Monthly State Let Construction Report For San Antonio District As Of Apr 11, 2020 Page 6 Of 8

Last Update: Saturday, April 11, 2020
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayVA
FromDISTRICTWIDE GUIDESIGNS FY20
To.
CSJ0915-00-201
Proj IDSTP 2020(682)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011582979.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-201
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04203216
Totals1582979.250.000.000.0

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2018
To.
CSJ0915-00-205
Proj IDSTP 2018(682)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011479469.001204059.5381.3
Work Order05-14-18
Work Began08-23-18
Work Completed
Time Computed06-13-18
Contract Working Days320
Addl Days Granted0
Working Days Charged285
Percent Time Used89
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-205
ARTILLERY, LLC (2.85)
VALLEY STRIPING CORP. (2.08)
Contract #04183004
Totals1479469.0092411.221204059.5381.3

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2018
To.
CSJ0915-00-206
Proj IDSTP 2018(899)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001391447.22214965.6354.9
Work Order08-09-18
Work Began01-28-19
Work Completed
Time Computed09-08-18
Contract Working Days120
Addl Days Granted0
Working Days Charged78
Percent Time Used65
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-206
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183229
Totals391447.220.00214965.6354.9

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-207
Proj IDSTP 2019(169)
Work TypeSIDEWALK, SIGNAL, SIGN, PAV'T MRKNG
 
0.100533807.50549059.6999.9
Work Order01-07-19
Work Began04-01-19
Work Completed
Time Computed02-06-19
Contract Working Days248
Addl Days Granted0
Working Days Charged93
Percent Time Used37
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-207
HEARN CO. (4.62)
TEXAS MATERIALS GROUP, INC. (2.00)
FLASHER EQUIPMENT COMPANY (10.10)
CATO ELECTRIC COMPANY (0.45)
ALAMO CRANE SERVICE, INC. (0.40)
Contract #11183009
Totals533807.5085.23549059.6999.9

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS-RURAL
To.
CSJ0915-00-209
Proj IDSTP 2019(902)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.0011371713.35925254.9067.4
Work Order06-17-19
Work Began08-12-19
Work Completed
Time Computed07-17-19
Contract Working Days71
Addl Days Granted5
Working Days Charged76
Percent Time Used100
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-209
INTERSTATE BARRICADES & MARKINGS, INC. (2.99)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.12)
SAECO ELECTRIC & UTILITY, LTD. (5.53)
Contract #05193040
Totals1371713.3528707.60925254.9067.4

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS-URBAN
To.
CSJ0915-00-210
Proj IDSTP 2019(903)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.0012758844.47227607.578.2
Work Order06-20-19
Work Began07-20-19
Work Completed
Time Computed07-20-19
Contract Working Days322
Addl Days Granted0
Working Days Charged120
Percent Time Used37
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-210
DIIBS SPECIALISTS (2.19)
F & W ELECTRICAL CONTRACTORS, INC. (8.75)
FLASHER EQUIPMENT COMPANY (3.80)
Contract #05193222
Totals2758844.4710000.00227607.578.2

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN COMAL AND
ToBEXAR COUNTIES
CSJ0915-00-211
Proj IDSTP 2019(796)MM
Work TypeTRAFFIC CONTROL DEVICES
 
0.001378363.883197.520.8
CountyCOMAL
HighwayVA
FromVARIOUS LOCATIONS IN NEW BRAUNFELS
To.
CSJ0915-17-069
Proj IDSTP 2019(796)MM
Work TypeTRAFFIC CONTROL DEVICES
 
0.00131575.000.000.0
Work Order07-16-19
Work Began00-00-00
Work Completed
Time Computed08-16-19
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-211
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193202
Totals409938.880.003197.520.7

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN GUADALUPE
ToAND WILSON COUNTIES
CSJ0915-00-220
Proj IDSTP 1902(062)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.0012393563.502064031.4586.2
Work Order07-23-19
Work Began12-02-19
Work Completed
Time Computed08-22-19
Contract Working Days126
Addl Days Granted0
Working Days Charged72
Percent Time Used57
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-220
TRP CONSTRUCTION GROUP, LLC (1.08)
ROADWAY SPECIALTIES, INC. (0.76)
W.A. ROBBINS CONSTRUCTION CO., INC. (0.00)
PBJ CONSTRUCTION (5.53)
Contract #06193039
Totals2393563.50263944.652064031.4586.2

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2019
To.
CSJ0915-00-221
Proj IDSTP 2019(684)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011539906.000.000.0
Work Order05-09-19
Work Began00-00-00
Work Completed
Time Computed06-08-19
Contract Working Days320
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-221
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193228
Totals1539906.000.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-222
Proj IDSTP 2019(904)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011519049.051005170.0066.1
Work Order06-13-19
Work Began00-00-00
Work Completed
Time Computed07-13-19
Contract Working Days320
Addl Days Granted0
Working Days Charged85
Percent Time Used26
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-222
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193241
Totals1519049.05311431.581005170.0066.1

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS-RURAL
To.
CSJ0915-00-223
Proj IDSTP 2019(905)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.0013461234.911186325.6534.2
Work Order06-20-19
Work Began09-23-19
Work Completed
Time Computed07-20-19
Contract Working Days212
Addl Days Granted0
Working Days Charged102
Percent Time Used48
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-223
ENVIRONMENTAL SAFETY SERVICES, INC. (4.62)
SAECO ELECTRIC & UTILITY, LTD. (5.48)
TEXAS MATERIALS GROUP, INC. (25.34)
LONE STAR SITEWORK, LLC (4.14)
TRP CONSTRUCTION GROUP, LLC (4.88)
Contract #05193022
Totals3461234.91162181.971186325.6534.2

CountyBEXAR
HighwayCS
FromOLD SEGUIN ROAD @ SALADO CREEK
To.
CSJ0915-12-531
Proj IDBR 1402(213)
Work TypeBRIDGE REPLACEMENT
 
742387.250.000.0
CountyBEXAR
HighwayCS
FromOLD SEGUIN ROAD @ SALADO CREEK
To.
CSJ0915-12-663
Proj IDCC 915-12-531
Work TypeUTILITY ADJUSTMENTS
 
246247.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-18-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days116
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-531
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01203217
Totals988634.750.000.000.0

CountyBEXAR
HighwayCS
FromON CALLAGHAN ROAD
ToAT INGRAM ROAD
CSJ0915-12-566
Proj IDSTP 2019(899)HES
Work TypeSAFETY
 
1.4001774682.651247576.1770.2
Work Order06-17-19
Work Began10-21-19
Work Completed
Time Computed07-17-19
Contract Working Days222
Addl Days Granted0
Working Days Charged96
Percent Time Used43
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-566
CATO ELECTRIC COMPANY (0.10)
LOZANO CONSTRUCTION COMPANY, INC. (0.00)
FIBERTEL, LLC (7.40)
ALAMO CRANE SERVICE, INC. (0.49)
ALAMO TRUCKING, INC. (0.00)
FLASHER EQUIPMENT COMPANY (2.45)
Contract #05193235
Totals1774682.6536365.231247576.1770.2

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-591
Proj IDNH 1702(678)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001510193.00446397.7587.4
Work Order09-14-17
Work Began01-02-18
Work Completed
Time Computed10-14-17
Contract Working Days95
Addl Days Granted0
Working Days Charged95
Percent Time Used100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-591
FLASHER EQUIPMENT COMPANY (2.92)
Contract #08173010
Totals510193.004000.00446397.7587.4

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-592
Proj IDNH 1702(679)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001682419.00556948.1181.6
Work Order09-14-17
Work Began01-08-18
Work Completed
Time Computed10-14-17
Contract Working Days82
Addl Days Granted0
Working Days Charged82
Percent Time Used100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-592
FLASHER EQUIPMENT COMPANY (3.12)
Contract #08173230
Totals682419.005000.00556948.1181.6

CountyBEXAR
HighwayVA
FromIN SAN ANTONIO
ToAT TRANSGUIDE CENTER
CSJ0915-12-602
Proj IDSTP 1902(097)MM
Work TypeTNR
 
0.0015866947.001715314.2729.2
Work Order09-18-19
Work Began00-00-00
Work Completed
Time Computed10-18-19
Contract Working Days190
Addl Days Granted0
Working Days Charged68
Percent Time Used35
Contractor(s)
SPAW GLASS CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-602
ALAMO1 (0.74)
INTERTECH FLOORING (0.47)
JEWEL"S COMMERCIAL CLEANING (0.08)
SAN ANTONIO FLOOR FINISHERS, INC. (0.51)
THE LEVY COMPANY, INC. (13.22)
WESTERN STATES FIRE PROTECTION CO. (1.76)
SAMUEL DEAN SHEET METAL, INC. (4.67)
SOUTH TEXAS DRYWALL & CONSTRUCTION, INC. (2.26)
FCS FOX COMMERCIAL SERVICES, LLC (1.51)
JACK LAURENCE CORPORATION (1.41)
F. A. MC COMAS, INC. (0.58)
ONE DIVERSIFIED, LLC (45.97)
Contract #08193055
Totals5866947.00712130.241715314.2729.2

CountyBEXAR
HighwayCS
FromON BULVERDE RD AT TPC PKWY
To.
CSJ0915-12-622
Proj IDSTP 1902(200)HES
Work TypeSFT
 
2.4001694497.851657318.1997.8
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed09-12-19
Contract Working Days140
Addl Days Granted0
Working Days Charged91
Percent Time Used65
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-622
FIBERTEL, LLC (5.01)
LOZANO TRUCKING COMPANY, INC. (0.00)
ALAMO CRANE SERVICE, INC. (0.06)
FLASHER EQUIPMENT COMPANY (4.96)
Contract #07193244
Totals1694497.85463415.811657318.1997.8

CountyATASCOSA
HighwayCR
FromON CR 324 0.5 MI W OF SH 16
ToAT GOOSE CREEK
CSJ0915-13-028
Proj IDBR 1702(572)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.001823867.00610125.5774.0
Work Order04-16-19
Work Began07-08-19
Work Completed
Time Computed05-16-19
Contract Working Days153
Addl Days Granted0
Working Days Charged144
Percent Time Used94
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-13-028
FLASHER EQUIPMENT COMPANY (0.78)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (12.19)
BOWMAN ENGINEERING & CONSULTING, INC. (0.52)
Contract #03193020
Totals823867.0073144.44610125.5774.0

CountyATASCOSA
HighwayCR
FromCR 422 @ LA PARITA CREEK
To.
CSJ0915-13-029
Proj IDBR 2019(907)
Work TypeBRIDGE REPLACEMENT
 
0.066619853.50603651.4797.3
Work Order06-20-19
Work Began09-03-19
Work Completed
Time Computed07-20-19
Contract Working Days102
Addl Days Granted0
Working Days Charged100
Percent Time Used98
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-13-029
FLASHER EQUIPMENT COMPANY (2.43)
LONE STAR EROSION CONTROL (24.64)
LONE STAR PAVING COMPANY (3.25)
BATTEN DRILLING, INC. (7.82)
Contract #05193052
Totals619853.5024717.28603651.4797.3

CountyCOMAL
HighwayCS
FromN SOLM RD @ DRY COMAL CREEK
To.
CSJ0915-17-067
Proj IDBR 2019(908)
Work TypeBRIDGE REPLACEMENT
 
0.0851589567.351432644.9390.1
Work Order06-20-19
Work Began07-22-19
Work Completed
Time Computed07-20-19
Contract Working Days213
Addl Days Granted6
Working Days Charged157
Percent Time Used71
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-17-067
AUSTIN MATERIALS, LLC (6.78)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.38)
FLASHER EQUIPMENT COMPANY (1.50)
LONE STAR EROSION CONTROL (8.20)
VOGES DRILLING CO. (7.12)
Contract #05193032
Totals1589567.3570951.701432644.9390.1

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8