Monthly Local Let Maintenance Report For San Angelo District As Of Mar 13, 2024 Page 5 Of 5
Last Update: Wednesday, March 13, 2024
|
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | CONCHO |
Highway | US0083 |
From | VARIOUS LOCATIONS IN THE SAN ANGELO DIST |
To | VARIOUS LOCATIONS IN SAN ANGELO DISTRICT |
CSJ | 6460-73-001 |
Proj ID | MMC - 646073001 |
Work Type | FLEXIBLE BASE |
|
| 0.010 | 161409.00 | | 50305.46 | 31.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-17-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 44 |
Percent Time Used | 24 |
Contractor(s) |
CSA MATERIALS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6460-73-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12230702 |
| Totals | 161409.00 | 50305.46 | 50305.46 | 31.1 |
|
County | KIMBLE |
Highway | US0083 |
From | VARIOUS LOCATIONS IN THE SAN ANGELO DIST |
To | VARIOUS LOCATIONS IN SAN ANGELO DISTRICT |
CSJ | 6462-77-001 |
Proj ID | RMC - 646277001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 213125.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 360 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6462-77-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03240702 |
| Totals | 213125.00 | 0.00 | 0.00 | 0.0 |
|