Monthly State Let Construction Report For San Antonio District As Of Apr 11, 2020 Page 2 Of 8

Last Update: Saturday, April 11, 2020
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayIH 35
FromIH 37/US 281
ToWALTERS ST.
CSJ0017-10-280
Proj IDSTP 2018(860)MM
Work TypeGRD, BSE, SIDEWALKS, SIGN, PAVT MRK
 
1.694635284.27599798.6394.4
CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
ToON STATE SYSTEM
CSJ0915-12-586
Proj IDSTP 2018(859)MM
Work TypeGRD, BSE, SIDEWALKS, SIGN, PAVT MRK
 
0.0013926556.573858001.1698.2
Work Order06-14-18
Work Began08-06-18
Work Completed
Time Computed07-14-18
Contract Working Days301
Addl Days Granted0
Working Days Charged301
Percent Time Used100
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-280
FUQUAY, INC. (9.00)
8A ELECTRIC, INC. (3.41)
ROADWAY SPECIALTIES, INC. (4.40)
C & C ALCOSER TRUCKING (0.84)
2 J RESOURCES COMPANY (12.33)
PRESTON BANKS CONSTRUCTION COMPANY, LLC (5.63)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.41)
Contract #05183026
Totals4561840.8415303.104457799.7997.7

CountyBEXAR
HighwayIH 35
FromPINE ST
ToUNION PACIFIC RAILROAD
CSJ0017-10-286
Proj IDNH 1802(386)
Work TypeLANDSCAPE DEVELOPMENT
 
1.750542994.35530729.3797.7
Work Order08-03-18
Work Began10-01-18
Work Completed
Time Computed09-02-18
Contract Working Days82
Addl Days Granted0
Working Days Charged81
Percent Time Used98
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-286
FLASHER EQUIPMENT COMPANY (1.72)
Contract #07183233
Totals542994.3516308.50530729.3797.7

CountyBEXAR
HighwayIH 35
FromUS 281
ToIH 410
CSJ0017-10-287
Proj IDSTP 1802(438)HES
Work TypeWRONG WAY DRIVER ADVANCED TECHNOLOG
 
8.927247299.32206286.3683.4
Work Order09-24-18
Work Began04-16-19
Work Completed
Time Computed10-24-18
Contract Working Days70
Addl Days Granted0
Working Days Charged62
Percent Time Used88
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-287
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (54.14)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (22.83)
Contract #08183055
Totals247299.323992.78206286.3683.4

CountyBEXAR ETC
HighwayIH 35 ETC
FromN SANTA ROSA ST
ToN FLORES ST
CSJ0017-10-288
Proj IDSTP 1902(206)HES
Work TypeSFT
 
7.1611477236.88203127.4613.7
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed09-12-19
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-288
ALAMO CRANE SERVICE, INC. (1.57)
Contract #07193249
Totals1477236.88157012.00203127.4613.7

CountyATASCOSA ETC
HighwaySH 132 ETC
FromAT SOMERSET STREET
To.
CSJ0017-13-010
Proj IDSTP 2019(044)HES
Work TypeTRAFFIC SIGNAL & ILLUMINATION
 
3.5483207689.813246245.8599.9
Work Order10-22-18
Work Began04-22-19
Work Completed
Time Computed11-21-18
Contract Working Days392
Addl Days Granted0
Working Days Charged215
Percent Time Used54
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0017-13-010
HEARN CO. (11.77)
FLASHER EQUIPMENT COMPANY (1.63)
CATO ELECTRIC COMPANY (0.52)
LOZANO CONSTRUCTION COMPANY, INC. (0.00)
ALAMO CRANE SERVICE, INC. (0.68)
Contract #09183222
Totals3207689.8116329.993246245.8599.9

CountyUVALDE ETC
HighwayUS 90 ETC
FromAT FM 2369
To.
CSJ0024-01-105
Proj IDSTP 1902(207)HES
Work TypeSFT
 
4.4001455288.95368477.6025.3
Work Order08-22-19
Work Began04-16-19
Work Completed
Time Computed09-21-19
Contract Working Days120
Addl Days Granted0
Working Days Charged25
Percent Time Used20
Contractor(s)
F & W ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0024-01-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193036
Totals1455288.9588829.60368477.6025.3

CountyBEXAR
HighwayUS 90
FromIH 410
ToLP 13
CSJ0024-08-128
Proj IDSTP 2017(331)HES
Work TypeGRAD, STR, SIGN,
 
1.1722331043.072341009.2699.9
Work Order02-22-17
Work Began05-08-17
Work Completed
Time Computed03-24-17
Contract Working Days210
Addl Days Granted0
Working Days Charged351
Percent Time Used167
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-128
FLASHER EQUIPMENT COMPANY (0.10)
SCOTT DERR PAINTING CO, LLC (0.42)
RDI FOUNDATION DRILLING (4.34)
F & W ELECTRICAL CONTRACTORS, INC. (3.22)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.04)
VALLEY PLACERS, LLC (0.27)
NATIONAL REINFORCEMENT STEEL (2.74)
Contract #01173030
Totals2331043.070.002341009.2699.9

CountyBEXAR
HighwayUS 90
FromIH 410
ToSW 36TH STREET
CSJ0024-08-135
Proj IDNH 2020(676)
Work TypeOVERLAY
 
4775401.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days138
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-135
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03203224
Totals4775401.100.000.000.0

CountyBEXAR
HighwayUS 90
FromLOOP 13
ToSH 151
CSJ0024-08-136
Proj IDNH 1702(024)
Work TypeILLUMINATION
 
2.441864247.19878764.6999.9
CountyBEXAR
HighwayUS 90
FromIH 410
ToLOOP 13
CSJ0024-08-137
Proj IDNH 1702(024)
Work TypeILLUMINATION
 
0.836412690.81367897.1289.1
Work Order06-08-17
Work Began10-09-17
Work Completed
Time Computed07-08-17
Contract Working Days120
Addl Days Granted0
Working Days Charged117
Percent Time Used97
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0024-08-136
RUCOBA & MAYA CONSTRUCTION (3.91)
MCL CONTRACTING, LLC (0.42)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.36)
LONE STAR EROSION CONTROL (0.69)
FLASHER EQUIPMENT COMPANY (0.48)
Contract #05173231
Totals1276938.000.001246661.8197.6

CountyBEXAR
HighwaySS 371
FromBILLY MITCHELL ROAD
ToUS 90
CSJ0024-09-024
Proj IDC 24-9-24
Work TypeSURFACE & PAVEMENT MARKINGS
 
1.7753620525.943823728.0199.9
CountyBEXAR
HighwaySS 421
FromIH 410
ToCHERYL DR.
CSJ0291-10-103
Proj IDC 291-10-103
Work TypeSURFACE & PAVEMENT MARKERS
 
2.9852622395.22797834.6030.4
Work Order03-25-19
Work Began07-09-19
Work Completed
Time Computed04-24-19
Contract Working Days255
Addl Days Granted4
Working Days Charged179
Percent Time Used69
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0024-09-024
FLASHER EQUIPMENT COMPANY (4.17)
TEXAS R & G CONSTRUCTION SERVICES LLC (3.11)
THE LEVY COMPANY, INC. (3.36)
LONE STAR EROSION CONTROL (0.13)
Contract #02193015
Totals6242921.16912942.134621562.6174.0

CountyBEXAR
HighwayIH 10
FromIH 410
ToLOOP 1604
CSJ0025-02-160
Proj IDC 25-2-160
Work TypeGRAD,STR,BASE & SURF
 
6.235108886144.2466866431.4061.4
Work Order06-11-18
Work Began10-15-18
Work Completed
Time Computed07-11-18
Contract Working Days700
Addl Days Granted29
Working Days Charged430
Percent Time Used58
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-160
AREA WIDE PROTECTIVE, INC. (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.93)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.62)
OLDCASTLE MATERIALS TEXAS, INC. (5.96)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.53)
BEAIRD DRILLING (1.59)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.46)
F & W ELECTRICAL CONTRACTORS, INC._(SAN ANTONIO) (4.47)
BOWMAN ENGINEERING & CONSULTING, INC. (1.49)
GRL ENGINEERS, INC. (0.00)
DEPENDABLE FENCE & WELDING CO. INC. (0.05)
GK CONSTRUCTION, LLC (0.10)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.22)
ANCORTEX, INC. (2.07)
M & M STRIPING & POWER WASHING, LLC (0.01)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21)
INDUS ROAD & BRIDGE, INC (1.39)
ADCOCK 4 INVESTMENTS, LLC (1.80)
FLASHER EQUIPMENT COMPANY (0.07)
URBAN INFRACONSTRUCTION LLC (0.25)
BEXAR COUNTY CONCRETE, LLC (0.12)
Contract #05183001
Totals108886144.243686225.3966866431.4061.4

CountyBEXAR
HighwayIH 10
FromFOSTER ROAD
ToGRAYTOWN ROAD
CSJ0025-02-198
Proj IDC 25-2-198
Work TypeGRAD, BS, STR, PVMT MRKG
 
6.26963752806.4456957351.2889.4
CountyBEXAR
HighwayIH 10
FromFOSTER ROAD
ToGRAYTOWN ROAD
CSJ0025-02-206
Proj IDROW 25-2-206
Work TypeUTILITY ADJUSTMENTS
 
0.8331536399.452277782.2099.9
Work Order10-14-16
Work Began10-27-16
Work Completed
Time Computed07-08-16
Contract Working Days812
Addl Days Granted127
Working Days Charged963
Percent Time Used102
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-198
ANCORTEX, INC. (0.52)
BAY CITY TRAFFIC (2.37)
PERFORMANCE EQUIPMENT SERVICE (0.15)
PENHALL COMPANY (AUSTIN) (0.02)
W. W. FOUNDATION DRILLING, LTD. (0.74)
C-3 ENVIRONMENTAL SPECIALTIES, LP (0.21)
DC CIVIL CONSTRUCTION LLC (2.09)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.33)
FLASHER EQUIPMENT COMPANY (0.61)
FOX QUALITY CONCRETE, L.L.C. (1.35)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04)
J.R. RAMON & SONS, INC. (0.17)
THE LEVY COMPANY, L.P. (1.06)
ROYAL REBAR (0.27)
SOUTH TEXAS PAINTING COMPANY (0.13)
ELLIS AND ELLIS (0.56)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.01)
GK CONSTRUCTION, LLC (0.04)
Contract #06163201
Totals65289205.891351518.5159235133.4890.8

CountyBEXAR
HighwayIH 10
FromIH 35
ToIH 37
CSJ0025-02-216
Proj IDC 25-2-216
Work TypeUPGRADE ILLUMINATION
 
2.6055251366.124555341.2186.7
CountyBEXAR
HighwayIH 37
FromFAIR AVENUE
ToIH 35
CSJ0073-08-192
Proj IDC 73-8-192
Work TypeUPGRADE ILLUMINATION
 
4.054916543.23517496.9056.4
Work Order08-21-18
Work Began04-01-19
Work Completed
Time Computed09-20-18
Contract Working Days183
Addl Days Granted30
Working Days Charged164
Percent Time Used76
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-216
FUQUAY, INC. (2.31)
TEXAS R & G CONSTRUCTION SERVICES LLC (8.00)
DOUBLE S CONSTRUCTION (1.27)
THOMAS 11 DEVELOPMENT LLC (14.91)
BUYERS BARRICADES SAN ANTONIO, LLC (0.86)
RANSOM DRILLING SERVICES, LLC (3.61)
ADCOCK 4 INVESTMENTS, LLC (15.63)
A K FUQUAY CONSTRUCTION (2.31)
Contract #07183019
Totals6167909.35156717.535072838.1182.2

CountyBEXAR
HighwayIH 10
FromIH 10 NFR AT CIBOLO CREEK
To.
CSJ0025-02-217
Proj IDBR 2019(035)
Work TypePAINT & REPAIR BRG, SURF, PAV'T MRK
 
0.1841479046.42672965.8645.4
Work Order10-22-18
Work Began06-17-19
Work Completed
Time Computed11-21-18
Contract Working Days130
Addl Days Granted0
Working Days Charged113
Percent Time Used86
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-217
DIIBS SPECIALISTS (2.09)
FLASHER EQUIPMENT COMPANY (0.67)
S&S BRIDGE PAINTING (41.95)
Contract #09183019
Totals1479046.420.00672965.8645.4

CountyBEXAR
HighwayIH 10
FromLOOP 1604
ToGRAYTOWN RD
CSJ0025-02-219
Proj IDNH 1902(314)
Work TypeWIDEN FREEWAY
 
2.84191651868.276777081.247.3
Work Order09-16-19
Work Began02-03-20
Work Completed
Time Computed10-16-19
Contract Working Days1,174
Addl Days Granted0
Working Days Charged50
Percent Time Used4
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-219
TRP CONSTRUCTION GROUP, LLC (0.66)
BUYERS BARRICADES SAN ANTONIO, LLC (0.56)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.54)
F & W ELECTRICAL CONTRACTORS, INC._(SAN ANTONIO) (2.56)
ADCOCK 4 INVESTMENTS, LLC (1.94)
PENHALL COMPANY (0.00)
AARON CONCRETE CONTRACTORS, L.P. (1.25)
J. R. (JOE) RAMON & SONS, INC. (0.19)
BEXAR CONCRETE WORKS INCORPORATED (3.51)
ROADWAY SPECIALTIES, INC. (0.51)
TEXAS MATERIALS GROUP, INC. (11.57)
TORO BRAVO CONSTRUCTION, LLC (0.00)
Contract #08193202
Totals91651868.27913973.726777081.247.3

CountyBEXAR
HighwayIH 10
From0.1 MILES WEST OF OF S. WALTERS
ToAMANDA
CSJ0025-02-223
Proj IDSTP 1902(318)
Work TypeLSE
 
1.1651049982.00572881.5554.5
Work Order09-25-19
Work Began12-09-19
Work Completed
Time Computed10-25-19
Contract Working Days125
Addl Days Granted0
Working Days Charged53
Percent Time Used42
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-223
TX DOWN UNDER CONSTRUCTION, LLC (0.94)
BUYERS BARRICADES SAN ANTONIO, LLC (0.69)
Contract #08193232
Totals1049982.00157154.90572881.5554.5

CountyBEXAR
HighwayFM 78
From2.939 MI W OF FM 1516
To2.325 MI W OF FM 1516
CSJ0025-09-079
Proj IDSTP 1902(315)HES
Work TypeSFT
 
0.614355921.72262255.1773.6
CountyBEXAR
HighwaySH 16
FromBRAUN RD
ToMYSTIC PARK
CSJ0291-10-112
Proj IDSTP 1902(315)HES
Work TypeSFT
 
0.481271953.1319327.047.1
Work Order09-25-19
Work Began02-10-20
Work Completed
Time Computed10-25-19
Contract Working Days75
Addl Days Granted0
Working Days Charged26
Percent Time Used34
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-09-079
CALAME CONTRACTING, LLC (13.32)
A K FUQUAY CONSTRUCTION (1.24)
AREA WIDE PROTECTIVE, INC. (0.90)
Contract #08193028
Totals627874.85135226.47281582.2144.8

CountyGUADALUPE
HighwayFM 78
From0.2 MI EAST OF GEMBLER ROAD
To0.1 MI WEST OF WESTGATE DRIVE
CSJ0025-10-092
Proj IDSTP 2019(171)
Work TypeSURFACE & PAVEMENT MARKINGS
 
6.9773808766.712869956.7875.3
CountyGUADALUPE
HighwaySH 46
FromC.H. MATTHIES JR
To0.7 MI EAST OF FM 467
CSJ0216-02-062
Proj IDSTP 2019(171)
Work TypeSURFACE & PAVEMENT MARKINGS
 
4.4343512735.994182705.8099.9
Work Order02-13-19
Work Began04-01-19
Work Completed
Time Computed03-15-19
Contract Working Days182
Addl Days Granted28
Working Days Charged148
Percent Time Used70
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-10-092
F & W ELECTRICAL CONTRACTORS, INC. (5.11)
A K FUQUAY CONSTRUCTION (0.43)
FLASHER EQUIPMENT COMPANY (2.78)
INTERSTATE BARRICADES & MARKINGS, INC. (4.12)
PRIMATE CONSTRUCTION, LP (3.50)
TRP CONSTRUCTION GROUP, LLC (0.25)
ROADWAY SPECIALTIES, INC. (4.69)
RUCOBA & MAYA CONSTRUCTION, LLC (6.25)
SOUTHERN CUTTING & CORING, LLC (0.04)
BEAVER BOYS SERVICES (0.06)
Contract #11183218
Totals7321502.70728675.867052662.5896.3

CountyUVALDE ETC
HighwayUS 83 ETC
From1.587 MI SW OF SH 127
To2.252 MI SW OF SH 127
CSJ0036-08-054
Proj IDSTP 1902(208)HES
Work TypeSFT
 
38.4523103120.92692541.4822.3
Work Order08-13-19
Work Began03-16-20
Work Completed
Time Computed09-12-19
Contract Working Days254
Addl Days Granted0
Working Days Charged11
Percent Time Used4
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0036-08-054
FIBERTEL, LLC (3.09)
TOTAL HIGHWAY MAINTENANCE, LLC (19.99)
FLASHER EQUIPMENT COMPANY (17.80)
LOZANO CONSTRUCTION COMPANY, INC. (0.69)
Contract #07193241
Totals3103120.92343951.73692541.4822.3

CountyUVALDE
HighwayUS 83
FromFM 1435
ToZAVALA COUNTY LINE
CSJ0037-01-042
Proj IDSTP 2019(170)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
8.04010197040.685919072.8658.0
Work Order12-17-18
Work Began03-04-19
Work Completed
Time Computed01-16-19
Contract Working Days287
Addl Days Granted183
Working Days Charged246
Percent Time Used52
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0037-01-042
HIGHWAY BARRICADES AND SERVICES, LLC (2.34)
A K FUQUAY CONSTRUCTION (2.07)
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED (2.03)
DEPENDABLE FENCE & WELDING CO. INC. (0.60)
PRIMATE CONSTRUCTION, LP (0.49)
STRIPE-A-ZONE, INC. (0.21)
AREA WIDE PROTECTIVE, INC. (0.15)
FLASHER EQUIPMENT COMPANY (0.05)
Contract #11183203
Totals10197040.68169851.345919072.8658.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8