Monthly State Let Maintenance Report For Tyler District As Of Dec 07, 2021 Page 2 Of 3

Last Update: Wednesday, December 08, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyRUSK
HighwaySH0042
FromVARIOUS ROADWAYS
ToIN RUSK COUNTY
CSJ6349-71-001
Proj IDRMC - 634971001
Work TypeTREE REMOVAL
 
0.010489250.00374984.0076.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-11-21
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged533
Percent Time Used73
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6349-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02204008
Totals489250.0034713.00374984.0076.6

CountyRUSK
HighwayUS0259
FromVARIOUS ROADWAYS
ToIN RUSK COUNTY
CSJ6352-70-001
Proj IDRMC - 635270001
Work TypeROW MOWING
 
0.010348212.38696994.8699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-20
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted55
Working Days Charged87
Percent Time Used66
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6352-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204023
Totals348212.380.00696994.8699.9

CountyGREGG
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToGREGG COUNTY
CSJ6359-27-001
Proj IDRMC - 635927001
Work TypeTREE REMOVAL
 
0.010338303.00146635.0043.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged418
Percent Time Used57
Contractor(s)
ROAD SOLUTIONS L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6359-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204022
Totals338303.000.00146635.0043.3

CountyHENDERSON
HighwaySH0031
FromVARIOUS LOCATIONS IS
ToHENDERSON & ANDERSON COUNTIES
CSJ6359-35-001
Proj IDRMC - 635935001
Work TypeTRAFFIC CONTROL
 
0.010880357.94682940.7077.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-20
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged455
Percent Time Used62
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6359-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05204223
Totals880357.9438297.32682940.7077.5

CountyWOOD
HighwayUS0080
FromVARIOUS LOCATIONS
ToVARIOUS LOCAITONS
CSJ6359-36-001
Proj IDRMC - 635936001
Work TypeTRAFFIC CONTROL
 
0.0101480960.001083923.0073.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged436
Percent Time Used59
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6359-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05204024
Totals1480960.0069996.001083923.0073.1

CountySMITH
HighwayUS0069
FromVARIOUS LOCATIONS IN
ToSMITH & CHEROKEE COUNTIES
CSJ6359-37-001
Proj IDRMC - 635937001
Work TypeTRAFFIC CONTROL
 
0.010832200.00832053.0699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged455
Percent Time Used62
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6359-37-001
L & M MOWING CONTRACTORS, LLC (99.87)
Contract #05204023
Totals832200.0041677.00832053.0699.9

CountyGREGG
HighwaySH0031
FromVARIOUS LOCATIONS IN
ToGREGG & RUSK COUNTIES
CSJ6359-38-001
Proj IDRMC - 635938001
Work TypeTRAFFIC CONTROL
 
0.0101028550.43694425.8667.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged428
Percent Time Used58
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6359-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05204222
Totals1028550.4346526.18694425.8667.5

CountySMITH
HighwayIH0020
FromIH-20 IN GREGG, SMITH
ToAND VAN ZANDT COUNTIES
CSJ6367-43-001
Proj IDRMC - 636743001
Work TypeTOTAL MAINTENANCE
 
0.0104603063.503869530.6984.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-28-21
Work Completed
Time Computed00-00-00
Contract Working Days469
Addl Days Granted0
Working Days Charged186
Percent Time Used39
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6367-43-001
CATACON, INC. (7.24)
STRIPING TECHNOLOGY, L.P. (9.91)
L & M MOWING CONTRACTORS, LLC (0.52)
CHEROKEE SERVICES (0.47)
TEXANA LAND & ASPHALT, INC. (33.81)
DUSTROL, INC. (5.58)
HX FARMS, INC. (4.87)
Contract #03214019
Totals4603063.50321650.683869530.6984.0

CountyHENDERSON
HighwayUS0175
FromVARIOUS ROADWAYS IN
ToHENDERSON COUNTY
CSJ6372-91-001
Proj IDRMC - 637291001
Work TypeROW MOWING
 
0.010700709.08349829.5449.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-21
Work Completed
Time Computed00-00-00
Contract Working Days114
Addl Days Granted0
Working Days Charged53
Percent Time Used46
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6372-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204021
Totals700709.080.00349829.5449.9

CountyVAN ZANDT
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToVAN ZANDT COUNTY
CSJ6372-92-001
Proj IDRMC - 637292001
Work TypeROW MOWING
 
0.010517662.52262605.9950.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days98
Addl Days Granted0
Working Days Charged45
Percent Time Used45
Contractor(s)
SERNA CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6372-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204022
Totals517662.5269670.22262605.9950.7

CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN
ToWOOD COUNTY
CSJ6372-93-001
Proj IDRMC - 637293001
Work TypeROW MOWING
 
0.010534762.34233955.2945.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days106
Addl Days Granted0
Working Days Charged66
Percent Time Used62
Contractor(s)
ABESCAPE LANDSCAPING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6372-93-001
S G COMPANY, LLC (5.21)
Contract #12204222
Totals534762.3498735.49233955.2945.2

CountySMITH
HighwayUS0271
FromVARIOUS ROADWAYS IN
ToSMITH COUNTY
CSJ6372-94-001
Proj IDRMC - 637294001
Work TypeROW MOWING
 
0.010527979.45262791.9350.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-07-21
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged50
Percent Time Used49
Contractor(s)
HX FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6372-94-001
SERVIN MOWING (49.99)
SERNA CONTRACTORS, LLC (3.96)
Contract #12204223
Totals527979.450.00262791.9350.0

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN HENDERSON CO.
ToATHENS MAINTENANCE SECTION
CSJ6382-94-001
Proj IDRMC - 638294001
Work TypeTREE REMOVAL
 
0.010485500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PATTERSON'S COMPLETE TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6382-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08214015
Totals485500.000.000.000.0

CountyHENDERSON
HighwaySH0334
FromVARIOUS ROADWAYS
ToTYLER DISTRICT
CSJ6383-27-001
Proj IDBPM - 638327001
Work TypeBRIDGE JOINT CLEANING AND SEALING
 
0.010199924.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAD ENERGY SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6383-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214225
Totals199924.000.000.000.0

CountySMITH
HighwayUS0069
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6383-74-001
Proj IDRMC - 638374001
Work TypeCRACK SEAL
 
0.010452694.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days41
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CRACKSEAL OF TEXAS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6383-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08214214
Totals452694.000.000.000.0

CountyHENDERSON
HighwayUS0175
FromVARIOUS LOCATIONS WITHIN
ToTHE TYLER DISTRICT
CSJ6383-90-001
Proj IDMMC - 638390001
Work TypeAGGREGATE
 
0.0101078025.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6383-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11214225
Totals1078025.000.000.000.0

CountyGREGG
HighwayUS0271
FromVARIOUS LOCATIONS IN GREGG
To, RUSK, SMITH, AND CHEROKEE COUNTIES
CSJ6386-04-001
Proj IDBPM - 638604001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010432432.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days151
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RED BARON BUILDING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6386-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214024
Totals432432.200.000.000.0

CountyHENDERSON
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToHENDERSON AND ANDERSON COUNTIES
CSJ6386-89-001
Proj IDRMC - 638689001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.0101825545.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6386-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09214028
Totals1825545.000.000.000.0

CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN
ToWOOD AND VAN ZANDT COUNTIES
CSJ6386-90-001
Proj IDRMC - 638690001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.0101820645.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6386-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09214029
Totals1820645.000.000.000.0

CountyGREGG
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToGREGG AND RUSK COUNTIES
CSJ6386-91-001
Proj IDRMC - 638691001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.0101754859.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6386-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09214223
Totals1754859.000.000.000.0