.00 | 33.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 182 |
Percent Time Used | 49 |
Contractor(s) |
ROSS SA ENTERPRISE LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6441-97-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234209 |
| Totals | 719833.00 | 58349.00 | 240697.00 | 33.4 |
|
County | LAMAR |
Highway | FM0137 |
From | VARIOUS LOCATIONS IN |
To | PARIS DISTRICT |
CSJ | 6443-16-001 |
Proj ID | RMC - 644316001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 6031608.55 | | 2263375.09 | 37.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 114 |
Addl Days Granted | 0 |
Working Days Charged | 32 |
Percent Time Used | 28 |
Contractor(s) |
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6443-16-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06234425 |
| Totals | 6031608.55 | 1415631.92 | 2263375.09 | 37.5 |
|
County | GRAYSON |
Highway | US0075 |
From | VARIOUS LOCATIONS |
To | PARIS DISTRICT |
CSJ | 6445-19-001 |
Proj ID | MMC - 644519001 |
Work Type | DE-ICING SALT |
|
| 0.010 | 891158.00 | | 86829.23 | 9.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-18-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 0 |
Working Days Charged | 165 |
Percent Time Used | 90 |
Contractor(s) |
NSG LOGISTICS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6445-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234033 |
| Totals | 891158.00 | 3198.71 | 86829.23 | 9.7 |
|
County | LAMAR |
Highway | US0082 |
From | VARIOUS LOCATIONS IN |
To | PARIS DISTRICT |
CSJ | 6445-37-001 |
Proj ID | RMC - 644537001 |
Work Type | RAISED PAVEMENT MARKERS |
|
| 0.010 | 536512.00 | | 23108.00 | 4.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-26-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 4 |
Percent Time Used | 1 |
Contractor(s) |
BRYDL CONTRACTING, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6445-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234036 |
| Totals | 536512.00 | 23108.00 | 23108.00 | 4.3 |
|
County | HOPKINS |
Highway | IH0030 |
From | VARIOUS LOCATIONS |
To | IN HOPKINS AND FRANKLIN COUNTIES |
CSJ | 6446-04-001 |
Proj ID | MMC - 644604001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 525765.00 | | 90673.88 | 17.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 120 |
Working Days Charged | 152 |
Percent Time Used | 63 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6446-04-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234034 |
| Totals | 525765.00 | 0.00 | 90673.88 | 17.2 |
|