Monthly Local Let Maintenance Report For Pharr District As Of Dec 07, 2021 Page 2 Of 3

Last Update: Wednesday, December 08, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
HighwaySH0495
FromHIDALGO COUNTY
ToVARIOUS ROADWAYS
CSJ6376-20-001
Proj IDSUP - 637620001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010760261.2559774.687.8
Work Order08-17-21
Work Began09-10-21
Work Completed
Time Computed09-10-21
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-20-001
RGR INDUSTRIES, INC. (0.00)
Contract #08212139
Totals760261.2513247.0559774.687.8

CountyCAMERON
HighwayIH0069E
FromSAN BENITO AREA OFFICE
ToSAN BENITO MAINTENANCE OFFICE
CSJ6376-76-001
Proj IDSUP - 637676001
Work TypeSTATE USE CONTRACT
 
0.01056617.606883.2612.1
Work Order09-01-21
Work Began09-01-21
Work Completed
Time Computed09-01-21
Contract Working Days730
Addl Days Granted0
Working Days Charged91
Percent Time Used12
Contractor(s)
WORKQUEST
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-76-001
GOODWILL INDUSTRIES OF SOUTH TEXAS, (0.00)
Contract #08212133
Totals56617.602286.486883.2612.1

CountyHIDALGO
HighwayIH0069C
FromPHARR DISTRICT COMPLEX
ToPHARR MNT/AO
CSJ6376-78-001
Proj IDSUP - 637678001
Work TypeGROUNDS MAINTENANCE
 
0.01061812.006237.0010.0
Work Order08-19-21
Work Began09-20-21
Work Completed
Time Computed09-20-21
Contract Working Days730
Addl Days Granted0
Working Days Charged91
Percent Time Used12
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-78-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #08212134
Totals61812.002079.006237.0010.0

CountySTARR
HighwayFM1017
FromHEBBRONVILLLE AND ROMA MAINTENANCE
ToVARIOUS ROADWAYS
CSJ6376-79-001
Proj IDSUP - 637679001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010937724.08193467.0320.6
Work Order09-01-21
Work Began09-27-21
Work Completed
Time Computed09-27-21
Contract Working Days365
Addl Days Granted0
Working Days Charged65
Percent Time Used17
Contractor(s)
WORKQUEST
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-79-001
UPPER VALLEY HELPSOURCE, INC. (0.00)
Contract #08212137
Totals937724.0886617.92193467.0320.6

CountyCAMERON
HighwayIH0069E
FromCAMERON, WILLACY AND KENEDY COUNTY
ToSAN BENITO, BROWNSVILLE AND RAYMONDVILLE
CSJ6376-80-001
Proj IDSUP - 637680001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010431833.5081235.8518.8
Work Order09-01-21
Work Began09-02-21
Work Completed
Time Computed09-02-21
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-80-001
RGR INDUSTRIES, INC. (0.00)
Contract #08212138
Totals431833.506459.4081235.8518.8

CountySTARR
HighwayUS0083
FromROMA/HEBBRONVILLE MAINTENANCE
ToVARIOUS ROADWAYS
CSJ6377-12-001
Proj IDSUP - 637712001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010747124.6544708.905.9
Work Order09-01-21
Work Began09-01-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-12-001
RGR INDUSTRIES, INC. (0.00)
Contract #08212105
Totals747124.6512714.7044708.905.9

CountyCAMERON
HighwayIH0002
FromIH 2, IH 69E AND SP 54
ToCAMERON, WILLACY AND KENEDY COUNTY
CSJ6377-13-001
Proj IDSUP - 637713001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010932713.3334007.793.6
Work Order08-20-21
Work Began10-04-21
Work Completed
Time Computed09-01-21
Contract Working Days730
Addl Days Granted0
Working Days Charged91
Percent Time Used12
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-13-001
RGR INDUSTRIES, INC. (0.00)
Contract #08212132
Totals932713.3311708.6934007.793.6

CountyCAMERON
HighwayBU0077W
FromVARIOUS COUNTIES (SBAO MAINT BOUNDARY)
ToCAMERON, KENEDY, WILLACY COUNTIES
CSJ6377-56-001
Proj IDMMC - 637756001
Work TypeEMULSION
 
0.010173490.00117456.7967.7
Work Order04-08-21
Work Began05-03-21
Work Completed
Time Computed05-03-21
Contract Working Days120
Addl Days Granted120
Working Days Charged212
Percent Time Used88
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03212101
Totals173490.0023286.36117456.7967.7

CountyHIDALGO
HighwaySH0495
FromPHARR AREA OFFICE MAINTENANCE BOUNDARY
ToHIDALGO COUNTY
CSJ6377-57-001
Proj IDMMC - 637757001
Work TypeEMULSION
 
0.01062755.0020591.5232.8
Work Order04-08-21
Work Began05-03-21
Work Completed
Time Computed05-03-21
Contract Working Days120
Addl Days Granted120
Working Days Charged212
Percent Time Used88
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03212102
Totals62755.000.0020591.5232.8

CountySTARR
HighwayUS0083
FromVARIOUS COUNTIES (RAO MAINT BOUNDARY)
ToSTARR, JIMHOGG, BROOKS, ZAPATA COUNTIES
CSJ6377-58-001
Proj IDMMC - 637758001
Work TypeEMULSION
 
0.01062694.0025191.1940.1
Work Order04-08-21
Work Began05-03-21
Work Completed
Time Computed05-03-21
Contract Working Days120
Addl Days Granted120
Working Days Charged182
Percent Time Used75
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03212103
Totals62694.000.0025191.1940.1

CountySTARR
HighwayUS0083
FromVARIOUS COUNTIES (RAO MAINT BOUNDARY)
ToSTARR, JIM HOGG, BROOKS, ZAPATA COUNTIES
CSJ6378-52-001
Proj IDMMC - 637852001
Work TypeLIMESTONE ROCK AND ASPHALT
 
0.010190618.10569202.0099.9
Work Order04-08-21
Work Began04-30-21
Work Completed
Time Computed04-30-21
Contract Working Days120
Addl Days Granted240
Working Days Charged215
Percent Time Used59
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6378-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03212104
Totals190618.10179067.53569202.0099.9

CountyWILLACY
HighwayBU0077W
FromRAYMONDVILLE MAINTENANCE BOUNDARY
ToWILLACY COUNTY
CSJ6378-53-001
Proj IDMMC - 637853001
Work TypeLIMESTONE ROCK AND ASPHALT
 
0.010244686.00664909.7199.9
Work Order04-08-21
Work Began04-30-21
Work Completed
Time Computed04-30-21
Contract Working Days120
Addl Days Granted240
Working Days Charged215
Percent Time Used59
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6378-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03212105
Totals244686.00176633.38664909.7199.9

CountyCAMERON
HighwayUS0281
FromBROWNSVILLE MAINTENANCE BOUNDARY
ToCAMERON COUNTY
CSJ6378-54-001
Proj IDMMC - 637854001
Work TypeLIMESTONE ROCK AND ASPHALT
 
0.010250175.00388897.1499.9
Work Order04-08-21
Work Began04-30-21
Work Completed
Time Computed04-30-21
Contract Working Days120
Addl Days Granted240
Working Days Charged215
Percent Time Used59
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6378-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03212106
Totals250175.000.00388897.1499.9

CountyHIDALGO
HighwaySH0495
FromPHARR AREA OFFICE MAINTENANCE BOUNDARY
ToHIDALGO COUNTY
CSJ6378-56-001
Proj IDMMC - 637856001
Work TypeLIMESTONE ROCK AND ASPHALT
 
0.010225400.00490136.4299.9
Work Order04-08-21
Work Began04-30-21
Work Completed
Time Computed04-30-21
Contract Working Days120
Addl Days Granted240
Working Days Charged215
Percent Time Used59
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6378-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03212107
Totals225400.00152533.17490136.4299.9

CountyCAMERON
HighwayBU0077W
FromCAMERON COUNTY
ToSAN BENITO MAINTENANCE OFFICE
CSJ6378-57-001
Proj IDMMC - 637857001
Work TypeLIMESTONE ROCK AND ASPHALT
 
0.010243201.00474219.8599.9
Work Order04-08-21
Work Began04-30-21
Work Completed
Time Computed04-30-21
Contract Working Days120
Addl Days Granted240
Working Days Charged215
Percent Time Used59
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6378-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03212108
Totals243201.000.00474219.8599.9

CountyHIDALGO
HighwaySH0495
FromDISTRICT WIDE
ToVARIOUS COUNTIES
CSJ6381-53-001
Proj IDMMC - 638153001
Work TypeSAND
 
0.01018480.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MESA D CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6381-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07212101
Totals18480.000.000.000.0

CountyHIDALGO
HighwaySH0495
FromVARIOUS COUNTIES
ToDISTRICTWIDE
CSJ6381-61-001
Proj IDMMC - 638161001
Work TypeHYDRAULIC CEMENT
 
0.010152932.50160601.0099.9
Work Order07-06-21
Work Began07-16-21
Work Completed
Time Computed07-16-21
Contract Working Days120
Addl Days Granted120
Working Days Charged138
Percent Time Used57
Contractor(s)
KLP COMMERCIAL, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6381-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06212103
Totals152932.500.00160601.0099.9

CountyHIDALGO
HighwaySH0495
FromDISTRICT WIDE
ToVARIOUS COUNTIES
CSJ6382-22-001
Proj IDMMC - 638222001
Work TypeFLEXIBLE BASE
 
0.010229600.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6382-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07212102
Totals229600.000.000.000.0

CountyHIDALGO
HighwaySH0495
FromHIDALGO COUNTY
ToVARIOUS ROADWAYS
CSJ6385-75-001
Proj IDSUP - 638575001
Work TypeCRASH CUSHION ATTENUATOR REPAIR
 
0.010414702.5542014.1010.1
Work Order08-31-21
Work Began09-24-21
Work Completed
Time Computed09-24-21
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6385-75-001
RGR INDUSTRIES, INC. (0.00)
Contract #08212102
Totals414702.5515094.5042014.1010.1

CountyCAMERON
HighwayIH0069E
FromCAMERON, WILLACY AND KENEDY COUNTY
ToSAN BENITO, BROWNSVILLE AND RAYMONDVILLE
CSJ6387-83-001
Proj IDSUP - 638783001
Work TypeCRASH CUSHION ATTENUATOR REPAIR
 
0.010583734.8072082.0512.3
Work Order09-02-21
Work Began09-02-21
Work Completed
Time Computed09-02-21
Contract Working Days365
Addl Days Granted0
Working Days Charged90
Percent Time Used24
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6387-83-001
RGR INDUSTRIES, INC. (0.00)
Contract #08212103
Totals583734.8024493.3572082.0512.3