Monthly State Let Construction Report For Pharr District As Of Dec 07, 2021 Page 2 Of 4

Last Update: Wednesday, December 08, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCAMERON ETC
HighwaySH 48 ETC
FromAT COFFEEPORT RD.
To.
CSJ0220-05-081
Proj IDSTP 2020(626)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.800801029.45799461.5299.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-14-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days105
Addl Days Granted0
Working Days Charged105
Percent Time Used100
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0220-05-081
TEXAS HIGHWAY SYSTEMS, INC. (2.28)
PAVEMENT MARKINGS INC. (3.67)
IZAGUIRRE CONSTRUCTION LLC (2.91)
G & E ESCOBEDO CONSTRUCTION, INC. (1.43)
MUNOZ FOUNDATION DRILLING, INC. (0.53)
Contract #03203012
Totals801029.450.00799461.5299.8

CountyBROOKS
HighwayUS 281
From0.9 MI S OF FM 3066
To3.1 MI N OF FM 755
CSJ0255-04-094
Proj IDC 255-4-94
Work TypeREHABILITATE ROADWAY
 
16.70817284414.2018426212.2399.9
Work Order12-07-18
Work Began07-30-19
Work Completed
Time Computed01-07-19
Contract Working Days240
Addl Days Granted0
Working Days Charged313
Percent Time Used130
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-04-094
WEST TEXAS ROCK RESOURCES, LLC (0.11)
PAVEMENT MARKINGS INC. (1.19)
GP7 CONSTRUCTION INC. (0.19)
Contract #11183017
Totals17284414.200.0018426212.2399.9

CountyBROOKS ETC
HighwayUS 281 ETC
From.75 MILES SOUTH OF FM 3066
To10.825 MILES SOUTH OF FM 3066
CSJ0255-04-099
Proj IDNH 2B20(153)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.0016056599.775732798.9794.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-20-20
Work Began01-11-21
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged168
Percent Time Used70
Contractor(s)
MASSANA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-04-099
TEXAS HIGHWAY SYSTEMS, INC. (0.81)
TEXAS ICON CONSTRUCTION, LLC (2.72)
Contract #07203022
Totals6056599.771090684.815732798.9794.6

CountyHIDALGO
HighwayUP 281
FromSH 336
ToSP 600
CSJ0255-09-094
Proj IDNH 2019(045)
Work TypeREHABILITATE ROADWAY
 
3.55422771150.7622235474.3497.6
CountyHIDALGO
HighwaySS 600
FromUS 281
ToEND OF STATE MAINTENANCE
CSJ0255-12-006
Proj IDCC 255-12-6
Work TypeREHABILITATE ROADWAY
 
0.2001211279.701211712.0599.9
Work Order10-22-18
Work Began01-21-19
Work Completed
Time Computed11-22-18
Contract Working Days440
Addl Days Granted0
Working Days Charged440
Percent Time Used100
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0255-09-094
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.89)
HIGHWAY BARRICADES AND SERVICES, LLC (1.35)
SOIL-TECH, INC. (0.13)
CERTIFIED PLACERS LLC (2.15)
GNH COMPANY LLC (1.41)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.35)
HOUSTON SAWING & DRILLING (0.31)
Contract #09183203
Totals23982430.469514.0123447186.3997.7

CountyKENEDY
HighwayUS 77
From1.34 MI N OF WILLACY/KENEDY C.L.
ToWILLACY/KENEDY COUNTY LINE
CSJ0327-05-042
Proj IDNH 1802(561)
Work TypeCONSTRUCT MAINLANES & OVERPASSES
 
1.3457192983.436769163.9794.1
CountyWILLACY
HighwayUS 77
FromWILLACY/KENEDY C.L.
To0.93 MI S OF WILLACY/KENEDY C.L.
CSJ0327-10-062
Proj IDNH 1802(561)
Work TypeCONSTRUCT MAINLANES & OVERPASSE
 
0.9428216284.277767912.0097.5
Work Order09-18-18
Work Began12-18-18
Work Completed
Time Computed10-18-18
Contract Working Days292
Addl Days Granted0
Working Days Charged484
Percent Time Used165
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0327-05-042
GP7 CONSTRUCTION INC. (6.35)
SOIL-TECH, INC. (1.79)
HIGHWAY BARRICADES AND SERVICES, LLC (0.89)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.58)
AARON CONCRETE CONTRACTORS, L.P. (1.88)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.20)
WEST TEXAS ROCK RESOURCES, LLC (0.03)
STRAIGHT LINE SAWING & SEALING, INC. (0.23)
SOIL TECH ADVANCE INC. (1.56)
PENHALL COMPANY (0.06)
G & E ESCOBEDO CONSTRUCTION, INC. (0.03)
SCOTT DERR PAINTING CO, LLC (0.16)
Contract #08183204
Totals15409267.7019354.9614537075.9795.9

CountyWILLACY
HighwayUS 77
From0.93 MI S OF WILLACY/KENEDY CL
ToBUSINESS 77
CSJ0327-10-057
Proj IDNH 1702(492)
Work TypeCONSTRUCT MAINLANES & OVERPASS
 
3.97722671108.1322638199.0799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-17
Work Began01-08-18
Work Completed
Time Computed00-00-00
Contract Working Days480
Addl Days Granted58
Working Days Charged681
Percent Time Used126
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0327-10-057
SOIL-TECH, INC (4.94)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.55)
AARON CONCRETE CONTRACTORS, L.P. (1.26)
WEST TEXAS RUMBLE STRIP (0.03)
PAVEMENT MARKINGS INC. (0.60)
LAREDO STRIPING INC. (3.89)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.08)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
SOIL TECH ADVANCE INC. (3.16)
GP7 CONSTRUCTION INC. (0.22)
SCOTT DERR PAINTING CO, LLC (0.12)
Contract #08173005
Totals22671108.13113454.0022638199.0799.9

CountyCAMERON
HighwaySH 100
FromS. MESQUITE ST.
To567 FT. EAST OF EBANO ST.
CSJ0331-01-052
Proj IDNH 2021(193)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.9004728315.841055666.2122.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-18-21
Work Began04-19-21
Work Completed
Time Computed00-00-00
Contract Working Days237
Addl Days Granted16
Working Days Charged97
Percent Time Used38
Contractor(s)
EARTHWORKS ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-052
GO UNDERGROUND, LIMITED LIABILITY COMPANY (2.44)
GP7 CONSTRUCTION INC. (0.77)
SOIL TECH ADVANCE INC. (0.34)
TEXAS HIGHWAY SYSTEMS, INC. (2.18)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.33)
PAVEMENT MARKINGS INC. (3.53)
Contract #11203202
Totals4728315.84145064.051055666.2122.3

CountyCAMERON
HighwayPR 100
FromAT QUEEN ISABELLA CAUSEWAY
ToSTR #:_0331-04-005
CSJ0331-04-069
Proj IDBR 2020(709)
Work TypeBRIDGE MAINTENANCE
 
2.6399814198.004030648.6241.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-09-20
Work Began10-19-20
Work Completed
Time Computed00-00-00
Contract Working Days576
Addl Days Granted0
Working Days Charged269
Percent Time Used46
Contractor(s)
SOUTHERN ROAD & BRIDGE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0331-04-069
MOBILE ENTERPRISES, INC. (3.60)
Contract #04203206
Totals9814198.00447578.934030648.6241.0

CountyHIDALGO
HighwaySH 107
From59TH STREET
ToSEAWALL BLVD
CSJ0342-01-074
Proj IDSTP 2019(085)
Work TypeCONST 6 LN DIV RURAL
 
7.07520492319.776322801.1830.8
CountyHIDALGO
HighwaySH 107
From0.7 MI W OF FM 2128
To0.4 MI W OF FM 2128
CSJ0342-01-088
Proj IDSTP 2019(084)HES
Work TypeSAFETY LIGHTING
 
1.101321205.000.000.0
CountyHIDALGO
HighwaySH 107
From@ FM 1423
To.
CSJ0342-01-089
Proj IDSTP 2019(084)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.200121038.600.000.0
CountyHIDALGO
HighwaySH 107
From@ FM 907
To.
CSJ0342-01-090
Proj IDSTP 2019(084)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.200169327.800.000.0
Work Order04-16-19
Work Began05-03-21
Work Completed
Time Computed05-25-20
Contract Working Days461
Addl Days Granted0
Working Days Charged123
Percent Time Used26
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0342-01-074
GP7 CONSTRUCTION INC. (13.50)
HIGHWAY BARRICADES AND SERVICES, LLC (1.85)
SOIL-TECH, INC. (0.54)
TRAF-TEX, INC. (6.59)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.03)
SOIL TECH ADVANCE INC. (0.54)
Contract #03193203
Totals21103891.17197683.476322801.1829.9

CountyHIDALGO
HighwaySH 107
FromWEST LEVEE
ToFM 1425
CSJ0342-02-054
Proj IDNH 1902(320)
Work TypeRER
 
4.55010978592.6610501690.5795.6
Work Order09-18-19
Work Began02-17-20
Work Completed
Time Computed01-01-20
Contract Working Days341
Addl Days Granted0
Working Days Charged309
Percent Time Used90
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0342-02-054
D&S TEXAS ICON CONSTRUCTION (3.03)
GP7 CONSTRUCTION INC. (6.94)
HIGHWAY BARRICADES AND SERVICES, LLC (2.14)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.61)
Contract #08193005
Totals10978592.660.0010501690.5795.6

CountyHIDALGO
HighwaySH 186
FromUS 281
ToHIDALGO/ WILLACY C.L.
CSJ0433-01-030
Proj IDSTP 1702(838)
Work TypeREHABILITATE ROADWAY_(SUPER 2)
 
9.50012133439.1012647784.2799.9
Work Order11-13-17
Work Began02-14-18
Work Completed
Time Computed12-13-17
Contract Working Days566
Addl Days Granted179
Working Days Charged802
Percent Time Used107
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0433-01-030
GULF COAST CONTRACTORS, INC. (1.34)
HIGHWAY BARRICADES AND SERVICES, LLC (3.28)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.67)
Contract #10173018
Totals12133439.10150409.3812647784.2799.9

CountyWILLACY
HighwaySH 186
FromHIDALGO/ WILLACY C.L.
ToKING ST
CSJ0433-02-052
Proj IDC 433-2-52
Work TypeREHABILITATE ROADWAY (SUPER 2)
 
12.29620899927.8512367151.6859.1
Work Order09-18-18
Work Began01-07-19
Work Completed
Time Computed10-18-18
Contract Working Days560
Addl Days Granted131
Working Days Charged644
Percent Time Used93
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0433-02-052
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.52)
HIGHWAY BARRICADES AND SERVICES, LLC (3.78)
GULF COAST CONTRACTORS, INC. (0.73)
Contract #08183008
Totals20899927.85273070.2912367151.6859.1

CountyWILLACY ETC
HighwaySH 186 ETC
FromFM 2209
ToN SHORE DR
CSJ0433-05-025
Proj IDC 433-5-25
Work TypeSEAL COAT
 
1.0074153227.610.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-23-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days84
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0433-05-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09213207
Totals4153227.610.000.000.0

CountyJIM HOGG ETC
HighwaySH 16 ETC
From0.22 MI S OF SIESTA RD.
ToJIM HOGG/ZAPATA COUNTY LINE
CSJ0517-06-036
Proj IDSTP 2B20(155)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
148.4144952063.281891483.2338.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-20
Work Began03-08-21
Work Completed
Time Computed00-00-00
Contract Working Days256
Addl Days Granted0
Working Days Charged167
Percent Time Used65
Contractor(s)
VECTOR UTILITIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0517-06-036
DEPENDABLE FENCE & WELDING CO. INC. (10.09)
HIGHWAY BARRICADES AND SERVICES, LLC (0.18)
TEXAS ICON CONSTRUCTION, LLC (30.18)
TERRA CONSTRUCTION LLC (6.87)
JMG CONCRETE INC (5.91)
TREBOL TRAFFIC SAFETY GROUP LLC (3.63)
Contract #08203016
Totals4952063.28105134.091891483.2338.1

CountyHIDALGO
HighwayFM 681
FromFM 681 (N) @ FM 2221
ToSH 107
CSJ0669-01-043
Proj IDSTP 2013(039)MM
Work TypeWIDEN TO 4 LANE DIVIDED URBAN
 
1.78412345193.5214672181.4299.9
CountyHIDALGO
HighwayFM 2221
From0.25 MI W OF SH 364 (LA HOMA)
To.25 MI W OF MOOREFIELD RD
CSJ0862-01-037
Proj IDSTP 2013(040)MM
Work TypeWIDEN TO 4 LANE DIVIDED
 
0.5742333144.962364800.1099.9
CountyHIDALGO
HighwayFM 2221
From0.25 MI W OF MOOREFIELD RD
ToFM 681
CSJ0862-01-047
Proj IDSTP 2013(039)MM
Work TypeWIDEN TO 4 LANE DIVIDED URBAN
 
0.3382162777.752249792.4699.9
Work Order08-19-13
Work Began09-04-13
Work Completed
Time Computed09-04-13
Contract Working Days540
Addl Days Granted57
Working Days Charged623
Percent Time Used104
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-043
GO UNDERGROUND, LIMITED LIABILITY COMPANY (20.85)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.29)
SOIL-TECH, INC. (1.94)
PAVEMENT MARKINGS INC. (1.01)
VALLEY INFRASTRUCTURE, INC. (10.14)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.76)
(INACTIVE)D&S TEXAS ICON CONSTRUCTION (1.06)
Contract #06133203
Totals16841116.230.0019286773.9899.9

CountyCAMERON
HighwayFM 511
From.4 MI S OF SH 4 STR#0684-02-007
ToOVER DRAINAGE DITCH
CSJ0684-02-014
Proj IDBR 2021(644)
Work TypeBRIDGE REPLACEMENT
 
1147081.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-22-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days131
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0684-02-014
HIGHWAY BARRICADES AND SERVICES, LLC (8.20)
Contract #06213229
Totals1147081.100.000.000.0

CountyCAMERON
HighwayFM 1732
FromUS 281
ToIH-69E
CSJ0684-03-022
Proj IDSTP 2B20(170)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.0006603453.603835148.5958.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-14-20
Work Began12-17-20
Work Completed
Time Computed00-00-00
Contract Working Days350
Addl Days Granted0
Working Days Charged193
Percent Time Used55
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0684-03-022
GP7 CONSTRUCTION INC. (3.86)
TRAF-TEX, INC. (2.30)
TEXAS ICON CONSTRUCTION, LLC (1.65)
HIGHWAY BARRICADES AND SERVICES, LLC (1.65)
Contract #07203220
Totals6603453.60381482.323835148.5958.0

CountyHIDALGO ETC
HighwayFM 88 ETC
From0.5 MI N OF MILE 9 N RD.
ToMILE 9 N RD.
CSJ0698-03-095
Proj IDSTP 2019(649)HES
Work TypeSAFETY LIGHTING
 
8.5081620585.001582519.3897.6
Work Order04-03-19
Work Began03-17-20
Work Completed
Time Computed03-17-21
Contract Working Days239
Addl Days Granted0
Working Days Charged224
Percent Time Used93
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0698-03-095
G & E ESCOBEDO CONSTRUCTION, INC. (4.50)
VALLEY STRIPING CORP. (2.63)
Contract #03193016
Totals1620585.000.001582519.3897.6

CountyHIDALGO
HighwayFM 88 ETC
FromMILE 12
ToIH-2
CSJ0698-03-099
Proj IDNH 2021(191)
Work TypeOVERLAY
 
1.2854998520.952027757.9740.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-05-21
Work Began10-12-21
Work Completed
Time Computed00-00-00
Contract Working Days98
Addl Days Granted0
Working Days Charged78
Percent Time Used79
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0698-03-099
HIGHWAY BARRICADES AND SERVICES, LLC (5.99)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.72)
Contract #11203232
Totals4998520.951667808.432027757.9740.5

CountyHIDALGO ETC
HighwayFM 490 ETC
From750 FT W OF JESUS FLORES RD.
To450 FT N OF JESUS FLORES RD.
CSJ0860-01-020
Proj IDSTP 2B20(156)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.6911006965.00811990.1080.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-08-20
Work Began03-29-21
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged146
Percent Time Used81
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0860-01-020
PAVEMENT MARKINGS INC. (1.43)
TEXAS HIGHWAY SYSTEMS, INC. (1.77)
G & E ESCOBEDO CONSTRUCTION, INC. (2.03)
Contract #08203245
Totals1006965.00145437.50811990.1080.6

page 1 | page 2 | page 3 | page 4