Monthly State Let Construction Report For Tyler District As Of Jun 08, 2018 Page 3 Of 3

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySMITH
HighwayCS
FromFM 2813, N ALONG W SIDE OF FM 2493
To3 LKS PKWY, S TO CMBRLND ON E SIDE
CSJ0910-16-135
Proj IDSTP 2017(443)TAPS
Work TypeCONSTRUCT HIKE & BIKE TRAIL
 
4.0004606677.251936238.6042.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-08-17
Work Began01-02-18
Work Completed
Time Computed00-00-00
Contract Working Days225
Addl Days Granted0
Working Days Charged91
Percent Time Used40
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-135
WOLFE CONSTRUCTION GROUP, INC. (6.33)
MORRIS COUNTY CONTRACTORS, LLC (2.28)
ISAACS CONSTRUCTION SERVICES, LLC. (0.74)
FLEX SUPPLY, LLC (0.35)
PETTY"S IRRIGATION & LANDSCAPE, LTD. (5.71)
Contract #11173209
Totals4606677.25254880.891936238.6042.0

CountySMITH
HighwayVA
FromON SH110,FRM HAGAN,.7 MI S OF FM346
To0.1 MI S OF LEAMINGTON SPA IN WHTHS
CSJ0910-16-143
Proj IDSTP 2018(481)
Work TypeCONSTRUCT SIDEWALKS AND CURB RAMPS
 
0.300126560.00129330.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began03-26-18
Work Completed
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged18
Percent Time Used37
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-143
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (3.20)
Contract #12173028
Totals126560.004500.00129330.0099.9

CountySMITH
HighwayFM 850
FromAT MUD CREEK, STR# 116301003
To0.5 MI W OF FM 2607
CSJ1163-01-022
Proj IDBR 1702(756)
Work TypeRPLC BR&APPR,ACP BS&SURF,MBGF,PV MK
 
0.1261077661.381079215.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-17
Work Began10-30-17
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged109
Percent Time Used109
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1163-01-022
PANOLA SIGN & BARRICADE, INC. (1.26)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.81)
DUSTIN ALLEN, INC. (2.26)
STRIPING TECHNOLOGY, L.P. (1.17)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.89)
BOWMAN ENGINEERING & CONSULTING, INC (0.28)
TEXOP CONSTRUCTION (0.72)
ISAACS CONSTRUCTION SERVICES, LLC. (0.49)
PEACHTREE CONSTRUCTION, LTD. (15.77)
PENHALL COMPANY (0.30)
Contract #08173240
Totals1077661.388291.601079215.6099.9

CountyVAN ZANDT
HighwayFM 1256
FromFM 316, E
ToSH 19
CSJ1172-01-007
Proj IDSSW 1172-1-7
Work TypeGR, FLEX BS, TCST, STRS, PV MK
 
7.9545779955.804190615.6372.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-02-16
Work Began07-08-16
Work Completed
Time Computed00-00-00
Contract Working Days206
Addl Days Granted0
Working Days Charged172
Percent Time Used83
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1172-01-007
ODUM SERVICES, L.P. (0.69)
STRIPING TECHNOLOGY, L.P. (1.35)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.68)
MORRIS COUNTY CONTRACTORS, LLC (0.40)
PANOLA SIGN & BARRICADE, INC. (0.50)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.73)
STRIPING SYSTEMS, INC. (0.02)
MAC TRANSPORTATION, LTD, L.L.P. (0.87)
KENSAR LLC DBA S & S TRUCKING (1.49)
ACE CONTRACTORS, INC. (0.06)
Contract #04163210
Totals5779955.80276144.624190615.6372.5

CountyGREGG
HighwaySH 300
FromFM 2275 (GEO RICHEY RD), S
ToUS 80 IN LONGVIEW
CSJ1385-02-024
Proj IDNH 2018(517)
Work TypeBS RPR, OCST, PFC, HMAC, PVT MRKG
 
8.9496613692.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days285
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 1385-02-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183010
Totals6613692.240.000.000.0

CountyVAN ZANDT
HighwayFM 1652
FromFM 17 S OF GRAND SALINE, S
ToFM 1255 NW OF OAKLAND
CSJ1672-01-004
Proj IDSSW 1672-1-4
Work TypeGR, FLX BS, TCST, STRS, PVT MRKG
 
6.0104481848.931450808.5232.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-17
Work Began09-27-17
Work Completed
Time Computed00-00-00
Contract Working Days346
Addl Days Granted0
Working Days Charged103
Percent Time Used29
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1672-01-004
AREA WIDE PROTECTIVE, INC. (0.59)
DIIBS SPECIALISTS (1.16)
ISAACS CONSTRUCTION SERVICES, LLC. (1.48)
WOLFE CONSTRUCTION GROUP, INC. (0.08)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.91)
ACTION COMMERCIAL SERVICES, L.L.C. (1.28)
DUSTROL, INC. (0.22)
TEXANA LAND & ASPHALT, INC. (7.47)
Contract #07173017
Totals4481848.93475004.431450808.5232.3

CountyVAN ZANDT
HighwayFM 1653
FromSH 64 NEAR BEN WHEELER, SW
ToFM 858 AT MARTINS MILL
CSJ1673-01-008
Proj IDSSW 1673-1-8
Work TypeGR, FLX BS, TCST, STRS, PVT MRKG
 
5.6603972777.001063177.4826.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-17
Work Began10-25-17
Work Completed
Time Computed00-00-00
Contract Working Days344
Addl Days Granted0
Working Days Charged146
Percent Time Used42
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1673-01-008
PANOLA SIGN & BARRICADE, INC. (0.56)
STRIPING TECHNOLOGY, L.P. (2.64)
JB PINNACLE GROUP, LLC (10.73)
FREDONIA CONSTRUCTION SERVICES (0.46)
MORRIS COUNTY CONTRACTORS, LLC (1.11)
ISAACS CONSTRUCTION SERVICES, LLC. (1.41)
TEXAS ALTERNATIVE GRASSER, INC. (0.87)
Contract #07173242
Totals3972777.0089059.721063177.4826.7

CountyVAN ZANDT
HighwayFM 1861
FromSH 19, E
ToFM 2339
CSJ1673-02-017
Proj IDSTP 2017(929)
Work TypeSTRS,PLNG,HMAC,OCST,ACP,MBGF,BS RPR
 
3.3202436392.261115042.0145.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-17
Work Began06-12-17
Work Completed
Time Computed00-00-00
Contract Working Days136
Addl Days Granted0
Working Days Charged125
Percent Time Used91
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1673-02-017
AREA WIDE PROTECTIVE, INC. (0.86)
J & M CONTRACTING, COMPANY (9.92)
CHEROKEE SERVICES (0.43)
FORTSON CONTRACTING, INC. (3.25)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.73)
STRIPING TECHNOLOGY, L.P. (1.75)
KENSAR LLC DBA S & S TRUCKING (4.80)
NIXON ENGINEERING, L.L.C. (0.14)
HOUSTON TRUCKING & PAVING CO. (0.53)
Contract #04173028
Totals2436392.26305052.111115042.0145.7

CountySMITH
HighwaySS 248
From1.75 MI W OF FM 848(OLD OMEN RD), E
ToSH 64 SE OF TYLER
CSJ2558-01-015
Proj IDSTP 2013(211)
Work TypeRECONSTR GR,STRS,BS,C&G, SURF & PAV
 
2.1778660946.196925463.8780.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-09-16
Work Began06-06-16
Work Completed
Time Computed00-00-00
Contract Working Days315
Addl Days Granted4
Working Days Charged339
Percent Time Used106
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2558-01-015
FLEX SUPPLY, LLC (0.24)
SCOTT DERR PAINTING CO, LLC (0.06)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.89)
ROBINSON CONSTRUCTION (4.06)
APAC-TEXAS, INC. (15.95)
SLATON BROTHERS, INC. (6.48)
TEXOP CONSTRUCTION (0.25)
STRIPING TECHNOLOGY, L.P. (0.78)
JE CASEY, LLC (1.28)
SOUTH TEXAS ILLUMINATION, LLC (1.78)
KENSAR LLC DBA S & S TRUCKING (5.28)
STRIPING SYSTEMS, INC. (0.01)
ISAACS CONSTRUCTION SERVICES, LLC. (1.01)
JOHNSON CONSTRUCTION, J.C. (2.68)
PBJ CONSTRUCTION (0.15)
Contract #12153229
Totals8660946.19432179.496925463.8780.2

CountySMITH
HighwaySS 248
From1.1 MI E OF SL323/LAKE,IN TYLER, E
To1.7 MI W OF FM848/OLD OMEN RD
CSJ2558-01-017
Proj IDSTP 2018(429)
Work TypeTREES,SHRUBS,DRIP IRRGTN,SOIL PREP
 
0.27069000.0028485.0041.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-14-18
Work Began05-22-18
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged7
Percent Time Used20
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2558-01-017
PANOLA SIGN & BARRICADE, INC. (5.54)
Contract #01183005
Totals69000.0028485.0028485.0041.2

CountyGREGG
HighwaySL 281
FromUS 80 IN LONGVIEW, N
ToSHOFNER DR (0.35 MI N OF FM 1845)
CSJ2642-01-046
Proj IDNH 1602(441)
Work TypeGR, STRS, ACP BASE & SURF, PVT MRKG
 
0.5394546219.504306297.6394.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-06-16
Work Began01-23-17
Work Completed
Time Computed00-00-00
Contract Working Days234
Addl Days Granted59
Working Days Charged261
Percent Time Used89
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2642-01-046
ACU CONSTRUCTION LLC (1.51)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. (1.20)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (11.83)
ISAACS CONSTRUCTION SERVICES, LLC. (0.10)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.58)
STRIPE-A-ZONE, INC. (0.87)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.17)
TOTAL HIGHWAY MAINTENANCE, LLC (0.69)
VELASCO"S TRANSPORTS (2.47)
KLP COMMERCIAL, LLC (2.33)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (0.32)
S & W FOUNDATION CONTRACTORS, INC. (0.10)
Contract #10163226
Totals4546219.50477488.804306297.6394.7