Monthly Local Let Maintenance Report For Pharr District As Of Nov 22, 2017 Page 4 Of 4

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCAMERON
HighwayIH0069E
FromHIDALGO COUNTY
ToBROWNSVILLE, HIDALGO & SAN BENITO
CSJ6312-15-001
Proj IDRMC - 631215001
Work TypeMAINTENANCE OF TBSIF
 
0.01026546.3014479.8054.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-09-16
Work Completed
Time Computed00-00-00
Contract Working Days669
Addl Days Granted0
Working Days Charged365
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162130
Totals26546.301206.6514479.8054.5

CountyCAMERON
HighwayUS0281
FromCAMERON
ToHIDALGO
CSJ6314-09-001
Proj IDRMC - 631409001
Work TypeSPECIALTY RMC
 
0.010279381.50346805.1199.9
Work Order06-26-17
Work Began07-11-17
Work Completed
Time Computed07-11-17
Contract Working Days80
Addl Days Granted65
Working Days Charged78
Percent Time Used53
Contractor(s)
VALLEY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06172101
Totals279381.5020095.00346805.1199.9

CountyHIDALGO
HighwayIH0002
FromIH 2 AND IH 69C
ToHIDALGO COUNTY
CSJ6314-56-001
Proj IDSUP - 631456001
Work TypeROADSIDE MOWING AND LITTER REMOVAL
 
0.010549937.5037007.336.7
Work Order08-31-17
Work Began00-00-00
Work Completed
Time Computed09-01-17
Contract Working Days256
Addl Days Granted0
Working Days Charged16
Percent Time Used6
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172130
Totals549937.5016993.0737007.336.7

CountyCAMERON
HighwayIH0069E
FromIH 2, IH 69E, SP 54
ToCAMERON, WILLACY AND KENEDY COUNTY
CSJ6314-57-001
Proj IDSUP - 631457001
Work TypeROADSIDE MOWING AND LITTER REMOVAL
 
0.010955972.6381464.698.5
Work Order08-31-17
Work Began00-00-00
Work Completed
Time Computed09-01-17
Contract Working Days416
Addl Days Granted0
Working Days Charged19
Percent Time Used4
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172131
Totals955972.6329539.5581464.698.5

CountyJIM HOGG
HighwayFM1017
FromHEBBRONVILLE AND ROMA MAINTENANCE
ToVARIOUS ROADWAYS
CSJ6314-58-001
Proj IDSUP - 631458001
Work TypeROADSIDE MOWING AND LITTER REMOVAL
 
0.0101185240.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-03-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days342
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172132
Totals1185240.980.000.000.0

CountyCAMERON
HighwayIH0069E
FromSAN BENITO AREA OFFICE
ToSAN BENITO MAINTENANCE OFFICE
CSJ6314-59-001
Proj IDSUP - 631459001
Work TypeTECHNICAL ASSISTANCE
 
0.01054953.604385.727.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172134
Totals54953.602272.124385.727.9

CountyCAMERON
HighwayIH0069E
FromBROWNSVILLE, RAYMONDVILLE, SAN BENITO
ToVARIOUS ROADWAYS
CSJ6314-60-001
Proj IDSUP - 631460001
Work TypeMETAL BEAM GUARD FENCE_REPAIR
 
0.010733187.420.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days669
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11172135
Totals733187.420.000.000.0

CountyHIDALGO
HighwayIH0069C
FromPHARR, EDCOUCH, MISSION
ToVARIOUS_ROADWAYS
CSJ6314-61-001
Proj IDSUP - 631461001
Work TypeMETAL BEAM GUARD FENCE_REPAIR
 
0.010734900.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days669
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11172133
Totals734900.430.000.000.0

CountySTARR
HighwayUS0083
FromROMA, HEBBRONVILLE
ToVARIOUS_ROADWAYS
CSJ6314-62-001
Proj IDSUP - 631462001
Work TypeMETAL BEAM GUARD FENCE_REPAIR
 
0.010538308.010.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days669
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11172136
Totals538308.010.000.000.0

CountyHIDALGO
HighwayIH0002
FromPHARR DISTRICT
ToPHARR AREA OFFICE
CSJ6314-64-001
Proj IDSUP - 631464001
Work TypeGROUNDS MAINTENANCE
 
0.01061212.004158.006.7
Work Order09-01-17
Work Began09-18-17
Work Completed
Time Computed09-18-17
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172137
Totals61212.002079.004158.006.7

CountyCAMERON
HighwayIH0069E
FromDISTRICT WIDE
ToVARIOUS
CSJ6314-65-001
Proj IDSUP - 631465001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010346793.5435258.0010.1
Work Order09-01-17
Work Began00-00-00
Work Completed
Time Computed09-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172138
Totals346793.5416592.0035258.0010.1

CountySTARR
HighwayUS0083
FromROMA AREA OFFICE
ToROMA MAINTENANCE OFFICE
CSJ6314-66-001
Proj IDSUP - 631466001
Work TypeJANITORIAL MAINTENANCE
 
0.01082517.327845.779.5
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172139
Totals82517.324955.227845.779.5