Monthly State Let Construction Report For Pharr District As Of Oct 16, 2017 Page 2 Of 3

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCAMERON
HighwayUS 281
FromFM 1421
ToFM 3248
CSJ0220-04-035
Proj IDSTP 2016(428)
Work TypeCONSTRUCT RURAL 4 LANE
 
5.42812496309.815609417.6944.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-31-16
Work Began06-27-14
Work Completed
Time Computed00-00-00
Contract Working Days460
Addl Days Granted0
Working Days Charged276
Percent Time Used60
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0220-04-035
GP7 CONSTRUCTION, INC. (12.81)
SOIL-TECH, INC. (1.08)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.68)
PAVEMENT MARKINGS INC. (1.27)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.38)
Contract #01163044
Totals12496309.81240372.475609417.6944.8

CountyCAMERON ETC
HighwaySH 48 ETC
FromBUS 77
ToUS 77
CSJ0220-05-069
Proj IDSTP 1702(829)
Work TypeOVERLAY
 
22.6775234721.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0220-05-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173023
Totals5234721.770.000.000.0

CountyHIDALGO
HighwayUS 281
From0.315 MI N OF SH 186
ToBROOKS/HIDALGO C.L.
CSJ0255-06-065
Proj IDNH 1502(262)
Work TypeSMA/OVERLAY (NB & SB LANES)
 
15.52016635027.8613802072.4182.9
CountyHIDALGO
HighwayUS 281
FromSH 186
To.315 MI N OF SH 186
CSJ0255-07-132
Proj IDNH 1502(262)
Work TypeSMA/OVERLAY (NB & SB LANES)
 
0.315261169.91166000.2563.5
Work Order11-24-15
Work Began10-04-16
Work Completed
Time Computed12-24-15
Contract Working Days280
Addl Days Granted0
Working Days Charged225
Percent Time Used80
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-06-065
WEST TEXAS RUMBLE STRIP (0.16)
DUSTROL, INC. (2.93)
HIGHWAY BARRICADES AND SERVICES, LLC (1.62)
J & P TRUCKING AND HAULING (1.46)
Contract #10153029
Totals16896197.771072402.3713968072.6682.6

CountyHIDALGO ETC
HighwayIH 69C ETC
FromSH 107
To3.052 MI N OF SH 107
CSJ0255-07-141
Proj IDNH 1702(836)
Work TypeSEAL COAT_(NB & SB FRONTAGE ROADS)
 
23.4101572940.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days79
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-07-141
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173228
Totals1572940.520.000.000.0

CountyHIDALGO
HighwayUS 281 ETC
FromRIDGE RD.
ToSP 600
CSJ0255-09-095
Proj IDNH 2017(123)
Work TypeOVERLAY
 
15.4544450423.062848115.8163.9
Work Order03-02-17
Work Began00-00-00
Work Completed
Time Computed04-02-17
Contract Working Days95
Addl Days Granted0
Working Days Charged80
Percent Time Used84
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0255-09-095
MUSTANG COLT SERVICES, INC. (3.83)
PAVEMENT MARKINGS INC. (5.89)
Contract #09163030
Totals4450423.062028.002848115.8163.9

CountyWILLACY
HighwayUS 77
From0.93 MI S OF WILLACY/KENEDY CL
ToBUSINESS 77
CSJ0327-10-057
Proj IDNH 1702(492)
Work TypeCONSTRUCT MAINLANES & OVERPASS
 
3.97722671108.130.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days480
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0327-10-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173005
Totals22671108.130.000.000.0

CountyWILLACY
HighwayIH 69E
FromCAMERON/WILLACY COUNTY LINE
ToFM 1018
CSJ0327-10-058
Proj IDNH 2017(047)
Work TypeOVERLAY (MAIN LANES)
 
1.000645473.55705340.4099.9
CountyWILLACY
HighwayIH 69E
FromFM 3168
ToBUS 77
CSJ0327-10-059
Proj IDNH 2017(047)
Work TypeOVERLAY (MAIN LANES)
 
1.0001365423.751486312.0399.9
CountyWILLACY
HighwayIH 69E
FromCAMERON/WILLACY COUNTY LINE
ToFM 1018
CSJ0327-10-060
Proj IDNH 2017(047)
Work TypeOVERLAY (FRONTAGE ROADS)
 
1.000592418.25597605.1299.9
CountyWILLACY
HighwayIH 69E
FromFM 3168
ToBUS 77
CSJ0327-10-061
Proj IDNH 2017(047)
Work TypeOVERLAY (FRONTAGE ROADS)
 
1.0001517081.481580438.7599.9
Work Order10-21-16
Work Began11-18-16
Work Completed
Time Computed11-18-16
Contract Working Days90
Addl Days Granted5
Working Days Charged92
Percent Time Used96
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0327-10-058
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.10)
DIAMOND SURFACE, INC. (0.37)
PAVEMENT MARKINGS INC. (5.33)
Contract #09163220
Totals4120397.030.004369696.3099.9

CountyCAMERON
HighwaySH 100
From4.0 EAST OF FM 1847
To6.27 MI EAST OF FM 1847
CSJ0331-01-044
Proj IDNH 1502(584)
Work TypeINSTALL WILDLIFE CROSSINGS
 
2.2532561306.502529885.9798.7
CountyCAMERON
HighwaySH 100
From6.27 MI EAST OF FM 1847
To1.75 MILES WEST OF FM 510
CSJ0331-02-052
Proj IDNH 1502(584)
Work TypeINSTALL WILDLIFE CROSSINGS
 
4.8183778680.753553671.3394.0
Work Order05-18-16
Work Began09-06-16
Work Completed
Time Computed05-31-16
Contract Working Days340
Addl Days Granted0
Working Days Charged259
Percent Time Used76
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-044
GP7 CONSTRUCTION, INC. (3.57)
SOIL-TECH, INC. (4.39)
TEXAS HIGHWAY SYSTEMS, INC. (0.01)
VALLEY STRIPING CORP. (1.13)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.07)
PENHALL COMPANY (AUSTIN) (0.17)
Contract #03163031
Totals6339987.2574256.606083557.3095.9

CountyCAMERON
HighwayPR 100
FromCITY OF SPI CONVENTION CENTER SOUTH
ToQUEEN ISABELA CAUSEWAY
CSJ0331-04-067
Proj IDSTP 2017(193)TAPS
Work TypeCONST. SIDEWALKS,RAMPS,CURBS
 
3.9303351562.06929230.5627.7
CountyCAMERON
HighwayCS
FromQUEEN ISABELA CAUSEWAY SOUTH_.67 MI
ToISLA BLANCA PARK ENTRANCE
CSJ0921-06-299
Proj IDSTP 2017(193)TAPS
Work TypeCONST. SIDEWALKS,RAMPS,CURBS
 
0.670100947.133657.203.6
Work Order03-16-17
Work Began05-02-17
Work Completed
Time Computed04-16-17
Contract Working Days316
Addl Days Granted0
Working Days Charged116
Percent Time Used36
Contractor(s)
REIM CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0331-04-067
SOIL-TECH, INC. (14.00)
GP7 CONSTRUCTION, INC. (23.08)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (7.12)
G & E ESCOBEDO CONSTRUCTION, INC. (2.82)
Contract #01173038
Totals3452509.19169592.15932887.7627.0

CountyCAMERON
HighwaySH 107
FromBUSINESS 77_(COMBES)
ToIH-69E
CSJ0342-04-032
Proj IDNH 2017(971)
Work TypeWIDEN TO 4 LANE UNDIVIDED C&G
 
0.4654313269.70464899.9010.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days285
Addl Days Granted0
Working Days Charged17
Percent Time Used5
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0342-04-032
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.65)
GP7 CONSTRUCTION, INC. (5.92)
GULF COAST CONTRACTORS, INC. (2.83)
PAVEMENT MARKINGS INC. (1.08)
VALLEY INFRASTRUCTURE, INC. (18.54)
Contract #04173209
Totals4313269.70464899.90464899.9010.7

CountyHIDALGO
HighwaySH 186
FromUS 281
ToHIDALGO/ WILLACY C.L.
CSJ0433-01-030
Proj IDSTP 1702(838)
Work TypeREHABILITATE ROADWAY_(SUPER 2)
 
9.50012133439.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days566
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0433-01-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173018
Totals12133439.100.000.000.0

CountyCAMERON
HighwaySH 345
FromFM 1561
ToFM 3462
CSJ0630-01-051
Proj IDSTP 1602(085)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
3.277296534.00453138.7099.9
Work Order06-06-16
Work Began08-03-16
Work Completed
Time Computed07-06-16
Contract Working Days80
Addl Days Granted35
Working Days Charged92
Percent Time Used80
Contractor(s)
VALLEY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0630-01-051
HIGHWAY BARRICADES AND SERVICES, LLC (2.91)
D & T CONSTRUCTION, INC. (12.72)
GULF COAST CONTRACTORS, INC. (3.68)
Contract #05163025
Totals296534.001749.80453138.7099.9

CountyCAMERON
HighwayFM 106
From@ RIO HONDO LIFT BRIDGE
To.
CSJ0630-02-041
Proj IDBR 1502(468)
Work TypeBRIDGE REHABILITATION
 
0.10012406043.3010343639.6283.3
Work Order10-30-15
Work Began00-00-00
Work Completed
Time Computed11-30-15
Contract Working Days651
Addl Days Granted0
Working Days Charged353
Percent Time Used54
Contractor(s)
PCL CIVIL CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0630-02-041
RHYNER CONSTRUCTION SERVICES, INC. (2.57)
TX TINMAN ENTERPRISES, LLC. (0.60)
HIGHWAY BARRICADES AND SERVICES, LLC (0.58)
FOREMOST PAVING, INC. (1.83)
S & S BRIDGE PAINTING, INC. (14.21)
FAITH TECHNOLOGIES, INC. (8.51)
RG PAINTING, INC. (0.64)
AIRS COMPANY, INC. (0.06)
Contract #07153019
Totals12406043.30627074.6510343639.6283.3

CountyHIDALGO
HighwayFM 681
FromFM 681 (N) @ FM 2221
ToSH 107
CSJ0669-01-043
Proj IDSTP 2013(039)MM
Work TypeWIDEN TO 4 LANE DIVIDED URBAN
 
1.78412345193.527843124.1263.5
CountyHIDALGO
HighwayFM 2221
From0.25 MI W OF SH 364 (LA HOMA)
To.25 MI W OF MOOREFIELD RD
CSJ0862-01-037
Proj IDSTP 2013(040)MM
Work TypeWIDEN TO 4 LANE DIVIDED
 
0.5742333144.96208459.608.9
CountyHIDALGO
HighwayFM 2221
From0.25 MI W OF MOOREFIELD RD
ToFM 681
CSJ0862-01-047
Proj IDSTP 2013(039)MM
Work TypeWIDEN TO 4 LANE DIVIDED URBAN
 
0.3382162777.75469592.4721.7
Work Order08-19-13
Work Began09-04-13
Work Completed
Time Computed09-04-13
Contract Working Days540
Addl Days Granted0
Working Days Charged83
Percent Time Used15
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-043
GO UNDERGROUND, LIMITED LIABILITY COMPANY (20.85)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.29)
SOIL-TECH, INC. (1.94)
PAVEMENT MARKINGS INC. (1.01)
VALLEY INFRASTRUCTURE, INC. (10.14)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.76)
Contract #06133203
Totals16841116.23260222.198521176.1950.5

CountyHIDALGO
HighwayFM 681
From1.66 MILES NORTH OF FM 2058
To0.02 MILES SOUTH OF FM 1925
CSJ0669-01-049
Proj IDSTP 2017(317)
Work TypeREHABILITATE ROADWAY
 
8.2088889677.742280762.2225.6
Work Order01-17-17
Work Began06-05-17
Work Completed
Time Computed02-17-17
Contract Working Days576
Addl Days Granted0
Working Days Charged110
Percent Time Used19
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-049
HIGHWAY BARRICADES AND SERVICES, LLC (3.46)
D&S TEXAS ICON CONSTRUCTION (0.81)
L & R PRECAST CONCRETE WORKS, INC. (1.21)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (DONNA) (0.69)
Contract #12163023
Totals8889677.74171882.952280762.2225.6

CountyHIDALGO
HighwayFM 88
FromSH 107, SOUTH
To0.25 MI N OF MILE 16 N
CSJ0698-03-084
Proj IDSTP 2012(699)MM
Work TypeWIDEN TO 4 LANE DIVIDED
 
0.2492681776.782617292.6099.9
CountyHIDALGO
HighwayFM 88
FromSH 107, SOUTH
To0.25 MI. N. OF MIE 16 N
CSJ0698-03-086
Proj IDRW 0698-3-86
Work TypeROW ACQUISITION
 
0.249467213.71586195.3699.9
Work Order01-03-13
Work Began04-09-13
Work Completed
Time Computed01-19-13
Contract Working Days164
Addl Days Granted0
Working Days Charged379
Percent Time Used231
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0698-03-084
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.44)
VALLEY STRIPING CORP. (1.43)
SOIL-TECH, INC. (0.07)
Contract #09123235
Totals3148990.4912950.003203487.9699.9

CountyHIDALGO
HighwayFM 493
FromCHAMPION ST.
ToUS 281
CSJ0863-01-047
Proj IDHP 2014(907)
Work TypeRECONSTRUCT & ADD SHOULDERS
 
5.68111333645.324293236.5737.8
CountyHIDALGO
HighwayFM 493
FromBUSINESS 83
ToCHAMPION AVE
CSJ0863-01-053
Proj IDHP 2014(907)
Work TypeOVERLAY
 
0.768579679.560.000.0
CountyZERO COUNTIES
Highway
From
To
CSJ0863-01-057
Proj ID
Work Type
 
0.00257988.350.0
Work Order09-09-14
Work Began07-13-15
Work Completed
Time Computed09-25-14
Contract Working Days480
Addl Days Granted0
Working Days Charged246
Percent Time Used51
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0863-01-047
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.32)
PAVEMENT MARKINGS INC. (1.32)
LAREDO STRIPING INC. (1.35)
SOIL-TECH, INC. (4.05)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.03)
Contract #07143208
Totals11913324.88102462.874551224.9238.2

CountyHIDALGO
HighwayCS
FromON OWASSA RD, FROM JACKSON RD
ToI 69-C
CSJ0921-02-140
Proj IDSTP 2008(328)MM
Work TypeRECONSTRUCTION AND WIDENING
 
1.1004819279.372737898.1856.8
CountyHIDALGO
HighwayCS
FromON OWASSA RD, FROM JACKSON RD
ToI 69-C
CSJ0921-02-357
Proj IDSTP 2017(218)
Work TypeROW ACQUISITION
 
1.100386829.00345559.0089.3
Work Order02-22-17
Work Began05-17-17
Work Completed
Time Computed03-22-17
Contract Working Days440
Addl Days Granted0
Working Days Charged121
Percent Time Used27
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-140
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.99)
SOIL-TECH, INC. (0.26)
SALAZAR UTILITY CONSTRUCTION INC. (0.44)
VALLEY STRIPING CORP. (1.06)
Contract #01173031
Totals5206108.37317415.033083457.1859.2

CountyHIDALGO
HighwayCS
FromMILE 2 WEST, FROM MILE 12 NORTH
To.44 MI NORTH OF US 83
CSJ0921-02-170
Proj IDHP 2008(128)
Work TypeRECONSTRUCT & WIDEN TO 2 LN RDWY
 
4.7504729717.444574502.31100.0
CountyHIDALGO
HighwayCS
FromON MILE 2 NORTH,.44 MI N OF US 83
ToUS 83
CSJ0921-02-307
Proj IDHP 2008(128)
Work TypeRECONSTRUCT & WIDEN TO 2 LN RDWY
 
0.440744320.06706892.25100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-26-13
Work Began12-16-13
Work Completed08-30-17
Time Computed07-12-13
Contract Working Days480
Addl Days Granted6
Working Days Charged427
Percent Time Used87
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-170
GO UNDERGROUND, LIMITED LIABILITY COMPANY (12.90)
SOIL-TECH, INC. (6.29)
PAVEMENT MARKINGS INC. (0.92)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.48)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.68)
Contract #04133203
Totals5474037.500.005281394.56100.0

CountyHIDALGO
HighwayVA
FromUS CUSTOMS PORT OF ENTRY EXIT
ToUS 281
CSJ0921-02-173
Proj IDBOR 2002(632)
Work TypeCONSTRUCT BSIF
 
1.35020116428.4517566408.9287.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-11
Work Began10-18-11
Work Completed
Time Computed09-10-11
Contract Working Days380
Addl Days Granted115
Working Days Charged495
Percent Time Used100
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-173
BULLARD CONSTRUCTION, INC. (19.38)
HIGHWAY TECHNOLOGIES, INC. (1.61)
HURRICANE FENCE COMPANY (0.96)
METTLER TOTLEDO (5.03)
NORTH TEXAS REBAR, LLC (0.54)
ROVAN, LLC (3.33)
SOIL-TECH, INC. (1.21)
STAR OPERATIONS, INC. (19.28)
TSI LABORATORIES SOUTH,INC. (0.04)
RGV ALLIANCE CONSTRUCTION, LLC (0.54)
FOREMOST PAVING, INC. (9.34)
CONTINENTAL REFRIGERATION (1.12)
M & A PAINTING SERVICE, INC. (0.39)
L & G CONCRETE CONSTRUCTION, INC. (3.86)
SOUTHERN STEEL FABRICATORS (4.27)
CANTU"S PLUMBING (0.88)
METRO ELECTRIC, INC. (1.81)
ROUND ROCK INDUSTRIAL EQUIPMENT COMPANY, INC. (0.07)
INTERTECH FLOORING (0.33)
WEIGHT AND TEST SOLUTIONS, INC. (0.70)
RGV ALLIANCE CONSTRUCTION, LLC (0.12)
MCALLEN PEST CONTROL (0.03)
THE CABINET SHOP (0.24)
PRIME CONSTRUCTION (0.10)
TAYLOR LIGHTNING PROTECTION (0.14)
TAMU, DBA CONSTRUCTION SPECIALTIES (0.37)
T & D SOLUTIONS, LTD (0.87)
Contract #07113207
Totals20116428.450.0017566408.9287.3

page 1 | page 2 | page 3