Monthly State Let Maintenance Report For Tyler District As Of Nov 13, 2018 Page 2 Of 2

Last Update: Tuesday, November 13, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToHENDERSON AND ANDERSON COUNTIES
CSJ6329-51-001
Proj IDRMC - 632951001
Work TypeTRAFFIC CONTROL
 
0.001940200.5082245.808.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-18
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged60
Percent Time Used8
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6329-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184008
Totals940200.5040518.5482245.808.7

CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN
ToWOOD AND VAN ZANDT COUNTIES
CSJ6329-52-001
Proj IDRMC - 632952001
Work TypeTRAFFIC CONTROL
 
0.0011263543.72110735.598.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-18
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged60
Percent Time Used8
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6329-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184009
Totals1263543.7250294.21110735.598.7

CountySMITH
HighwayUS0069
FromVARIOUS ROADWAYS IN
ToSMITH AND CHEROKEE COUNTIES
CSJ6329-53-001
Proj IDRMC - 632953001
Work TypeTRAFFIC CONTROL
 
0.0011019948.0495753.589.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-18
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged60
Percent Time Used8
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184206
Totals1019948.0451884.6595753.589.3

CountyGREGG
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToGREGG AND RUSK COUNTIES
CSJ6329-54-001
Proj IDRMC - 632954001
Work TypeTRAFFIC CONTROL
 
0.001942173.0688040.129.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-18
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged60
Percent Time Used8
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184207
Totals942173.0652370.5788040.129.3

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6329-55-001
Proj IDRMC - 632955001
Work TypeCRACK SEAL HOT POUR
 
651.190492381.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days62
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6329-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09184220
Totals492381.900.000.000.0

CountyHENDERSON
HighwaySH0031
FromVARIOUS LOCATIONS IN
ToTHE TYLER DISTRICT
CSJ6329-58-001
Proj IDRMC - 632958001
Work TypePAINT
 
0.010353375.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6329-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11184210
Totals353375.000.000.000.0

CountyGREGG
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToGREGG AND RUSK COUNTIES
CSJ6330-91-001
Proj IDRMC - 633091001
Work TypeGUARDRAIL REPAIR
 
0.010418248.0045857.0010.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-05-18
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged57
Percent Time Used7
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184001
Totals418248.0019414.0045857.0010.9

CountySMITH
HighwayUS0069
FromVARIOUS ROADWAYS IN
ToSMITH AND CHEROKEE COUNTIES
CSJ6330-93-001
Proj IDRMC - 633093001
Work TypeGUARDRAIL REPAIR
 
0.010400142.0012511.003.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-14-18
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged42
Percent Time Used5
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184202
Totals400142.0012511.0012511.003.1

page 1 | page 2