Monthly State Let Construction Report For San Antonio District As Of Sep 18, 2019 Page 6 Of 8

Last Update: Thursday, September 19, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyATASCOSA
HighwaySH 16
FromAT ATASCOSA RIVER
To.
CSJ0613-02-063
Proj IDC 613-2-63
Work TypeGRAD, BSE, STR, SURF, PAV'T MRKNGS
 
0.4975704330.283569913.9862.5
Work Order06-11-18
Work Began11-26-18
Work Completed
Time Computed07-11-18
Contract Working Days252
Addl Days Granted0
Working Days Charged171
Percent Time Used67
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0613-02-063
ENVIRONMENTAL SAFETY SERVICES, INC. (6.55)
GEOSOURCE, INC. (1.93)
FLASHER EQUIPMENT COMPANY (1.14)
MCL CONTRACTING, LLC (0.71)
K. L. DURHAM CONSTRUCTION, L.L.C. (1.08)
W. W. FOUNDATION DRILLING, LTD. (26.09)
HB FARMER FOUNDATION, LLC (7.38)
Contract #05183207
Totals5704330.28225973.133569913.9862.5

CountyATASCOSA
HighwayFM 140
FromSH 16
ToLA PARITA CREEK
CSJ0748-05-040
Proj IDSTP 2019(110)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
3.4584730331.281866237.3139.4
Work Order11-15-18
Work Began01-14-19
Work Completed
Time Computed12-15-18
Contract Working Days358
Addl Days Granted0
Working Days Charged145
Percent Time Used40
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0748-05-040
AREA WIDE PROTECTIVE, INC. (0.49)
THE LEVY COMPANY, INC. (0.11)
LONE STAR EROSION CONTROL (1.45)
MURRAY CONSTRUCTION (0.67)
PAVEMENT MARKINGS INC. (2.45)
RELMCO, INC. (15.52)
BEAVER BOYS SERVICES (0.32)
GEOSOURCE, INC. (0.00)
Contract #10183008
Totals4730331.28528514.551866237.3139.4

CountyMEDINA
HighwayFM 462
FromCR 433
ToCASTRO AVENUE
CSJ0848-04-046
Proj IDSTP 2018(596)
Work TypeWIDEN AND ADD SHOULDERS
 
2.2541968967.682058024.8699.9
Work Order04-13-18
Work Began07-05-18
Work Completed
Time Computed05-13-18
Contract Working Days257
Addl Days Granted0
Working Days Charged193
Percent Time Used75
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0848-04-046
LONE STAR EROSION CONTROL (0.71)
MV HENKE COMPANY, LLC (0.58)
FUQUAY, INC. (2.05)
SAECO ELECTRIC & UTILITY, LTD. (2.34)
DEPENDABLE FENCE & WELDING CO. INC. (1.36)
FLASHER LIMITED (1.58)
Contract #03183015
Totals1968967.680.002058024.8699.9

CountyECTOR
HighwayVA
FromON IH 10 IN PECOS COUNTY
To.
CSJ0906-00-180
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001112682.11135514.8499.9
CountyTOM GREEN
HighwayVA
FromON IH 10 FROM KIMBLE/KERR CO LINE
ToTO CROCKETT/PECOS COUNTY LINE
CSJ0907-00-183
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001683074.05792988.7899.9
CountyBEXAR
HighwayVA
FromON IH 10 FROM CITY OF BOERNE
ToKIMBLE/KERR COUNTY LINE
CSJ0915-00-194
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001960828.161149740.0899.9
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed04-14-17
Contract Working Days123
Addl Days Granted45
Working Days Charged164
Percent Time Used97
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-180
LIGHT IT UP ELECTRIC (10.81)
JCD CONSTRUCTION, LLC (2.68)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (13.71)
FLASHER EQUIPMENT COMPANY (1.13)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.36)
GRUPO CONSTRUCTOR VELACOR, LLC (2.73)
Contract #02173235
Totals1756584.3217107.492078243.7099.9

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN ATASCOSA,
ToFRIO & MEDINA COUNTIES
CSJ0915-00-168
Proj IDSTP 2018(865)
Work TypeCONSTRUCT CURB RAMPS
 
0.0011394063.861317613.2694.5
Work Order06-11-18
Work Began12-03-18
Work Completed
Time Computed07-11-18
Contract Working Days193
Addl Days Granted0
Working Days Charged112
Percent Time Used58
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-168
8A ELECTRIC, INC. (10.15)
AMERICAN SIGNAL EQUIPMENT CO. (1.13)
DEPENDABLE FENCE & WELDING CO. INC. (0.87)
Contract #05183010
Totals1394063.860.001317613.2694.5

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BANDERA
ToAND UVALDE COUNTIES
CSJ0915-00-179
Proj IDSTP 2018(866)
Work TypeCONSTRUCT CURB RAMPS
 
0.0011236777.05990455.2680.0
Work Order06-11-18
Work Began07-16-18
Work Completed
Time Computed07-11-18
Contract Working Days186
Addl Days Granted30
Working Days Charged216
Percent Time Used100
Contractor(s)
F. D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-179
F & W ELECTRICAL CONTRACTORS, INC. (4.70)
SHORT-LINE CORPORATION (3.00)
Contract #05183213
Totals1236777.0599000.12990455.2680.0

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2018
To.
CSJ0915-00-181
Proj IDSTP 2018(318)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011424651.881318642.0392.5
Work Order03-08-18
Work Began08-14-18
Work Completed
Time Computed05-01-18
Contract Working Days320
Addl Days Granted0
Working Days Charged226
Percent Time Used70
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-181
C2 CONCRETE, INC. (2.14)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (3.11)
SO-TEX SERVICES LLC (1.91)
CALAME CONTRACTING, LLC (4.49)
GRUPO CONSTRUCTOR VELACOR, LLC (1.14)
Contract #02183215
Totals1424651.8815801.921318642.0392.5

CountyBEXAR
HighwayVA
FromDISTRICTWIDE GUIDESIGNS FY18
To.
CSJ0915-00-182
Proj IDSTP 2018(733)
Work TypeDISTRICTWIDE GUIDESIGNS FY18
 
0.0011921528.61897808.3446.7
Work Order05-08-18
Work Began02-05-19
Work Completed
Time Computed06-07-18
Contract Working Days360
Addl Days Granted0
Working Days Charged108
Percent Time Used30
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-182
ROADWAY SPECIALTIES, INC. (4.40)
JAG PUBLIC SAFETY, LLC (16.26)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (1.87)
Contract #04183207
Totals1921528.61117906.78897808.3446.7

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-186
Proj IDSTP 1702(556)
Work TypeTRAFFIC SIGNAL REHAB/UPGRADE
 
0.0012664496.903294782.6799.9
Work Order08-11-17
Work Began02-28-19
Work Completed
Time Computed09-10-17
Contract Working Days319
Addl Days Granted25
Working Days Charged223
Percent Time Used64
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-186
FIBERTEL, LLC (0.00)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.47)
HEARN CO. (0.96)
ALAMO CRANE SERVICE, INC. (0.95)
Contract #07173035
Totals2664496.9079309.613294782.6799.9

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2019
To.
CSJ0915-00-191
Proj IDC 915-00-191
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011540867.8119414.931.2
Work Order03-18-19
Work Began00-00-00
Work Completed
Time Computed04-17-19
Contract Working Days320
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-191
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02193224
Totals1540867.810.0019414.931.2

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-192
Proj IDSTP 2019(777)
Work TypeSIGNALS,SIGNS,PAV'T MRKS
 
0.001817876.0077550.009.4
Work Order05-10-19
Work Began06-24-19
Work Completed
Time Computed06-09-19
Contract Working Days100
Addl Days Granted0
Working Days Charged10
Percent Time Used10
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-192
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193026
Totals817876.000.0077550.009.4

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2017
To.
CSJ0915-00-204
Proj IDSTP 2017(894)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011349187.001313551.8597.3
Work Order05-09-17
Work Began07-18-17
Work Completed
Time Computed07-03-17
Contract Working Days320
Addl Days Granted0
Working Days Charged314
Percent Time Used98
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-204
L & R FOUNDATION DRILLING, INC. (1.03)
M & M STRIPING & POWER WASHING, LLC (4.15)
MINTCO GROUP LLC (1.60)
Contract #04173003
Totals1349187.000.001313551.8597.3

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2018
To.
CSJ0915-00-205
Proj IDSTP 2018(682)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011479469.00643813.6443.5
Work Order05-14-18
Work Began08-23-18
Work Completed
Time Computed06-13-18
Contract Working Days320
Addl Days Granted0
Working Days Charged179
Percent Time Used55
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-205
ARTILLERY, LLC (2.85)
VALLEY STRIPING CORP. (2.08)
Contract #04183004
Totals1479469.0021571.04643813.6443.5

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2018
To.
CSJ0915-00-206
Proj IDSTP 2018(899)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.001391447.22175974.6344.9
Work Order08-09-18
Work Began01-28-19
Work Completed
Time Computed09-08-18
Contract Working Days120
Addl Days Granted0
Working Days Charged71
Percent Time Used59
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-206
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183229
Totals391447.2262450.00175974.6344.9

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-207
Proj IDSTP 2019(169)
Work TypeSIDEWALK, SIGNAL, SIGN, PAV'T MRKNG
 
0.100533807.50358432.7667.1
Work Order01-07-19
Work Began04-01-19
Work Completed
Time Computed02-06-19
Contract Working Days248
Addl Days Granted0
Working Days Charged57
Percent Time Used22
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-207
HEARN CO. (4.62)
TEXAS MATERIALS GROUP, INC. (2.00)
FLASHER EQUIPMENT COMPANY (2.41)
Contract #11183009
Totals533807.5029283.77358432.7667.1

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS-RURAL
To.
CSJ0915-00-209
Proj IDSTP 2019(902)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.0011371713.35295777.1021.5
Work Order06-17-19
Work Began00-00-00
Work Completed
Time Computed07-17-19
Contract Working Days71
Addl Days Granted0
Working Days Charged15
Percent Time Used21
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-209
INTERSTATE BARRICADES & MARKINGS, INC. (2.99)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.12)
SAECO ELECTRIC & UTILITY, LTD. (5.53)
Contract #05193040
Totals1371713.35295777.10295777.1021.5

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS-URBAN
To.
CSJ0915-00-210
Proj IDSTP 2019(903)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.0012758844.470.000.0
Work Order06-20-19
Work Began00-00-00
Work Completed
Time Computed07-20-19
Contract Working Days322
Addl Days Granted0
Working Days Charged5
Percent Time Used1
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-210
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193222
Totals2758844.470.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN COMAL AND
ToBEXAR COUNTIES
CSJ0915-00-211
Proj IDSTP 2019(796)MM
Work TypeTRAFFIC CONTROL DEVICES
 
0.001378363.880.000.0
CountyCOMAL
HighwayVA
FromVARIOUS LOCATIONS IN NEW BRAUNFELS
To.
CSJ0915-17-069
Proj IDSTP 2019(796)MM
Work TypeTRAFFIC CONTROL DEVICES
 
0.00131575.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-211
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193202
Totals409938.880.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN GUADALUPE
ToAND WILSON COUNTIES
CSJ0915-00-220
Proj IDSTP 1902(062)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.0012393563.500.000.0
Work Order07-23-19
Work Began00-00-00
Work Completed
Time Computed08-22-19
Contract Working Days126
Addl Days Granted0
Working Days Charged7
Percent Time Used5
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-220
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193039
Totals2393563.500.000.000.0

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2019
To.
CSJ0915-00-221
Proj IDSTP 2019(684)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011539906.000.000.0
Work Order05-09-19
Work Began00-00-00
Work Completed
Time Computed06-08-19
Contract Working Days320
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-221
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193228
Totals1539906.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8