Monthly Local Let Maintenance Report For Pharr District As Of Apr 12, 2024 Page 1 Of 2

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
HighwaySH0107
FromVARIOUS MAINTENANCE OFFICES
ToEDCOUCH, MISSION AND RAYMONDVILLE MNT
CSJ6192-98-001
Proj IDRMC - 619298001
Work TypeJANITORIAL MAINTENANCE
 
0.01038499.840.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days974
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RENFRO CONTRACT SERVICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6192-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11092101
Totals38499.840.000.000.0

CountyJIM HOGG
HighwaySH0016
FromVARIOUS LIMITS
ToVARIOUS COUNTIES
CSJ6193-07-001
Proj IDSUP - 619307001
Work TypeFIREBREAK MAINTENANCE
 
0.01074049.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days457
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6193-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04092146
Totals74049.360.000.000.0

CountyJIM HOGG
HighwayFM1017
From004, 006, 008, 009
ToVARIOUS ROADWAYS
CSJ6212-33-001
Proj IDSUP - 621233001
Work TypeFIREBREAK MAINTENANCE
 
0.01037906.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6212-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09102138
Totals37906.220.000.000.0

CountyCAMERON
HighwayUS0077
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6376-17-001
Proj IDSUP - 637617001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010584184.00433164.0074.1
Work Order08-11-21
Work Began09-07-21
Work Completed
Time Computed09-07-21
Contract Working Days730
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-17-001
RGR INDUSTRIES, INC. (0.00)
Contract #08212135
Totals584184.000.00433164.0074.1

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6396-99-001
Proj IDSUP - 639699001
Work TypeDRAINAGE SYSTEM CLEANING
 
0.010591300.00123690.0020.9
Work Order08-23-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged578
Percent Time Used79
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-99-001
RGR INDUSTRIES, INC. (0.00)
Contract #08222103
Totals591300.000.00123690.0020.9

CountyHIDALGO
HighwayIH0002
FromEDCOUCH/ MISSION MAINTENANCE
ToRAYMONDVILLE MAINTENANCE
CSJ6397-00-001
Proj IDSUP - 639700001
Work TypeJANITORIAL MAINTENANCE
 
0.01061321.8040189.7365.5
Work Order08-19-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged578
Percent Time Used79
Contractor(s)
WORKQUEST
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6397-00-001
GOODWILL INDUSTRIES OF SOUTH TEXAS, (0.00)
Contract #08222104
Totals61321.802044.0640189.7365.5

CountyCAMERON
HighwayUS0281
FromBROWNSVILLE MAINTENANCE BOUNDARY
ToCAMERON COUNTY
CSJ6397-14-001
Proj IDMMC - 639714001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010348595.00589756.39100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-22
Work Completed08-31-23
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged360
Percent Time Used100
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6397-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03222104
Totals348595.000.00589756.39100.0

CountyCAMERON
HighwayUS0077
FromSAN BENITO MAINTENANCE
ToSAN BENITO AREA OFFICE
CSJ6397-51-001
Proj IDSUP - 639751001
Work TypeJANITORIAL MAINTENANCE
 
0.01058602.5446950.8780.1
Work Order08-16-22
Work Began09-02-22
Work Completed
Time Computed09-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged578
Percent Time Used79
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6397-51-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08222130
Totals58602.541884.5846950.8780.1

CountyCAMERON
HighwayIH0069E
FromIH 2, IH 69E/ IH 2 INTERCHANGE
ToCAMERON COUNTY
CSJ6400-80-001
Proj IDSUP - 640080001
Work TypeLANDSCAPE MAINTENANCE
 
0.010364202.00212072.0058.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-24-23
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged402
Percent Time Used54
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6400-80-001
RGR INDUSTRIES, INC. (0.00)
Contract #10222137
Totals364202.0015148.00212072.0058.2

CountyCAMERON
HighwayIH0069E
FromHIDALGO AND CAMERON COUNTY
ToBROWNSVILLE, HIDALGO & SAN BENITO
CSJ6400-81-001
Proj IDSUP - 640081001
Work TypeGROUNDS MAINTENANCE
 
0.01038823.3629117.5275.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged547
Percent Time Used74
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6400-81-001
RGR INDUSTRIES, INC. (0.00)
Contract #08222101
Totals38823.361617.6429117.5275.0

CountyHIDALGO
HighwayIH0002
FromIH2, IH 69E, IH 69C, US 281
ToHIDALGO AND CAMERON COUNTY
CSJ6400-82-001
Proj IDSUP - 640082001
Work TypeDEBRIS REMOVAL
 
0.010549994.72436919.8379.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-19-22
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged578
Percent Time Used79
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6400-82-001
RGR INDUSTRIES, INC. (0.00)
Contract #08222139
Totals549994.7223132.02436919.8379.4

CountyHIDALGO
HighwayIH0002
FromPHARR DISTRICT COMPLEX
ToPHARR AREA/MAINTENACE OFFICE
CSJ6400-83-001
Proj IDSUP - 640083001
Work TypeJANITORIAL MAINTENANCE
 
0.010269848.92193183.3571.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged578
Percent Time Used79
Contractor(s)
WORKQUEST
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6400-83-001
E.Q.U.I.P. ENTERPRISES (0.00)
Contract #08222138
Totals269848.9210201.65193183.3571.5

CountyCAMERON
HighwayUS0281
FromCITY OF BROWNSVILLE
ToVARIOUS ROADWAYS
CSJ6414-47-001
Proj IDMMA - 641447001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.01086160.0068210.0079.1
Work Order08-19-22
Work Began08-24-22
Work Completed
Time Computed09-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged578
Percent Time Used79
Contractor(s)
CITY OF BROWNSVILLE
SUBCONTRACTOR(S) FOR CCSJ: 6414-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08222131
Totals86160.003590.0068210.0079.1

CountyCAMERON
HighwayBU0077W
FromCITY OF HARLINGEN
ToVARIOUS ROADWAYS
CSJ6414-49-001
Proj IDMMA - 641449001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.01099600.0078850.0079.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-24-22
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged578
Percent Time Used79
Contractor(s)
CITY OF HARLINGEN
SUBCONTRACTOR(S) FOR CCSJ: 6414-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08222132
Totals99600.004150.0078850.0079.1

CountyCAMERON
HighwaySH0004
From1000' LF WEST OF MASSEY WAY
ToSTARBASE WEST ACCESS ROAD
CSJ6427-51-001
Proj IDEMC - 642751001
Work TypeREHABILITATION OF EXISTING ROADWAY
 
0.0109489785.409522305.20100.0
Work Order12-27-22
Work Began01-01-23
Work Completed11-30-23
Time Computed01-02-23
Contract Working Days120
Addl Days Granted20
Working Days Charged125
Percent Time Used89
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6427-51-001
GP7 CONSTRUCTION INC. (2.47)
PAVEMENT MARKINGS INC. (1.67)
Contract #12222150
Totals9489785.400.009522305.20100.0

CountyHIDALGO
HighwaySH0495
FromHIDALGO COUNTY
ToVARIOUS ROADWAYS
CSJ6432-78-001
Proj IDSUP - 643278001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010767174.00188113.1024.5
Work Order08-16-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6432-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232139
Totals767174.0028309.50188113.1024.5

CountyHIDALGO
HighwaySH0495
FromHIDALGO COUNTY
ToVARIOUS ROADWAYS
CSJ6432-80-001
Proj IDSUP - 643280001
Work TypeCRASH CUSHION ATTENUATOR REPAIR
 
0.010800150.00130025.0016.2
Work Order08-29-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6432-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232138
Totals800150.000.00130025.0016.2

CountyHIDALGO
HighwayIH0069C
FromVARIOUS ROADWAYS
ToHIDALGO COUNTY
CSJ6433-28-001
Proj IDSUP - 643328001
Work TypeLITTER REMOVAL
 
0.010278694.0046096.7516.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged213
Percent Time Used29
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232131
Totals278694.0019464.7546096.7516.5

CountyCAMERON
HighwayIH0069E
FromSAN BENITO AREA OFFICE
ToSAN BENITO MAINTENANCE OFFICE
CSJ6433-32-001
Proj IDSUP - 643332001
Work TypeSTATE USE CONTRACT
 
0.01058780.8015274.5325.9
Work Order09-01-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days731
Addl Days Granted0
Working Days Charged213
Percent Time Used29
Contractor(s)
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232133
Totals58780.802373.8415274.5325.9

CountySTARR
HighwayUS0083
FromVARIOUS LOCATIONS IN STARR AND JIM HOGG
ToROMA AND HEBBRONVILLE MAINTENANCE
CSJ6433-34-001
Proj IDSUP - 643334001
Work TypeCRASH CUSHION ATTENUATOR REPAIR
 
0.010261565.004850.001.8
Work Order08-31-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232130
Totals261565.000.004850.001.8

page 1 | page 2