Monthly State Let Construction Report For San Antonio District As Of Apr 11, 2020 Page 8 Of 8

Last Update: Saturday, April 11, 2020
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOMAL
HighwayMH
FromIN NEW BRAUNFELS ON SAN ANTONIO ST
ToAT COMAL RIVER
CSJ8408-15-006
Proj IDBR 2019(910)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.0014518896.313718850.5782.2
Work Order06-20-19
Work Began08-16-19
Work Completed
Time Computed09-03-19
Contract Working Days470
Addl Days Granted0
Working Days Charged208
Percent Time Used44
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 8408-15-006
AUSTIN WOOD RECYCLING (0.65)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.27)
MCL CONTRACTING, LLC (1.49)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.06)
LONE STAR PAVING COMPANY (2.48)
VOGES DRILLING CO. (3.11)
THE LEVY COMPANY, INC. (2.19)
SOUTH TEXAS PAINTING COMPANY (0.23)
TRP CONSTRUCTION GROUP, LLC (0.97)
TEXAS CUTTING & CORING GP, INC. (0.44)
J. R. (JOE) RAMON & SONS, INC. (0.63)
FRANK JR REINFORCEMENT LLC (0.18)
Contract #05193220
Totals4518896.31396599.363718850.5782.2