Monthly State Let Construction Report For San Antonio District As Of Sep 18, 2019 Page 2 Of 8

Last Update: Thursday, September 19, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayIH 35
FromIH 37/US 281
ToWALTERS ST.
CSJ0017-10-280
Proj IDSTP 2018(860)MM
Work TypeGRD, BSE, SIDEWALKS, SIGN, PAVT MRK
 
1.694635284.27502353.4179.0
CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
ToON STATE SYSTEM
CSJ0915-12-586
Proj IDSTP 2018(859)MM
Work TypeGRD, BSE, SIDEWALKS, SIGN, PAVT MRK
 
0.0013926556.573284820.2083.6
Work Order06-14-18
Work Began08-06-18
Work Completed
Time Computed07-14-18
Contract Working Days301
Addl Days Granted0
Working Days Charged242
Percent Time Used80
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-280
FUQUAY, INC. (9.00)
8A ELECTRIC, INC. (3.41)
ROADWAY SPECIALTIES, INC. (4.40)
C & C ALCOSER TRUCKING (0.84)
2 J RESOURCES COMPANY (12.33)
PRESTON BANKS CONSTRUCTION COMPANY, LLC (5.63)
Contract #05183026
Totals4561840.84187353.643787173.6183.0

CountyBEXAR
HighwayIH 35
FromPINE ST
ToUNION PACIFIC RAILROAD
CSJ0017-10-286
Proj IDNH 1802(386)
Work TypeLANDSCAPE DEVELOPMENT
 
1.750542994.35390518.8771.9
Work Order08-03-18
Work Began10-01-18
Work Completed
Time Computed09-02-18
Contract Working Days82
Addl Days Granted0
Working Days Charged54
Percent Time Used65
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-286
FLASHER EQUIPMENT COMPANY (1.72)
Contract #07183233
Totals542994.355000.00390518.8771.9

CountyBEXAR
HighwayIH 35
FromUS 281
ToIH 410
CSJ0017-10-287
Proj IDSTP 1802(438)HES
Work TypeWRONG WAY DRIVER ADVANCED TECHNOLOG
 
8.927247299.32183245.0374.0
Work Order09-24-18
Work Began00-00-00
Work Completed
Time Computed10-24-18
Contract Working Days70
Addl Days Granted0
Working Days Charged56
Percent Time Used80
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-287
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (54.14)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (22.83)
Contract #08183055
Totals247299.32117951.05183245.0374.0

CountyBEXAR ETC
HighwayIH 35 ETC
FromN SANTA ROSA ST
ToN FLORES ST
CSJ0017-10-288
Proj IDSTP 1902(206)HES
Work TypeSFT
 
7.1611477236.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-288
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193249
Totals1477236.880.000.000.0

CountyATASCOSA ETC
HighwaySH 132 ETC
FromAT SOMERSET STREET
To.
CSJ0017-13-010
Proj IDSTP 2019(044)HES
Work TypeTRAFFIC SIGNAL & ILLUMINATION
 
3.5483207689.812125932.5666.2
Work Order10-22-18
Work Began04-22-19
Work Completed
Time Computed11-21-18
Contract Working Days392
Addl Days Granted0
Working Days Charged84
Percent Time Used21
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-13-010
HEARN CO. (11.77)
FLASHER EQUIPMENT COMPANY (1.63)
CATO ELECTRIC COMPANY (0.52)
LOZANO CONSTRUCTION COMPANY, INC. (0.00)
ALAMO CRANE SERVICE, INC. (0.68)
Contract #09183222
Totals3207689.81326698.512125932.5666.2

CountyMEDINA ETC
HighwaySH 132 ETC
FromATASCOSA C/L
ToFM 463
CSJ0017-14-018
Proj IDSTP 2017(153)
Work TypeSEAL COAT AND PAVEMENT MARKINGS
 
279.6549674310.4810718513.9999.9
Work Order12-05-16
Work Began05-31-17
Work Completed
Time Computed01-04-17
Contract Working Days65
Addl Days Granted0
Working Days Charged65
Percent Time Used100
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-14-018
INTERSTATE BARRICADES & MARKINGS, INC. (15.88)
COX PAVING OF TEXAS, INC. (16.31)
Contract #10163004
Totals9674310.480.0010718513.9999.9

CountyUVALDE
HighwayUS 90
FromFM 481
ToFM 2369
CSJ0024-01-103
Proj IDNH 2018(592)
Work TypeOVERLAY & PAVEMENT MARKINGS
 
6.3554809678.664759018.8299.2
Work Order04-18-18
Work Began06-11-18
Work Completed
Time Computed05-18-18
Contract Working Days169
Addl Days Granted4
Working Days Charged186
Percent Time Used107
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0024-01-103
RELMCO, INC. (10.55)
THE LEVY COMPANY, INC. (6.89)
HIGHWAY BARRICADES AND SERVICES, LLC (3.01)
PRIMATE CONSTRUCTION, INC. (1.42)
DEPENDABLE FENCE & WELDING CO. INC. (1.37)
AREA WIDE PROTECTIVE, INC. (0.94)
MURRAY CONSTRUCTION (0.98)
LONE STAR EROSION CONTROL (0.18)
FLASHER LIMITED (0.18)
Contract #03183235
Totals4809678.662548.334759018.8299.2

CountyUVALDE ETC
HighwayUS 90 ETC
FromAT FM 2369
To.
CSJ0024-01-105
Proj IDSTP 1902(207)HES
Work TypeSFT
 
4.4001455288.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-22-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F & W ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0024-01-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193036
Totals1455288.950.000.000.0

CountyMEDINA ETC
HighwayUS 90 ETC
FromAT CONSTANTINOPLE
To.
CSJ0024-06-064
Proj IDSTP 1602(527)HES
Work TypeSIGNALS
 
16.2151827606.471722947.8094.2
Work Order12-12-16
Work Began03-20-17
Work Completed
Time Computed01-11-17
Contract Working Days418
Addl Days Granted3
Working Days Charged410
Percent Time Used97
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0024-06-064
JCD CONSTRUCTION, LLC (2.49)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (1.89)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (4.31)
SAN ANTONIO CONCEPTS CONSTRUCTION, LLLC (0.82)
GRUPO CONSTRUCTOR VELACOR, LLC (0.85)
Contract #11163214
Totals1827606.47519.201722947.8094.2

CountyBEXAR
HighwayUS 90
FromIH 410
ToLP 13
CSJ0024-08-128
Proj IDSTP 2017(331)HES
Work TypeGRAD, STR, SIGN,
 
1.1722331043.072313866.8599.9
Work Order02-22-17
Work Began05-08-17
Work Completed
Time Computed03-24-17
Contract Working Days210
Addl Days Granted0
Working Days Charged351
Percent Time Used167
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-128
FLASHER EQUIPMENT COMPANY (0.10)
SCOTT DERR PAINTING CO, LLC (0.42)
RDI FOUNDATION DRILLING (4.34)
F & W ELECTRICAL CONTRACTORS, INC. (3.22)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.04)
VALLEY PLACERS, LLC (0.27)
NATIONAL REINFORCEMENT STEEL (2.74)
Contract #01173030
Totals2331043.070.002313866.8599.9

CountyBEXAR
HighwayUS 90
From1.0 MILE WEST OF LOOP 13
To1.0 MILE EAST OF LOOP 13
CSJ0024-08-131
Proj IDNH 1502(263)
Work TypeLANDSCAPE DEVELOPMENT
 
2.000355044.00350658.3398.7
Work Order07-14-15
Work Began10-15-15
Work Completed
Time Computed09-13-15
Contract Working Days58
Addl Days Granted0
Working Days Charged43
Percent Time Used74
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-131
FLASHER EQUIPMENT COMPANY (1.76)
Contract #06153211
Totals355044.000.00350658.3398.7

CountyBEXAR
HighwayUS 90
FromLP 13 -W MILITARY DR
ToCUPPLES ROAD
CSJ0024-08-133
Proj IDNH 1602(299)
Work TypeLANDSCAPE DEVELOPMENT
 
4.9001069800.00997087.3093.2
Work Order08-18-16
Work Began10-03-16
Work Completed
Time Computed09-17-16
Contract Working Days164
Addl Days Granted0
Working Days Charged132
Percent Time Used80
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-133
FLASHER EQUIPMENT COMPANY (1.21)
SOUTHWEST RB, LLC (0.85)
Contract #07163208
Totals1069800.002000.00997087.3093.2

CountyBEXAR
HighwayUS 90
FromLOOP 13
ToSH 151
CSJ0024-08-136
Proj IDNH 1702(024)
Work TypeILLUMINATION
 
2.441864247.19878764.6999.9
CountyBEXAR
HighwayUS 90
FromIH 410
ToLOOP 13
CSJ0024-08-137
Proj IDNH 1702(024)
Work TypeILLUMINATION
 
0.836412690.81367897.1289.1
Work Order06-08-17
Work Began10-09-17
Work Completed
Time Computed07-08-17
Contract Working Days120
Addl Days Granted0
Working Days Charged117
Percent Time Used97
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-136
RUCOBA & MAYA CONSTRUCTION (3.91)
MCL CONTRACTING, LLC (0.42)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.36)
LONE STAR EROSION CONTROL (0.69)
FLASHER EQUIPMENT COMPANY (0.48)
Contract #05173231
Totals1276938.000.001246661.8197.6

CountyBEXAR
HighwaySS 371
FromBILLY MITCHELL ROAD
ToUS 90
CSJ0024-09-024
Proj IDC 24-9-24
Work TypeSURFACE & PAVEMENT MARKINGS
 
1.7753620525.941530145.2642.2
CountyBEXAR
HighwaySS 421
FromIH 410
ToCHERYL DR.
CSJ0291-10-103
Proj IDC 291-10-103
Work TypeSURFACE & PAVEMENT MARKERS
 
2.9852622395.220.000.0
Work Order03-25-19
Work Began07-09-19
Work Completed
Time Computed04-24-19
Contract Working Days255
Addl Days Granted0
Working Days Charged37
Percent Time Used14
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0024-09-024
FLASHER EQUIPMENT COMPANY (4.17)
TEXAS R & G CONSTRUCTION SERVICES LLC (3.11)
THE LEVY COMPANY, INC. (3.36)
LONE STAR EROSION CONTROL (0.13)
Contract #02193015
Totals6242921.16438881.701530145.2624.5

CountyBEXAR
HighwayIH 10
FromIH 410
ToLOOP 1604
CSJ0025-02-160
Proj IDC 25-2-160
Work TypeGRAD,STR,BASE & SURF
 
6.235108886144.2441851019.0338.4
Work Order06-11-18
Work Began10-15-18
Work Completed
Time Computed07-11-18
Contract Working Days700
Addl Days Granted20
Working Days Charged266
Percent Time Used36
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-160
AREA WIDE PROTECTIVE, INC. (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.93)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.62)
OLDCASTLE MATERIALS TEXAS, INC. (5.96)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.53)
BEAIRD DRILLING (1.59)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.46)
F & W ELECTRICAL CONTRACTORS, INC._(SAN ANTONIO) (4.47)
BOWMAN ENGINEERING & CONSULTING, INC. (1.49)
GRL ENGINEERS, INC. (0.00)
DEPENDABLE FENCE & WELDING CO. INC. (0.05)
GK CONSTRUCTION, LLC (0.10)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.22)
ANCORTEX, INC. (2.07)
M & M STRIPING & POWER WASHING, LLC (0.01)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21)
INDUS ROAD & BRIDGE, INC (1.39)
ADCOCK 4 INVESTMENTS, LLC (1.80)
Contract #05183001
Totals108886144.244287865.9841851019.0338.4

CountyBEXAR
HighwayIH 10
FromFOSTER ROAD
ToGRAYTOWN ROAD
CSJ0025-02-198
Proj IDC 25-2-198
Work TypeGRAD, BS, STR, PVMT MRKG
 
6.26963752806.4448871551.2576.6
CountyBEXAR
HighwayIH 10
FromFOSTER ROAD
ToGRAYTOWN ROAD
CSJ0025-02-206
Proj IDROW 25-2-206
Work TypeUTILITY ADJUSTMENTS
 
0.8331536399.452273702.2099.9
Work Order10-14-16
Work Began10-27-16
Work Completed
Time Computed07-08-16
Contract Working Days812
Addl Days Granted103
Working Days Charged801
Percent Time Used87
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-198
ANCORTEX, INC. (0.52)
BAY CITY TRAFFIC (2.37)
PERFORMANCE EQUIPMENT SERVICE (0.15)
PENHALL COMPANY (AUSTIN) (0.02)
W. W. FOUNDATION DRILLING, LTD. (0.74)
C-3 ENVIRONMENTAL SPECIALTIES, LP (0.21)
DC CIVIL CONSTRUCTION LLC (2.09)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.33)
FLASHER EQUIPMENT COMPANY (0.61)
FOX QUALITY CONCRETE, L.L.C. (1.35)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04)
J.R. RAMON & SONS, INC. (0.17)
THE LEVY COMPANY, L.P. (1.06)
ROYAL REBAR (0.27)
SOUTH TEXAS PAINTING COMPANY (0.13)
ELLIS AND ELLIS (0.56)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.01)
GK CONSTRUCTION, LLC (0.04)
Contract #06163201
Totals65289205.891925297.5951145253.4578.3

CountyBEXAR
HighwayIH 10
FromIH 10 EB AT AMANDA STREET
To.
CSJ0025-02-210
Proj IDBR 1602(546)
Work TypeGRAD,STRUC,BASE,SURF, CLEAN & PAINT
 
0.8342671455.163482865.1999.9
CountyBEXAR
HighwayIH 10
FromIH 10 WB AT AMANDA STREET
To.
CSJ0025-02-211
Proj IDBR 1602(546)
Work TypeGRAD,BSE,STRUCTURE,SURF,CLN & PAINT
 
0.8342026497.492101872.4499.9
Work Order10-26-16
Work Began01-02-17
Work Completed
Time Computed11-25-16
Contract Working Days304
Addl Days Granted0
Working Days Charged289
Percent Time Used95
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-210
ROADWAY SPECIALTIES, INC. (1.49)
F & W ELECTRICAL CONTRACTORS, INC. (0.65)
FRANK JR REINFORCEMENT LLC (0.41)
LONE STAR PAVING COMPANY (12.07)
M & M STRIPING & POWER WASHING, LLC (1.18)
SHINN & GREGORY, INC. (3.79)
JARCO TRANSPORT, LLC (2.07)
SCOTT DERR PAINTING CO, LLC (0.18)
CEKRA INC. (6.48)
C & C ALCOSER TRUCKING (0.89)
FLASHER EQUIPMENT COMPANY (0.41)
Contract #08163034
Totals4697952.650.005584737.6399.9

CountyBEXAR
HighwayIH 10
FromIH 35
ToIH 37
CSJ0025-02-216
Proj IDC 25-2-216
Work TypeUPGRADE ILLUMINATION
 
2.6055251366.123213410.5361.1
CountyBEXAR
HighwayIH 37
FromFAIR AVENUE
ToIH 35
CSJ0073-08-192
Proj IDC 73-8-192
Work TypeUPGRADE ILLUMINATION
 
4.054916543.23139569.7915.2
Work Order08-21-18
Work Began04-01-19
Work Completed
Time Computed09-20-18
Contract Working Days183
Addl Days Granted30
Working Days Charged87
Percent Time Used40
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-216
FUQUAY, INC. (2.31)
TEXAS R & G CONSTRUCTION SERVICES LLC (8.00)
DOUBLE S CONSTRUCTION (1.27)
THOMAS 11 DEVELOPMENT LLC (14.91)
BUYERS BARRICADES SAN ANTONIO, LLC (0.86)
RANSOM DRILLING SERVICES, LLC (3.61)
Contract #07183019
Totals6167909.3578897.543352980.3254.3

CountyBEXAR
HighwayIH 10
FromIH 10 NFR AT CIBOLO CREEK
To.
CSJ0025-02-217
Proj IDBR 2019(035)
Work TypePAINT & REPAIR BRG, SURF, PAV'T MRK
 
0.1841479046.42331481.8522.4
Work Order10-22-18
Work Began00-00-00
Work Completed
Time Computed11-21-18
Contract Working Days130
Addl Days Granted0
Working Days Charged52
Percent Time Used40
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-217
DIIBS SPECIALISTS (2.09)
FLASHER EQUIPMENT COMPANY (0.67)
S&S BRIDGE PAINTING (41.95)
Contract #09183019
Totals1479046.42204021.09331481.8522.4

CountyBEXAR
HighwayIH 10
FromLOOP 1604
ToGRAYTOWN RD
CSJ0025-02-219
Proj IDNH 1902(314)
Work TypeWIDEN FREEWAY
 
2.84191651868.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,174
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-219
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193202
Totals91651868.270.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8