Monthly State Let Construction Report For Waco District As Of Jan 16, 2020 Page 1 Of 4

Last Update: Friday, January 17, 2020
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHILL
HighwaySH 81
FromHCR 2452
ToIH 35
CSJ0014-07-103
Proj IDSTP 1902(129)HES
Work TypeSFT
 
1.705482159.20230481.1047.8
Work Order09-18-19
Work Began11-20-19
Work Completed
Time Computed10-18-19
Contract Working Days30
Addl Days Granted0
Working Days Charged16
Percent Time Used53
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0014-07-103
T&L CLEANING SERVICES LLC (11.57)
Contract #08193242
Totals482159.20226481.10230481.1047.8

CountyHILL ETC
HighwayIH 35
FromIH 35 @SH 81
ToMCLENNAN CO LINE
CSJ0014-07-104
Proj IDSTP 2020(526)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
92.5081195738.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-15-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SURFACE PREPARATION TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0014-07-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12193038
Totals1195738.300.000.000.0

CountyMCLENNAN
HighwayIH 35
FromN LP 340
ToCRAVEN AVE
CSJ0015-01-226
Proj IDNH 2019(312)
Work TypeCNSTR FLUSH MEDIAN/DRNG&CONCTRAFBAR
 
1.24610654777.903978267.3937.3
CountyMCLENNAN
HighwayIH 35
FromS LP 340
ToN LP 340
CSJ0015-01-234
Proj IDNH 1402(012)
Work TypeACQ, RELOC, ASSIST, & ADJ, OF UTIL.
 
7.9296056337.004748816.8478.4
CountyMCLENNAN
HighwayIH 35
From12TH STREET
ToN LP 340
CSJ0015-01-243
Proj IDNH 2019(312)
Work TypeWDN, GR, STRS, & SURF
 
4.580305112618.3593622247.4030.6
CountyMCLENNAN
HighwayIH 35
From12TH STREET
ToBU 77
CSJ0015-01-244
Proj IDNH 2019(312)
Work TypeREPL BR
 
2.54619391266.751675000.008.6
Work Order01-31-19
Work Began04-29-19
Work Completed
Time Computed04-01-19
Contract Working Days1,150
Addl Days Granted0
Working Days Charged188
Percent Time Used16
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0015-01-226
PMI PAVEMENT MARKING, LLC (0.28)
ALTUS TRAFFIC MANAGEMENT LLC (0.08)
STRAIGHT LINE SAWING & SEALING, INC. (0.17)
ANTIGO CONSTRUCTION, INC. (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.72)
BOWMAN ENGINEERING & CONSULTING, INC. (1.03)
A BROTHERS MILLING, LLC (0.17)
ADCOCK 4 INVESTMENTS, LLC (1.71)
RENAISSANCE CONTRACTORS, INC. (8.18)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
ADRIAN CONTRACTING (0.02)
CND CONTRACTING (0.86)
DBI SERVICES, LLC (0.40)
C-HOP CONSTRUCTION (0.49)
KNIFE RIVER CORPORATION - SOUTH (5.97)
COWBOY AND SONS LP DBA COWBOY TRUCKING (0.31)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.98)
ROADWAY SPECIALTIES, INC. (0.15)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (3.75)
B-CORP UTILITIES INC (1.61)
AREA WIDE PROTECTIVE, INC. (0.13)
SOUTH TEXAS PAINTING COMPANY (0.07)
GILLIAM CONTRACTING, INC. (1.41)
K.B.L. CONSTRUCTION, LLC (0.36)
BEAIRD DRILLING (1.12)
GK CONSTRUCTION, LLC (0.05)
ANCORTEX, INC. (0.90)
FLASHER EQUIPMENT COMPANY (0.12)
TX DOWN UNDER CONSTRUCTION LLC (0.02)
TOTAL HIGHWAY MAINTENANCE, LLC (0.38)
STEEL EFFECTS (0.08)
RAY"S THREADING AND FAB SHOP (0.31)
INDUS ROAD & BRIDGE, INC (1.52)
URBAN INFRACONSTRUCTION, LLC. (1.37)
BLACK ROCK CONSTRUCTION (0.08)
HB FARMER FOUNDATION, LLC (0.77)
U.S. UNDERWATER SERVICES, LP (0.03)
Contract #12183001
Totals341215000.008882936.96104024331.6330.4

CountyMCLENNAN ETC
HighwayIH 35
FromFALLS COUNTY LINE
ToWOODLAWN RD
CSJ0015-02-048
Proj IDIM 0354(235)
Work TypeWDN, GR, STR, & SURF
 
18.183120722098.70138689284.2999.9
Work Order12-27-11
Work Began06-25-12
Work Completed
Time Computed06-24-12
Contract Working Days1,210
Addl Days Granted787
Working Days Charged1,997
Percent Time Used100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0015-02-048
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.54)
APAC-TEXAS, INC. (9.61)
BCG INVESTMENTS (0.24)
BEAIRD DRILLING (0.71)
BOSQUEZ ELECTRICAL, LLC. (1.03)
DANRIDGE CONSTRUCTION, LLC. (0.19)
DUSTROL, INC. (0.64)
FORTSON CONTRACTING, INC. (0.22)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.28)
HIGHWAY TECHNOLOGIES, INC. (1.17)
ISBELL CONSTRUCTION (0.30)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.48)
SOUTH TEXAS PAINTING COMPANY (0.11)
SPEEDY PAVING (0.21)
STEEL EFFECTS (0.15)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.55)
WOLFF CONSTRUCTION (3.46)
DRILL TECH DRILLING & SHORING, INC. (0.68)
TTG UTILITIES, INC. (1.57)
BECO CONSTRUCTION, L.L.C. (7.90)
CTBX, INC. (0.02)
GK CONSTRUCTION, LLC (0.04)
STAMPEDE CREEK TRANSPORTATION (0.03)
DIAMOND K MATERIALS (0.03)
DOUBLE R TRUCKING (0.00)
J & B (0.00)
KYKO HAULING (0.00)
R K STEPHENS CONSTRUCTION, LLC (0.17)
CHUCK WHITE TRUCKING (0.03)
BAR B CONTRACTING, INC. (0.01)
JM DAVIS TRUCKING (0.00)
DIVINE TRINITY, INC. (0.00)
HDB TRUCKING (0.03)
MSW TRUCKING, INC. (0.03)
N. ROCK SOLUTIONS (0.03)
ALAN JOHNSON TRUCKING (0.01)
PRECISION CONTRACTORS (0.00)
STP HAULERS, INC. (0.00)
TEXAS BAR J TRUCKING, LLC (0.00)
4D TRUCKN", LLC (0.00)
BACKOR TRUCKING (0.00)
PANTHER CREEK TRANSPORTATION, INC. (0.00)
INDUS CONSTRUCTION, L.P. (0.58)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00)
STAR OPERATIONS, INC. (1.07)
M&T TRUCKING, LLC (0.00)
KEITH SHEETS TRUCKING (0.00)
BRUSH SOLUTIONS, LLC (0.00)
HTM CONSTRUCTION COMPANY (0.06)
BPI ENVIRONMENTAL SERVICES INC. (0.00)
MAUNEY FARMS TRUCKING (0.00)
J.C. COMMUNICATION (0.01)
JACK FARMER TRUCKING (0.00)
S & S BRIDGE PAINTING, INC. (0.06)
AMM TRUCKING (0.00)
RANDIG_FARMS (0.00)
GK CONSTRUCTION, LLC (0.41)
A-CORE, INC. (0.00)
DIAMOND K MATERIALS (0.06)
SERVICELINE TRANSPORT (0.06)
WADE WHITE TRUCKING (0.00)
POTTER TRUCKING (0.06)
L T VAUGHAN, LLC (0.00)
HEAL TRUCKING (0.00)
JDK SERVICES, LLC (0.00)
HAROS BROS. CO. (0.04)
TRIPLE J-SA CONSTRUCTION (0.01)
A & R DEMOLITION (0.31)
FARR FOUNDATION, INC. (0.09)
THE LEVY COMPANY, L.P. (0.00)
CALAME CONTRACTING, LLC (0.01)
NORTHEAST SERVICE, INC. (0.02)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.02)
ROADWAY SPECIALTIES, INC. (0.11)
WEBBER BARRIER SERVICES, LLC. (0.48)
Contract #10113001
Totals120722098.700.00138689284.2999.9

CountyBELL
HighwayIH 35
FromNORTH LP 363
ToN OF TROY
CSJ0015-04-067
Proj IDC 15-4-67
Work TypeWDN, GR, STRS & SURF
 
5.469120853801.57132651679.5499.9
CountyBELL
HighwayIH 35
FromNORTH LP 363
ToN OF TROY
CSJ0015-04-083
Proj IDRW 15-4-83
Work TypeACQUISITION, RELOCATION & UTILITIES
 
5.5692774870.753114394.5499.9
Work Order07-22-11
Work Began03-12-12
Work Completed
Time Computed01-18-12
Contract Working Days1,166
Addl Days Granted856
Working Days Charged2,022
Percent Time Used100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0015-04-067
BEAIRD DRILLING (0.52)
BELL CONTRACTORS (1.66)
BIG CREEK CONSTRUCTION, LTD. (8.35)
GK CONSTRUCTION, LLC (0.57)
HJC FARMS, INC. (0.26)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25)
JAVELINA CONSTRUCTION SOUTH, INC. (0.41)
KELLYSTONE, INC (0.22)
SOUTH TEXAS PAINTING COMPANY (0.24)
HIGHWAY TECHNOLOGIES, INC. (1.34)
ISBELL CONSTRUCTION (0.58)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35)
SCOTT DERR PAINTING CO (0.03)
WOLFF CONSTRUCTION (2.95)
STAR OPERATIONS, INC. (1.48)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.09)
STAMPEDE CREEK TRANSPORTATION (0.19)
J & G CONCRETE PRODUCTS (1.46)
3 P TRUCKING (0.19)
4D TRUCKN", LLC (0.19)
BELL CONTRACTORS (0.19)
CHUCK WHITE TRUCKING (0.19)
DIAMOND K MATERIALS (0.19)
HDB TRUCKING (0.19)
JM DAVIS TRUCKING (0.19)
MSW TRUCKING, INC. (0.19)
R & A HAULING (0.19)
STP HAULERS, INC. (0.19)
VICTOR THOMAS (0.19)
ALVIN SOWDERS (0.19)
BRAZOS BOTTOM TRUCKING, LLC (0.19)
DOUBLE R TRUCKING (0.19)
L2 HAULERS, LLC (0.19)
MATERIALS-R-US (0.19)
RACHEL"S TRUCKING, LLC (0.19)
TOMMY T"S DUMP TRUCKING, INC. (0.19)
INDUS CONSTRUCTION, L.P. (0.62)
BRYANT & FREY CONSTRUCTION (0.19)
SHOWS UTILITIES, INC. (0.29)
DAKOTA UTILITY CONTRACTORS, INC. (0.16)
NY-MAC ENTERPRISES, INC. (0.06)
DIVINE TRINITY, INC. (0.19)
PRECISION CONTRACTORS (0.03)
TEXAS BAR J TRUCKING, LLC (0.03)
SMITH & SMITH (0.03)
J & B CONSTRUCTION COMPANY (0.03)
PERFORMANCE EQUIPMENT (0.41)
JOY LATTIMER, LLC. (0.03)
BAR B CONTRACTING, INC. (0.01)
ALAN JOHNSON TRUCKING (0.03)
VAUGHAN HAULING (0.00)
BACKOR TRUCKING (0.00)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00)
BMP SPECIALIST, LLC (0.00)
PANTHER CREEK TRANSPORTATION, INC. (0.01)
KEITH SHEETS TRUCKING (0.00)
J & B (0.00)
M&T TRUCKING, LLC (0.00)
TEXAS CUTTING & CORING, INC. (0.00)
BPI ENVIRONMENTAL SERVICES INC. (0.00)
HTM CONSTRUCTION COMPANY (0.20)
DUSTROL, INC. (0.00)
S & S BRIDGE PAINTING, INC. (0.24)
A-CORE, INC. (0.00)
DIAMOND K MATERIALS (0.26)
SERVICELINE TRANSPORT (0.06)
POTTER TRUCKING (0.06)
GK CONSTRUCTION, LLC (0.00)
TRIPLE J-SA CONSTRUCTION (0.07)
THE LEVY COMPANY, L.P. (0.12)
FARR FOUNDATION, INC. (0.04)
HAROS BROS. CO. (0.00)
MILLER SPRINGS MATERIALS (1.19)
CALAME CONTRACTING, LLC (0.01)
NORTHEAST SERVICE, INC. (0.02)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.07)
SPEEDY PAVING (0.23)
DUSTROL, INC. (0.00)
LINDAMOOD DEMOLITION, INC. (0.00)
OLDCASTLE MATERIALS TEXAS, INC. (0.00)
ROADWAY SPECIALTIES, INC. (0.18)
WEBBER BARRIER SERVICES, LLC. (0.15)
Contract #06113201
Totals123628672.322220.22135766074.0899.9

CountyBELL
HighwaySH 317
FromFM 93
To0.25 MI S OF FM 93
CSJ0015-05-050
Proj IDSTP 2019(837)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.067521881.0059899.9611.4
Work Order06-07-19
Work Began00-00-00
Work Completed
Time Computed07-07-19
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0015-05-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193037
Totals521881.000.0059899.9611.4

CountyBELL
HighwayIH 35
FromS LP 363 IN TEMPLE
ToNUGENT AVE
CSJ0015-14-091
Proj IDNH 2012(691)
Work TypeWDN GR, STRS & SURF
 
12.836241296935.09303612552.8099.9
Work Order11-15-12
Work Began09-11-13
Work Completed
Time Computed05-14-13
Contract Working Days1,200
Addl Days Granted460
Working Days Charged1,660
Percent Time Used100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0015-14-091
APAC-TEXAS, INC. (8.44)
BEAIRD DRILLING (1.04)
FORTSON CONTRACTING, INC. (0.41)
BREDA COMPANY, INC. (0.67)
BRYANT & FREY CONSTRUCTION (0.66)
DUSTROL, INC. (0.33)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.16)
SCOTT DERR PAINTING CO (0.28)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.64)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.31)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55)
STAR OPERATIONS, INC. (1.86)
SOUTH TEXAS PAINTING COMPANY (0.05)
CHOCTAW ERECTORS, INC. (0.12)
SPEEDY PAVING (0.11)
HOUSTON SAWING & DRILLING (0.03)
R K STEPHENS CONSTRUCTION, LLC (0.21)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.15)
HAROS BROS. CO. (0.64)
TTG UTILITIES, INC. (2.75)
GK CONSTRUCTION, LLC (0.48)
PANTHER CREEK TRANSPORTATION, INC. (0.07)
WOLFF CONSTRUCTION (0.16)
SCHNABEL FOUNDATION COMPANY (0.78)
HAROS PARTNERS, LP (0.62)
SCHNABEL FOUNDATION COMPANY (1.97)
GK CONSTRUCTION, LLC (0.06)
SHOWS UTILITIES, INC. (0.02)
RAMM"S PUMP & WATER WELL SERVICE, LLC (0.00)
HANSON PRESSURE PIPE, INC. (0.00)
SWEEP ACROSS TEXAS (0.00)
WEBBER BARRIER SERVICES, LLC. (0.74)
BELL CONTRACTORS (0.01)
1 PRIORITY ENVIRONMENTAL SERVICES, INC. (0.63)
TEXAS CUTTING & CORING, INC. (0.00)
A-CORE CONCRETE CUTTING, INC. (0.02)
LUNDIN ROOFING COMPANY, LLC (0.13)
THE LEVY COMPANY, L.P. (0.00)
CALAME CONTRACTING, LLC (0.00)
J.H. PAINTING COMPANY (0.14)
DAKOTA UTILITY CONTRACTORS, INC. (0.00)
WACO DRILLING CO., INC. (0.00)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.00)
Contract #09123001
Totals241296935.09400487.06303612552.8099.9

CountyBELL
HighwayIH 35
FromUS 190
ToLOOP 363
CSJ0015-14-126
Proj IDC 15-14-126
Work TypeMILL/PFC OVERLAY
 
4.9146939665.086365982.2991.7
Work Order02-25-19
Work Began05-20-19
Work Completed
Time Computed03-27-19
Contract Working Days60
Addl Days Granted36
Working Days Charged96
Percent Time Used100
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0015-14-126
AREA WIDE PROTECTIVE, INC. (0.40)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (11.24)
CPAVE, INC. (3.06)
ENVIRONMENTAL SAFETY SERVICES, INC. (13.24)
TEX OP CONSTRUCTION, LP (4.99)
TOTAL HIGHWAY MAINTENANCE, LLC (3.27)
PENHALL COMPANY (0.09)
Contract #01193005
Totals6939665.081816.006365982.2991.7

CountyHILL
HighwayIH 35E
FromIH 35W
ToELLIS CO LINE
CSJ0048-09-029
Proj IDNH 2019(834)
Work TypeWIDEN FREEWAY
 
7.887117517085.987411490.116.3
Work Order06-18-19
Work Began09-09-19
Work Completed
Time Computed07-18-19
Contract Working Days1,090
Addl Days Granted0
Working Days Charged87
Percent Time Used7
Contractor(s)
SACYR CONSTRUCTION USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 0048-09-029
ROADWAY SPECIALTIES, INC. (0.60)
PROTEX EROSION CONTROL, LLC (1.21)
ALTUS TRAFFIC MANAGEMENT LLC (0.22)
TEXAS SCORPION HAULERS LLC, DBA TEXAS PRIDE HAULERS (2.26)
KLP COMMERCIAL, L.L.C. (2.12)
STRAIGHT LINE SAWING & SEALING, INC. (0.00)
BIG CREEK CONSTRUCTION, LTD. (8.88)
Q. ROBERTS TRUCKING INCORPORATED (4.98)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (1.53)
ALAVA INTERNATIONAL, INC. (1.04)
A.Z. REBAR CONSTRUCTION, INC. (0.77)
PMI PAVEMENT MARKING, LLC (0.51)
FARR FOUNDATION, INC. (1.22)
DUSTROL, INC. (0.65)
DBI SERVICES, LLC (0.00)
BROOKLYN SWEEPS, INCORPORATED (0.53)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.92)
BEAIRD DRILLING (0.48)
Contract #05193001
Totals117517085.98552716.567411490.116.3

CountyMCLENNAN ETC
HighwaySH 6 ETC
From@ FM 1860
To.
CSJ0049-01-094
Proj IDSTP 1802(508)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.8841026074.001102887.4299.9
Work Order09-18-18
Work Began01-21-19
Work Completed
Time Computed10-18-18
Contract Working Days90
Addl Days Granted0
Working Days Charged85
Percent Time Used94
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-01-094
D. I. J. CONSTRUCTION, INC. (0.59)
Contract #08183255
Totals1026074.004020.751102887.4299.9

CountyCORYELL ETC
HighwayUS 84 ETC
FromAT FM 2412
To.
CSJ0055-04-031
Proj IDSTP 2019(999)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.230139750.000.000.0
Work Order09-25-19
Work Began00-00-00
Work Completed
Time Computed10-25-19
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0055-04-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193047
Totals139750.000.000.000.0

CountyMCLENNAN
HighwayUS 84
FromHARRIS CREEK RD
ToSOUTH BOSQUE RIVER
CSJ0055-08-099
Proj IDNH 2018(346)
Work TypeGR, STRS & SURF
 
1.91320587594.9617870041.9386.8
Work Order03-12-18
Work Began04-16-18
Work Completed
Time Computed04-11-18
Contract Working Days595
Addl Days Granted4
Working Days Charged439
Percent Time Used73
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0055-08-099
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.04)
BOWMAN ENGINEERING & CONSULTING, INC (0.53)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.07)
SAN-ANN-CO., INC. (0.43)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.70)
PRIMATE CONSTRUCTION, INC. (0.09)
ROADWAY SPECIALTIES, INC. (1.18)
S & S BRIDGE PAINTING, INC. (0.03)
STRIPING TECHNOLOGY, L.P. (0.79)
WOLFE CONSTRUCTION GROUP, INC. (0.18)
PIPE WHOLESALERS OF TEXAS, INC. (7.06)
BOWMAN ENGINEERING & CONSULTING, INC. (0.04)
KRL CONSTRUCTION INC. (0.03)
Contract #02183005
Totals20587594.96370448.8117870041.9386.8

CountyMCLENNAN
HighwayUS 84
FromSOUTH BOSQUE RIVER
ToSPUR 298
CSJ0055-08-119
Proj IDC 55-8-119
Work TypeMILL/PFC OVLY
 
6.1134721563.445179520.9299.9
Work Order05-14-18
Work Began08-27-18
Work Completed
Time Computed06-13-18
Contract Working Days90
Addl Days Granted10
Working Days Charged182
Percent Time Used182
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0055-08-119
FLASHER EQUIPMENT COMPANY (3.54)
PRIMATE CONSTRUCTION, INC. (1.65)
STRIPE-A-ZONE, INC. (0.35)
AREA WIDE PROTECTIVE, INC. (0.21)
DUSTROL, INC. (2.74)
Contract #04183232
Totals4721563.4421854.755179520.9299.9

CountyMCLENNAN
HighwayUS 84
From1.2 MI E OF FM 2837
To0.25 MI E OF SH 6
CSJ0055-08-122
Proj IDSTP 1902(127)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.650986493.0054779.005.5
Work Order09-18-19
Work Began12-18-19
Work Completed
Time Computed10-18-19
Contract Working Days60
Addl Days Granted0
Working Days Charged14
Percent Time Used23
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0055-08-122
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (7.23)
TOTAL HIGHWAY MAINTENANCE, LLC (0.92)
Contract #08193019
Totals986493.0054779.0054779.005.5

CountyLIMESTONE
HighwayUS 84
FromFM 1245
ToNAVASOTA RIVER
CSJ0056-02-033
Proj IDSTP 2019(224)
Work TypeWDN SHLDRS & ADD PASS LNS
 
15.0999187964.047964402.4686.7
Work Order12-17-18
Work Began03-18-19
Work Completed
Time Computed01-16-19
Contract Working Days168
Addl Days Granted0
Working Days Charged171
Percent Time Used101
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0056-02-033
D. I. J. CONSTRUCTION, INC. (1.16)
PRIMATE CONSTRUCTION, LP (0.87)
TRP CONSTRUCTION GROUP, LLC (0.15)
MURRAY CONSTRUCTION (0.81)
ROADWAY SPECIALTIES, INC. (5.55)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.17)
WEST TEXAS ROCK RESOURCES, LLC (0.07)
LS HIGHWAY PRODUCTS, INC. (0.76)
AREA WIDE PROTECTIVE, INC. (0.00)
BRYDL CONTRACTING, INC. (0.11)
Contract #11183006
Totals9187964.0461731.927964402.4686.7

CountyLIMESTONE
HighwaySH 14
FromFREESTONE CO LINE
ToFM 39
CSJ0093-04-046
Proj IDSTP 2020(468)
Work TypeOVERLAY
 
6.1193408710.760.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0093-04-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01203224
Totals3408710.760.000.000.0

CountyHAMILTON ETC
HighwayFM 218 ETC
From0.201 MI W OF FM 2005
To0.418 MI W OF FM 2005
CSJ0120-05-025
Proj IDSTP 2019(223)HES
Work TypeINCREASE SUPERELEVATION
 
1.164571906.90527189.1992.1
Work Order12-17-18
Work Began03-01-19
Work Completed
Time Computed01-16-19
Contract Working Days90
Addl Days Granted0
Working Days Charged74
Percent Time Used82
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0120-05-025
WEST TEXAS ROCK RESOURCES, LLC (0.69)
TOTAL HIGHWAY MAINTENANCE, LLC (5.18)
SAN-ANN-CO., INC. (3.64)
FORTSON CONTRACTING, INC. (5.16)
AREA WIDE PROTECTIVE, INC. (1.81)
TRP CONSTRUCTION GROUP, LLC (0.00)
Contract #11183221
Totals571906.90200.00527189.1992.1

CountyHILL
HighwaySH 31
FromCR 3344
ToNAVARRO CO LINE
CSJ0162-02-031
Proj IDSTP 2009(661)
Work TypeGR, STRS & SURF
 
9.77262906622.2838137012.0160.6
CountyHILL
HighwaySH 31
FromCR 3344
ToNAVARRO CO LINE
CSJ0162-02-036
Proj IDSTP 2009(676)
Work TypeROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
9.9241057262.641146086.8099.9
Work Order08-16-17
Work Began12-05-17
Work Completed
Time Computed10-15-17
Contract Working Days804
Addl Days Granted0
Working Days Charged549
Percent Time Used68
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0162-02-031
BUYERS BARRICADES, INC. (0.32)
EGGEMEYER LAND CLEARING, LLC (0.51)
ROADWAY SPECIALTIES, INC. (2.08)
VENUS CONSTRUCTION (1.62)
K & S UTILITY CONTRACTORS, INC. (0.80)
SAN_ANN BARRICADES,INC. (0.18)
D.I.J. CONSTRUCTION, INC (0.86)
DFW REBAR, INC. (0.55)
TEXAS STERLING CONSTRUCTION CO. (1.38)
BOWMAN ENGINEERING & CONSULTING, INC. (0.09)
J.E.D. TRUCKING, INC. (1.09)
OLDCASTLE MATERIALS TEXAS, INC. (21.47)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.92)
AUSTIN BRIDGE & ROAD SERVICES, LP (1.28)
FARR FOUNDATION, INC. (0.08)
Contract #07173002
Totals63963884.922363863.5739283098.8161.4

CountyHAMILTON
HighwaySH 36
FromUS 281
ToCORYELL CO LINE
CSJ0183-03-050
Proj IDSTP 2019(839)
Work TypeREHABILITATION OF EXISTING ROAD
 
15.81312587706.091851579.1414.7
Work Order06-20-19
Work Began08-05-19
Work Completed
Time Computed07-20-19
Contract Working Days330
Addl Days Granted5
Working Days Charged99
Percent Time Used29
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0183-03-050
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.64)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.30)
ROADWAY SPECIALTIES, INC. (3.70)
D. I. J. CONSTRUCTION, INC. (2.30)
SAN-ANN-CO., INC. (1.07)
SCR CIVIL CONSTRUCTION, LLC (2.21)
S & S BRIDGE PAINTING, INC. (2.16)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
J & M CONTRACTING, COMPANY (2.41)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.30)
Contract #05193209
Totals12587706.09429332.061851579.1414.7

CountyCORYELL
HighwaySH 36
FromFM 217
ToHAY VALLEY RD
CSJ0183-04-049
Proj IDSTP 1702(128)
Work TypeADD PASS LNS & WDN SHLDRS
 
11.82312363769.2111384689.4192.0
Work Order06-14-17
Work Began08-09-17
Work Completed
Time Computed07-14-17
Contract Working Days638
Addl Days Granted19
Working Days Charged597
Percent Time Used90
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0183-04-049
SAN-ANN-CO., INC. (1.09)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.41)
BEAR CREEK CONSTRUCTION, LLC (18.34)
FORTSON CONTRACTING, INC. (3.16)
D.I.J. CONSTRUCTION, INC (1.06)
STRIPE-A-ZONE, INC. (0.10)
CHEROKEE SERVICES (0.14)
POTTER TRUCKING (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
PRIMATE CONSTRUCTION, LP (0.13)
Contract #05173015
Totals12363769.21234870.8111384689.4192.0

page 1 | page 2 | page 3 | page 4