Monthly State Let Construction Report For Pharr District As Of Dec 07, 2021 Page 3 Of 4

Last Update: Wednesday, December 08, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
HighwayFM 2221
From0.1 MILES WEST OF FM 492
To0.33 MILES WEST OF SH 364
CSJ0862-01-059
Proj IDC 862-1-59
Work TypeREHABILITATION OF EXISTING ROAD
 
1.2503118299.071657557.4053.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-08-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days279
Addl Days Granted0
Working Days Charged120
Percent Time Used43
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0862-01-059
HIGHWAY BARRICADES AND SERVICES, LLC (1.90)
TRAF-TEX, INC. (5.07)
SOIL TECH ADVANCE INC. (0.98)
DUSTROL, INC. (1.64)
Contract #03213207
Totals3118299.07252989.371657557.4053.1

CountyHIDALGO
HighwayFM 493
FromCHAMPION ST.
ToUS 281
CSJ0863-01-047
Proj IDHP 2014(907)
Work TypeRECONSTRUCT & ADD SHOULDERS
 
5.68111333645.3214541330.2899.9
CountyHIDALGO
HighwayFM 493
FromBUSINESS 83
ToCHAMPION AVE
CSJ0863-01-053
Proj IDHP 2014(907)
Work TypeOVERLAY
 
0.768579679.561090198.7499.9
CountyZERO COUNTIES
Highway
From
To
CSJ0863-01-057
Proj ID
Work Type
 
0.001732905.520.0
Work Order09-09-14
Work Began07-13-15
Work Completed
Time Computed04-12-19
Contract Working Days480
Addl Days Granted374
Working Days Charged856
Percent Time Used100
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0863-01-047
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.32)
PAVEMENT MARKINGS INC. (1.32)
LAREDO STRIPING INC. (1.35)
SOIL-TECH, INC. (4.05)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.03)
Contract #07143208
Totals11913324.8833923.2817364434.5499.9

CountyHIDALGO
HighwaySH 495 ETC
FromFM 3362
ToFM 1426
CSJ0865-01-112
Proj IDNH 2020(111)
Work TypeOVERLAY
 
12.3759895598.428743342.4490.1
Work Order01-14-20
Work Began04-13-20
Work Completed
Time Computed02-14-20
Contract Working Days105
Addl Days Granted0
Working Days Charged267
Percent Time Used254
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0865-01-112
HIGHWAY BARRICADES AND SERVICES, LLC (3.51)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.78)
IOC COMPANY LLC (11.97)
Contract #11193211
Totals9895598.4215327.488743342.4490.1

CountyHIDALGO
HighwayVA
FromUS CUSTOMS PORT OF ENTRY EXIT
ToUS 281
CSJ0921-02-173
Proj IDBOR 2002(632)
Work TypeCONSTRUCT BSIF
 
1.35020116428.4520434846.9699.9
Work Order08-25-11
Work Began10-18-11
Work Completed
Time Computed09-10-11
Contract Working Days380
Addl Days Granted461
Working Days Charged823
Percent Time Used97
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-173
BULLARD CONSTRUCTION, INC. (19.38)
HIGHWAY TECHNOLOGIES, INC. (1.61)
HURRICANE FENCE COMPANY (0.96)
METTLER TOTLEDO (5.03)
NORTH TEXAS REBAR, LLC (0.54)
ROVAN, LLC (3.33)
SOIL-TECH, INC. (1.21)
STAR OPERATIONS, INC. (19.28)
TSI LABORATORIES SOUTH,INC. (0.04)
RGV ALLIANCE CONSTRUCTION, LLC (0.54)
FOREMOST PAVING, INC. (9.34)
CONTINENTAL REFRIGERATION (1.12)
M & A PAINTING SERVICE, INC. (0.39)
L & G CONCRETE CONSTRUCTION, INC. (3.86)
SOUTHERN STEEL FABRICATORS (4.27)
CANTU"S PLUMBING (0.88)
METRO ELECTRIC, INC. (1.81)
ROUND ROCK INDUSTRIAL EQUIPMENT COMPANY, INC. (0.07)
INTERTECH FLOORING (0.33)
WEIGHT AND TEST SOLUTIONS, INC. (0.70)
RGV ALLIANCE CONSTRUCTION, LLC (0.12)
MCALLEN PEST CONTROL (0.03)
THE CABINET SHOP (0.24)
PRIME CONSTRUCTION (0.10)
TAYLOR LIGHTNING PROTECTION (0.14)
TAMU, DBA CONSTRUCTION SPECIALTIES (0.37)
T & D SOLUTIONS, LTD (0.87)
THE LEVY COMPANY, INC. (0.08)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.16)
Contract #07113207
Totals20116428.45106189.1520434846.9699.9

CountyHIDALGO
HighwayCR
FromSTR #AA06-53-001 @ S FLOODWAY CHANL
To.40 MI E OF FM 907
CSJ0921-02-252
Proj IDBR 2010(761)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.080635348.47642890.9299.9
CountyBROOKS
HighwayCR
FromCR 113
ToOVER LOS OLMOS CREEK
CSJ0921-22-003
Proj IDBR 2012(630)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.087332099.50353495.2399.9
Work Order12-20-16
Work Began05-02-19
Work Completed
Time Computed01-20-17
Contract Working Days173
Addl Days Granted3
Working Days Charged229
Percent Time Used130
Contractor(s)
REIM CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-252
GREGORY PILE DRIVING, INC. (10.74)
SOIL-TECH, INC. (0.91)
PAVEMENT MARKINGS INC. (0.81)
CERTIFIED PLACERS LLC (0.92)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (4.15)
FOREMOST PAVING, INC. (7.73)
H & S CONSTRUCTORS, INC. (0.54)
Contract #07163220
Totals967447.970.00996386.1599.9

CountyHIDALGO
HighwayCR
FromVARIOUS
ToVARIOUS
CSJ0921-02-465
Proj IDC 921-2-465
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5092399.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-14-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days160
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-465
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213221
Totals5092399.000.000.000.0

CountyCAMERON
HighwayCS
FromS. PARALLEL CORRIDOR, FM 509 (PASO REAL)
ToFM 2520 (SAM HOUSTON RD)
CSJ0921-06-252
Proj IDCBI 2022(173)
Work TypeNEW LOCATION NON-FREEWAY
 
3.0609511089.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days376
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-252
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12213011
Totals9511089.360.000.000.0

CountyCAMERON
HighwayFM 1846
FromSAN JOSE RANCH ROAD
ToBUS 77
CSJ1065-02-039
Proj IDF 2022(108)
Work TypeREHABILITATION OF EXISTING ROAD
 
3889216.020.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days206
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1065-02-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213211
Totals3889216.020.000.000.0

CountyCAMERON
HighwayFM 802
FromFM 1847
ToOLD PORT ISABEL RD.
CSJ1140-02-038
Proj IDNH 2B20(157)
Work TypeWIDEN NON-FREEWAY
 
6262978.184340388.3469.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-20
Work Began01-04-21
Work Completed
Time Computed00-00-00
Contract Working Days230
Addl Days Granted0
Working Days Charged218
Percent Time Used94
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1140-02-038
HIGHWAY BARRICADES AND SERVICES, LLC (1.58)
GREGORY PILE DRIVING, INC. (0.89)
DUSTROL, INC. (0.70)
TRAF-TEX, INC. (4.77)
EXTERIOR DESIGNS (1.30)
PURLITO, INC. (0.35)
G & E ESCOBEDO CONSTRUCTION, INC. (0.00)
MUNOZ FOUNDATION DRILLING, INC. (0.25)
Contract #08203218
Totals6262978.18284682.584340388.3469.3

CountyJIM HOGG ETC
HighwayFM 1017 ETC
FromSH 285
ToJIM HOGG/STARR C.L.
CSJ1227-01-027
Proj IDSTP 2021(073)
Work TypeSEAL COAT
 
21.0715725978.986126885.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-20
Work Began04-06-21
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged102
Percent Time Used100
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1227-01-027
PAVEMENT MARKINGS INC. (22.67)
CLARK CONSTRUCTION OF TEXAS, INC. (1.33)
FLASHER EQUIPMENT COMPANY (1.07)
Contract #09203035
Totals5725978.9818098.256126885.6099.9

CountyHIDALGO ETC
HighwayFM 1017 ETC
FromHIDALGO/STARR C.L.
ToUS 281
CSJ1227-04-022
Proj IDSTP 2021(072)
Work TypeSEAL COAT
 
6.8115380487.175377815.2899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-20
Work Began04-13-21
Work Completed
Time Computed00-00-00
Contract Working Days93
Addl Days Granted0
Working Days Charged93
Percent Time Used100
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1227-04-022
PAVEMENT MARKINGS INC. (25.54)
CLARK CONSTRUCTION OF TEXAS, INC. (9.79)
FLASHER EQUIPMENT COMPANY (1.61)
Contract #09203034
Totals5380487.170.005377815.2899.9

CountyWILLACY
HighwayFM 1018
FromIH-69E NB FRONTAGE RD.
ToFM 1420
CSJ1236-01-015
Proj IDF 2021(843)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
12.37512441758.7096599.840.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days379
Addl Days Granted0
Working Days Charged10
Percent Time Used2
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1236-01-015
GP7 CONSTRUCTION INC. (6.65)
HIGHWAY BARRICADES AND SERVICES, LLC (3.08)
SOIL TECH ADVANCE INC. (4.30)
Contract #08213009
Totals12441758.7096599.8496599.840.7

CountyHIDALGO ETC
HighwayFM 1423 ETC
FromIH-2
ToBUS 83
CSJ1427-01-040
Proj IDSTP 2021(370)
Work TypeOVERLAY
 
7.7085388775.405783970.9399.9
Work Order04-01-21
Work Began05-24-21
Work Completed
Time Computed05-17-21
Contract Working Days100
Addl Days Granted0
Working Days Charged112
Percent Time Used112
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 1427-01-040
HIGHWAY BARRICADES AND SERVICES, LLC (7.53)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.37)
GULF COAST CONTRACTORS, INC. (0.27)
ROCKIN C MILLING (0.73)
Contract #02213203
Totals5388775.40764095.905783970.9399.9

CountyCAMERON
HighwayFM 1847
FromFM 510
ToFM 2893
CSJ1801-01-050
Proj IDSTP 1902(311)
Work TypeRER
 
1.5153568743.953507299.2198.2
CountyCAMERON
HighwayFM 1847
FromFM 106
ToFM 510
CSJ1801-02-017
Proj IDSTP 1902(311)
Work TypeRER
 
6.05416421154.1014410548.6987.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-19
Work Began02-04-20
Work Completed
Time Computed00-00-00
Contract Working Days480
Addl Days Granted11
Working Days Charged410
Percent Time Used83
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1801-01-050
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.08)
HURRICANE FENCE COMPANY (1.44)
GP7 CONSTRUCTION L.L.C. (2.71)
GO UNDERGROUND, LIMITED LIABILITY COMPANY (7.26)
SOIL TECH ADVANCE INC. (2.52)
HIGHWAY BARRICADES AND SERVICES, LLC (1.17)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.02)
GP7 CONSTRUCTION INC. (2.71)
DUSTROL, INC. (0.07)
TEXAS ICON CONSTRUCTION, LLC (2.32)
Contract #08193205
Totals19989898.05629553.0617917847.9089.6

CountyCAMERON ETC
HighwayFM 1847 ETC
FromFM 2893
ToSH 550
CSJ1801-01-051
Proj IDC 1801-1-51
Work TypeSEAL COAT
 
3.0834751671.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days84
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1801-01-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09213025
Totals4751671.800.000.000.0

CountyHIDALGO
HighwaySS 115
FromLUCILLE RD.
ToFM 3072 (DICKER RD.)
CSJ1804-01-078
Proj IDC 1804-1-78
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
338037.60230094.1368.0
Work Order09-16-20
Work Began11-02-20
Work Completed
Time Computed11-02-20
Contract Working Days75
Addl Days Granted0
Working Days Charged67
Percent Time Used89
Contractor(s)
LUCANIA CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1804-01-078
TEXAS HIGHWAY SYSTEMS, INC. (8.91)
GULF COAST CONTRACTORS, INC. (62.74)
GREEN THUMB LAWN AND SPECIAL SERVICES (0.00)
MVP INSTALLATIONS, L.P. (0.00)
G & E ESCOBEDO CONSTRUCTION, INC. (0.00)
Contract #08203056
Totals338037.602900.00230094.1368.0

CountyHIDALGO
HighwaySS 115
FromON SS 115NB @ HACKNEY LAKE FLOODWAY
ToSTR #:_1804-01-006
CSJ1804-01-079
Proj IDBR 1902(310)
Work TypeBRIDGE REPLACEMENT
 
905746.36728289.6896.4
CountyHIDALGO
HighwaySS 115
FromON SS 115SB @ HACKNEY LAKE FLOODWAY
ToSTR #:_1804-01-007
CSJ1804-01-080
Proj IDBR 1902(319)
Work TypeBRIDGE REPLACEMENT
 
854961.27870618.7199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-17-19
Work Began02-18-20
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted3
Working Days Charged288
Percent Time Used279
Contractor(s)
CLORE EQUIPMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 1804-01-079
VALLEY STRIPING CORP. (3.12)
CLORE CONSTRUCTION LLC (59.98)
HIGHWAY BARRICADES AND SERVICES, LLC (0.84)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (2.24)
SOIL TECH ADVANCE INC. (0.06)
CERTIFIED PLACERS LLC (0.51)
Contract #08193030
Totals1760707.630.001598908.3999.0

CountyHIDALGO
HighwayFM 2220
FromMILE 5 ROAD
ToFM 1924
CSJ2094-01-038
Proj IDSTP 1602(275)MM
Work TypeWIDEN TO 6 LANE
 
2.17311694140.7913280071.5299.9
CountyHIDALGO
HighwayFM 2220
FromMILE 5 ROAD
ToFM 1924
CSJ2094-01-044
Proj IDSTP 2016(795)
Work TypeROW ACQ., RELOC. ASSIST.; UTL ADJS
 
2.000598725.50496253.0082.8
Work Order08-10-18
Work Began09-24-18
Work Completed
Time Computed09-10-18
Contract Working Days604
Addl Days Granted0
Working Days Charged561
Percent Time Used92
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 2094-01-038
HIGHWAY BARRICADES AND SERVICES, LLC (1.19)
THE LEVY COMPANY, INC. (5.28)
(INACTIVE)SOUTH TEXAS PAINTING COMPANY (0.05)
EXTERIOR DESIGNS (0.65)
AMERICAN FENCE COMPANY, INC. (0.05)
SALAZAR UTILITY CONSTRUCTION INC. (2.70)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.23)
AZTEC HOUSE LEVELING AND REMODELING (0.25)
W.O.E. CONSTRUCTION, INC. (0.19)
CERTIFIED PLACERS LLC (0.05)
Contract #06183008
Totals12292866.2967888.4613776324.5299.9

CountyCAMERON
HighwayFM 106
FromFM 1847 ON GEN BRANT RD, E & S
ToFM 510
CSJ2243-01-009
Proj IDC 2243-1-9
Work TypeGR, STRS & SURF
 
11.44015555190.8915161170.8099.9
Work Order10-28-14
Work Began11-09-15
Work Completed
Time Computed11-09-15
Contract Working Days420
Addl Days Granted111
Working Days Charged920
Percent Time Used173
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2243-01-009
ALTUS TRAFFIC MANAGEMENT LLC (0.39)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.29)
HIGHWAY BARRICADES AND SERVICES, LLC (0.46)
HURFCO INDUSTRIES, INC. DBA HURRICANE FENCE COMPANY (3.11)
J & P TRUCKING AND HAULING (17.32)
LAREDO STRIPING INC. (0.37)
GULF COAST CONTRACTORS, INC. (1.91)
EZ FENCE (0.39)
R. M. WALSDORF, INC. (1.79)
GUERRA CONSTRUCTION COMPANY (0.00)
DUSTROL, INC. (0.02)
Contract #09143004
Totals15555190.89105282.3115161170.8099.9

CountyHIDALGO
HighwayFM 3072
FromFM 2061
ToVETERANS RD
CSJ3098-01-016
Proj IDC 3098-1-16
Work TypeREHABILITATION OF EXISTING ROAD
 
6196267.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-17-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days196
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3098-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213002
Totals6196267.700.000.000.0

page 1 | page 2 | page 3 | page 4