Monthly State Let Construction Report For Tyler District As Of Aug 23, 2019 Page 1 Of 4

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyVAN ZANDT ETC
HighwayUS 80 ETC
FromKAUFMAN C/L, E
To0.819 MI W OF FM 2965,WILLS PNT CL
CSJ0095-06-071
Proj IDSTP 2019(853)HESG
Work TypeSAFETY
 
53.070499197.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-19
Work Began08-15-19
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0095-06-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193041
Totals499197.050.000.000.0

CountyVAN ZANDT ETC
HighwayUS 80 ETC
From0.77 MI E OF SH 19, E
ToGR SALINE WCL, 1.5 MI W OF SH 110
CSJ0095-07-060
Proj IDSTP 2019(334)
Work TypeSEAL COAT AND PAVEMENT MARKINGS
 
247.76314140387.287358945.4852.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-11-19
Work Began07-08-19
Work Completed
Time Computed00-00-00
Contract Working Days109
Addl Days Granted0
Working Days Charged71
Percent Time Used65
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0095-07-060
INTERSTATE BARRICADES & MARKINGS, INC. (8.06)
INNOVATIVE ROADWAY SOLUTIONS LLC (1.54)
STRIPING TECHNOLOGY, L.P. (5.81)
BRYDL CONTRACTING, INC. (1.28)
Contract #12183205
Totals14140387.285179243.217358945.4852.0

CountyGREGG
HighwayUS 80
FromSL 485, E 1.15 MI
ToLOCKERPLANT RD IN GLADEWATER
CSJ0096-04-066
Proj IDNH 2017(893)
Work TypeGR,BS,HMAC SURF,STRM SWR,C&G,SIGNS
 
0.8373538933.213801033.02100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-17
Work Began06-20-17
Work Completed08-22-19
Time Computed00-00-00
Contract Working Days190
Addl Days Granted99
Working Days Charged304
Percent Time Used105
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0096-04-066
ISAACS CONSTRUCTION SERVICES, LLC. (1.24)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.93)
PANOLA SIGN & BARRICADE, INC. (0.39)
MAC TRANSPORTATION, LTD, L.L.P. (1.97)
STRIPING TECHNOLOGY, L.P. (0.76)
TEXOP CONSTRUCTION (1.84)
SOUTHWEST ENVIRONMENT SERIVES, LLC (2.04)
Contract #04173030
Totals3538933.210.003801033.02100.0

CountyVAN ZANDT ETC
HighwaySH 19 ETC
FromAT FM 1861
ToNEAR HENDERSON C/L
CSJ0108-02-034
Proj IDSTP 1902(030)HES
Work TypeTRAFFIC CONTROL DEVICES
 
3.751508062.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-02-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193044
Totals508062.500.000.000.0

CountyHENDERSON ETC
HighwaySH 19 ETC
FromVAN ZANDT C/L,S
To0.188 MI N OF US175/NE SL7 (CR3718)
CSJ0108-03-042
Proj IDSTP 2019(325)HES
Work TypePROFILE EDGELINE & CENTERLINE MKGS
 
35.245421343.10241505.4257.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-25-19
Work Began05-20-19
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged33
Percent Time Used78
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0108-03-042
AREA WIDE PROTECTIVE, INC. (1.42)
Contract #01193030
Totals421343.10133420.67241505.4257.3

CountyHENDERSON
HighwaySH 19
FromFM 1615, SOUTH 3.8 MI
To0.3 MI S OF COON CREEK BRIDGE
CSJ0108-04-037
Proj IDSTP 1702(091)
Work TypeGR,STRS,ACP SURF,FLEX BS,CAM,OCST
 
3.8364949012.535280349.0999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began08-08-17
Work Completed
Time Computed00-00-00
Contract Working Days295
Addl Days Granted3
Working Days Charged315
Percent Time Used105
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-04-037
COLD CREEK CONSTRUCTION, LTD (1.34)
J & M CONTRACTING, COMPANY (13.03)
TOTAL HIGHWAY MAINTENANCE, LLC (0.74)
SAN-ANN-CO., INC. (0.51)
FORTSON CONTRACTING, INC. (0.15)
AREA WIDE PROTECTIVE, INC. (0.29)
NIXON ENGINEERING, L.L.C. (0.09)
WACO DRILLING CO., INC. (0.02)
BIG CREEK CONSTRUCTION, LTD. (33.03)
Contract #05173028
Totals4949012.5344273.165280349.0999.9

CountyANDERSON
HighwayUS 287
FromFM 2419, S
To1.7 MI N OF SH 294 IN ELKHART
CSJ0109-01-062
Proj IDSTP 2019(092)
Work TypeBS RPR,TRT SBGR,ACP BS,OCST,PFC SRF
 
4.0066180316.712092708.4333.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-18
Work Began01-07-19
Work Completed
Time Computed00-00-00
Contract Working Days195
Addl Days Granted40
Working Days Charged103
Percent Time Used43
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-01-062
CHEROKEE SERVICES (0.15)
FORTSON CONTRACTING, INC. (0.46)
J & M CONTRACTING, COMPANY (9.08)
MURRAY CONSTRUCTION (0.44)
NIXON ENGINEERING (0.43)
PANOLA SIGN & BARRICADE, INC. (0.36)
STRIPING TECHNOLOGY, L.P. (1.32)
WOLFE CONSTRUCTION GROUP, INC. (2.09)
Contract #10183211
Totals6180316.71556395.532092708.4333.8

CountyANDERSON
HighwayUS 287
From0.154 MI S OF SH 294 IN ELKHART, S
ToHOUSTON C/L (3 MI N OF BU 287V)
CSJ0109-02-026
Proj IDSTP 2018(809)
Work TypePLNG,ACP,OCST,PFC,PVT MRKG
 
4.9673987345.303802321.3495.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-18
Work Began08-16-18
Work Completed
Time Computed00-00-00
Contract Working Days73
Addl Days Granted0
Working Days Charged88
Percent Time Used120
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0109-02-026
AREA WIDE PROTECTIVE, INC. (0.17)
COMEN ENTERPRISE LLC (0.80)
STRIPE-A-ZONE, INC. (0.36)
STRIPING TECHNOLOGY, L.P. (1.71)
TEXAS ORGANIC ENTERPRISES, LTD (0.17)
NIXON ENGINEERING (0.00)
Contract #05183256
Totals3987345.300.003802321.3495.7

CountyCHEROKEE
HighwayUS 84
FromUS 69 IN RUSK, N & E
To.46 MI E OF SH 110, NEAR PR50
CSJ0123-03-021
Proj IDC 123-3-21
Work TypeMILL & INLAY, SURF, PVT MRKG
 
1.3382742753.503018986.2599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-18
Work Began01-07-19
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted6
Working Days Charged46
Percent Time Used36
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0123-03-021
PANOLA SIGN & BARRICADE, INC. (0.46)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.10)
STRIPING TECHNOLOGY, L.P. (1.47)
R & G CONSTRUCTION, LLC (14.20)
Contract #05183012
Totals2742753.5025100.163018986.2599.9

CountyHENDERSON
HighwaySH 31
FromAT HENDERSON CNTY FAIRPARK COMPLEX
To0.7 MI NE OF US175/SL7 IN ATHENS
CSJ0164-01-072
Proj IDNH 2019(089)
Work TypeLANDSCAPE,LIGHTING,PIPE ENTRANCE
 
0.190144985.00128851.6288.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-18-19
Work Began04-22-19
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged47
Percent Time Used92
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0164-01-072
TX DOWN UNDER CONSTRUCTION, LLC (2.58)
Contract #02193033
Totals144985.006015.62128851.6288.8

CountySMITH
HighwaySH 31
FromSW SL 323 IN TYLER, E
To0.35 MI E OF US271, BROADWAY AVE
CSJ0164-04-160
Proj IDC 164-4-160
Work TypePLNG,PVMT RPR,OCST,PVMT MRKG
 
2.4193587845.301449234.9040.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-18
Work Began07-08-19
Work Completed
Time Computed00-00-00
Contract Working Days58
Addl Days Granted0
Working Days Charged20
Percent Time Used34
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0164-04-160
TEXOP CONSTRUCTION (4.67)
PANOLA SIGN & BARRICADE, INC. (0.32)
STRIPING TECHNOLOGY, L.P. (2.36)
Contract #07183246
Totals3587845.301416765.701449234.9040.3

CountySMITH
HighwayUS 271
FromFM 16, SW
ToFM 757
CSJ0165-02-064
Proj IDSTP 2019(734)HES
Work TypeIMPROVE GUARDRAIL
 
4.380160223.715700.003.5
CountySMITH
HighwayFM 346
FromUS 69
ToFM 756
CSJ0889-04-078
Proj IDSTP 2019(734)HES
Work TypeSAFETY TREATED FIXED OBJECTS
 
3.287638842.58228264.8735.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-02-19
Work Began06-27-19
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged23
Percent Time Used23
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0165-02-064
TOTAL HIGHWAY MAINTENANCE, LLC (0.89)
ISAACS CONSTRUCTION SERVICES LLC (3.33)
SOUTHWEST ENVIRONMENT SERIVES, LLC (4.16)
MORRIS COUNTY CONTRACTORS, L.L.C. (14.77)
Contract #04193234
Totals799066.29182764.87233964.8729.2

CountySMITH
HighwayUS 69
FromAT FM 346, E OF FLINT
To.
CSJ0191-01-063
Proj IDNH 2013(216)
Work TypeGR, STRS, ACP SURF, PVMT MRKG, MBGF
 
0.94816738120.333360989.0420.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-18
Work Began10-12-18
Work Completed
Time Computed00-00-00
Contract Working Days430
Addl Days Granted0
Working Days Charged93
Percent Time Used21
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0191-01-063
TOTAL HIGHWAY MAINTENANCE, LLC (0.18)
ISAACS CONSTRUCTION SERVICES, LLC. (2.32)
WOLFE CONSTRUCTION GROUP, INC. (0.95)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.33)
TEXOP CONSTRUCTION (0.45)
MORRIS COUNTY CONTRACTORS, LLC (1.40)
STRIPING TECHNOLOGY, L.P. (2.48)
BOWMAN ENGINEERING & CONSULTING, INC. (0.06)
LS HIGHWAY PRODUCTS, INC. (2.80)
SOUTH TEXAS PAINTING COMPANY (0.04)
Contract #08183210
Totals16738120.33542675.243360989.0420.0

CountySMITH
HighwayFM 2493
FromFM 2813 IN GRESHAM, S
ToFM 346 IN FLINT
CSJ0191-03-081
Proj IDSTP 2013(215)
Work TypeGR,FLX BS,ACP,CULV EXT&RPLCMT,SIGNS
 
2.24114458790.481753296.3811.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-17-18
Work Began04-12-19
Work Completed
Time Computed00-00-00
Contract Working Days506
Addl Days Granted0
Working Days Charged61
Percent Time Used12
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0191-03-081
AREA WIDE PROTECTIVE, INC. (0.36)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.43)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (21.55)
STRIPING TECHNOLOGY, L.P. (1.95)
TEXAS ORGANIC ENTERPRISES, LTD (3.45)
DUSTROL, INC. (0.68)
MARCOM"S MOWING SERVICE, LLC (0.24)
RELIABLE CONCRETE CUTTING LLC (0.03)
Contract #07183036
Totals14458790.48809155.371753296.3811.4

CountyHENDERSON
HighwayUS 175
From0.85 MI E OF FM 315, IN POYNOR
ToANDERSON C/L
CSJ0198-02-035
Proj IDC 198-2-35
Work TypeGR,SUB BS,BS,HMAC,DRAIN STRS,SIGNS
 
0.9237052578.986247378.3688.5
CountyANDERSON
HighwayUS 175
From1.9 MI S OF FM 315 (HENDERSON C/L)
To0.5 MI NW OF SH 155 AT FRANKSTON
CSJ0198-03-027
Proj IDNH 1502(561)
Work TypeGR,SUB BS,BS,HMAC,DRAIN STRS,SIGNS
 
3.80420312971.6616999228.4083.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-17-16
Work Began05-04-16
Work Completed
Time Computed00-00-00
Contract Working Days571
Addl Days Granted68
Working Days Charged571
Percent Time Used89
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-02-035
STRIPING TECHNOLOGY, L.P. (0.36)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.16)
MARCOM"S MOWING SERVICE, LLC (0.21)
FORTSON CONTRACTING, INC. (0.04)
STRIPING SYSTEMS, INC. (0.00)
FARR FOUNDATION, INC. (0.32)
BIG CREEK CONSTRUCTION, LTD. (27.92)
NIXON ENGINEERING (0.03)
A. L. CONSTRUCTION, LLC (0.25)
KENSAR LLC DBA S & S TRUCKING (1.84)
Contract #12153202
Totals27365550.64536905.8423246606.7684.9

CountyCHEROKEE
HighwaySH 204
FromUS 79 IN JACKSONVILLE, SE
ToSH 110
CSJ0198-07-014
Proj IDSTP 1902(166)
Work TypeSP2
 
10.70413705298.280.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days206
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-07-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193205
Totals13705298.280.000.000.0

CountyCHEROKEE ETC
HighwaySH 204 ETC
FromSL 456 IN JACKSONVILLE, SE
ToSH 110
CSJ0198-07-015
Proj IDSTP 2019(882)HESG
Work TypeSAFETY
 
61.832562313.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-07-015
BRYDL CONTRACTING, INC. (6.23)
Contract #05193238
Totals562313.800.000.000.0

CountyCHEROKEE
HighwayUS 69
FromNACOGDOCHES ST (0.1 MI S OF US79),S
ToTENA(.1 MI S OF FM768)IN JACK'VILLE
CSJ0199-01-084
Proj IDNH 1902(286)
Work TypePED
 
0.916502100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days231
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0199-01-084
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193034
Totals502100.000.000.000.0

CountyCHEROKEE
HighwayUS 69
From2.0 MI N OF FM 1247,NEAR WELLS,S
To0.9 MI S OF FM 1247 (ANGELINA C/L)
CSJ0199-03-028
Proj IDHP 2013(803)
Work TypeGRDG,STRS,BASE,OCST,SURF,PVT MRKG
 
2.89617687832.8712062645.3068.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-16
Work Began01-23-17
Work Completed
Time Computed00-00-00
Contract Working Days350
Addl Days Granted54
Working Days Charged388
Percent Time Used96
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0199-03-028
AMERICAN REMEDIATION OPTIONS, INC. (2.08)
STRIPING TECHNOLOGY, L.P. (0.52)
STRIPING SYSTEMS, INC. (0.00)
TEX OP CONSTRUCTION, LP (1.05)
LUDCO, INC. (1.00)
FLEX SUPPLY, LLC (0.15)
Contract #06163005
Totals17687832.87169804.3412062645.3068.1

CountySMITH
HighwayFM 1253 ETC
FromUS 80, S
ToSH 110 S OF GARDEN VALLEY
CSJ0203-08-016
Proj IDSTP 2019(619)HES
Work TypePROFILE EDGELINE & CENTERLINE MKGS
 
67.267706776.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days84
Addl Days Granted0
Working Days Charged39
Percent Time Used46
Contractor(s)
CENTERLINE TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0203-08-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03193218
Totals706776.900.000.000.0

page 1 | page 2 | page 3 | page 4