Monthly Local Let Maintenance Report For San Antonio District As Of Apr 12, 2024 Page 1 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKENDALL
HighwayIH0010
FromVARIOUS LOCATIONS
ToIN BEXAR COUNTY
CSJ6194-73-001
Proj IDRMC - 619473001
Work TypeLITTER PICK UP
 
0.00159313.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GOLDEN ARBOR TEC LLC
SUBCONTRACTOR(S) FOR CCSJ: 6194-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09091505
Totals59313.600.000.000.0

CountyGUADALUPE
HighwayFM0078
FromWEST FORK YOUNG CREEK BRIDGE
ToWEST FORK YOUNG CREEK BRIDGE
CSJ6201-92-001
Proj IDBPM - 620192001
Work TypeSCOUR REPAIR
 
0.10052978.930.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
C3 ENVIRONMENTAL SPECIALTIES, LP
SUBCONTRACTOR(S) FOR CCSJ: 6201-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01101502
Totals52978.930.000.000.0

CountyBEXAR
HighwayPA1502
FromPA 1502 (WURZBACH PARKWAY)
To(NEW LOCATION)
CSJ6237-07-001
Proj IDRMC - 623707001
Work TypeEXCAVATION
 
0.001455087.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SLACK & CO. CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12111501
Totals455087.600.000.000.0

CountyBEXAR
HighwayFM1957
FromFM1957 AT
ToHEB
CSJ6327-64-001
Proj IDRMC - 632764001
Work TypeINSTALL LOOM TURNAROUND
 
0.001191351.88173517.08100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-09-18
Work Began07-16-18
Work Completed09-03-18
Time Computed07-16-18
Contract Working Days35
Addl Days Granted0
Working Days Charged35
Percent Time Used100
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6327-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05181501
Totals191351.880.00173517.08100.0

CountyMEDINA
HighwayUS0090
FromMEDINA COUNTY
ToMEDINA COUNTY
CSJ6348-48-001
Proj IDRMC - 634848001
Work TypePICNIC AREA MAINTENANCE
 
0.00144300.0090700.00100.0
Work Order10-26-19
Work Began11-04-19
Work Completed02-15-24
Time Computed11-04-19
Contract Working Days730
Addl Days Granted820
Working Days Charged1,550
Percent Time Used100
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6348-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08191502
Totals44300.000.0090700.00100.0

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS WITHIN KERRVILLE
ToMAINTENANCE SECTIONS
CSJ6382-98-001
Proj IDMMC - 638298001
Work TypeLIMESTONE ROCK AND ASPHALT
 
0.010213205.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6382-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07211510
Totals213205.000.000.000.0

CountyMEDINA
HighwayUS0090
FromVARIOUS LOCATIONS IN HONDO
ToMAINTENANCE SECTION
CSJ6392-26-001
Proj IDMMC - 639226001
Work TypeHOT MIX
 
0.010237750.00715093.3899.9
Work Order01-25-23
Work Began04-03-23
Work Completed
Time Computed02-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged425
Percent Time Used58
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6392-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221510
Totals237750.00164656.52715093.3899.9

CountyBEXAR
HighwayIH0410
From4615 NW LOOP 410
To4615 NW LOOP 410
CSJ6399-68-001
Proj IDSUP - 639968001
Work TypeJANITORIAL MAINTENANCE
 
0.010437385.44319823.9873.1
Work Order03-10-22
Work Began03-11-22
Work Completed
Time Computed03-14-22
Contract Working Days730
Addl Days Granted31
Working Days Charged749
Percent Time Used98
Contractor(s)
WORKQUEST
ENDEAVORS UNLIMITED, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6399-68-001
ENDEAVORS UNLIMITED, INC. (0.00)
Contract #02221532
Totals437385.4411670.00319823.9873.1

CountyBEXAR
HighwayFM1976
From6550 WALZEM RD
To6550 WALZEM RD
CSJ6399-73-001
Proj IDSUP - 639973001
Work TypeJANITORIAL MAINTENANCE
 
0.01072127.1232423.9544.9
Work Order03-01-22
Work Began03-05-22
Work Completed
Time Computed03-07-22
Contract Working Days731
Addl Days Granted31
Working Days Charged756
Percent Time Used99
Contractor(s)
WORKQUEST
ENDEAVORS UNLIMITED, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6399-73-001
ENDEAVORS UNLIMITED, INC. (0.00)
Contract #03221530
Totals72127.12731.1232423.9544.9

CountyBEXAR
HighwayIH0410
From7395 PEARSALL RD
To7395 PEARSALL RD
CSJ6404-41-001
Proj IDSUP - 640441001
Work TypeSTATE USE CONTRACT
 
0.010116038.8452732.0945.4
Work Order04-28-22
Work Began05-04-22
Work Completed
Time Computed05-04-22
Contract Working Days731
Addl Days Granted0
Working Days Charged698
Percent Time Used95
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6404-41-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #04221530
Totals116038.841592.2652732.0945.4

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN EAST AND WEST BEXAR
ToMAINTENANCE SECTIONS
CSJ6406-26-001
Proj IDMMC - 640626001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010266395.00172937.2664.9
Work Order01-10-23
Work Began06-06-23
Work Completed
Time Computed01-17-23
Contract Working Days365
Addl Days Granted366
Working Days Charged440
Percent Time Used60
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221511
Totals266395.000.00172937.2664.9

CountyCOMAL
HighwayIH0035
FromVARIOUS LOCATIONS IN NEW BRAUNFELS
ToMAINTENANCE SECTION
CSJ6406-30-001
Proj IDMMC - 640630001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010104450.00103740.4399.3
Work Order00-00-00
Work Began06-05-23
Work Completed
Time Computed02-02-23
Contract Working Days365
Addl Days Granted366
Working Days Charged424
Percent Time Used58
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221512
Totals104450.000.00103740.4399.3

CountyATASCOSA
HighwayIH0037
FromVARIOUS LOCATIONS IN PLEASANTON
ToMAINTENANCE SECTION
CSJ6406-32-001
Proj IDMMC - 640632001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010283200.001561441.8799.9
Work Order01-12-23
Work Began01-25-23
Work Completed
Time Computed01-19-23
Contract Working Days365
Addl Days Granted366
Working Days Charged438
Percent Time Used59
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221513
Totals283200.00217087.181561441.8799.9

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN SEGUIN
ToMAINTENANCE SECTION
CSJ6406-36-001
Proj IDMMC - 640636001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010272500.00410144.9499.9
Work Order00-00-00
Work Began01-23-23
Work Completed
Time Computed01-16-23
Contract Working Days365
Addl Days Granted366
Working Days Charged441
Percent Time Used60
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221514
Totals272500.0057067.62410144.9499.9

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS THROUGHOUT
ToSAN ANTONIO DISTRICT
CSJ6407-71-001
Proj IDMMC - 640771001
Work TypeFLEXIBLE BASE
 
0.010278100.003314.661.1
Work Order00-00-00
Work Began02-02-24
Work Completed
Time Computed08-19-23
Contract Working Days365
Addl Days Granted0
Working Days Charged226
Percent Time Used61
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6407-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231510
Totals278100.000.003314.661.1

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS THROUGHOUT
ToSAN ANTONIO DISTRICT
CSJ6407-73-001
Proj IDMMC - 640773001
Work TypeROCK/RIPRAP
 
0.010270121.0098171.1536.3
Work Order00-00-00
Work Began09-12-23
Work Completed
Time Computed08-26-23
Contract Working Days365
Addl Days Granted0
Working Days Charged219
Percent Time Used60
Contractor(s)
USA AMTECH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6407-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231511
Totals270121.0021950.6598171.1536.3

CountyWILSON
HighwaySH0097
From317 SH 97 E
To317 SH 97 E
CSJ6408-57-001
Proj IDSUP - 640857001
Work TypeJANITORIAL MAINTENANCE
 
0.010111099.5634348.9530.9
Work Order06-13-22
Work Began06-13-22
Work Completed
Time Computed06-13-22
Contract Working Days731
Addl Days Granted0
Working Days Charged658
Percent Time Used90
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6408-57-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #05221532
Totals111099.56997.3434348.9530.9

CountyATASCOSA
HighwayUS0281
From2154 SOUTH 2ND STREET
To2154 SOUTH 2ND STREET
CSJ6409-57-001
Proj IDSUP - 640957001
Work TypeJANITORIAL MAINTENANCE
 
0.010110412.4435846.9732.4
Work Order06-06-22
Work Began06-06-22
Work Completed
Time Computed06-07-22
Contract Working Days731
Addl Days Granted0
Working Days Charged665
Percent Time Used90
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6409-57-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #05221531
Totals110412.441008.8935846.9732.4

CountyGUADALUPE
HighwaySH0046
From2028 HWY 46 N
To2028 HWY 46 N
CSJ6409-59-001
Proj IDSUP - 640959001
Work TypeJANITORIAL MAINTENANCE
 
0.010116594.2427984.6224.0
Work Order06-07-22
Work Began06-07-22
Work Completed
Time Computed06-06-22
Contract Working Days731
Addl Days Granted0
Working Days Charged665
Percent Time Used90
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6409-59-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #05221530
Totals116594.24926.9527984.6224.0

CountyCOMAL
HighwayIH0035
From4102 IH 35 SOUTH
To4102 IH 35 SOUTH
CSJ6410-21-001
Proj IDSUP - 641021001
Work TypeJANITORIAL MAINTENANCE
 
0.010132771.5648523.3036.5
Work Order06-13-22
Work Began06-20-22
Work Completed
Time Computed06-20-22
Contract Working Days731
Addl Days Granted0
Working Days Charged651
Percent Time Used89
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6410-21-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #05221533
Totals132771.561439.7448523.3036.5

page 1 | page 2 | page 3