Monthly Local Let Maintenance Report For Waco District As Of Feb 09, 2018 Page 2 Of 5

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHILL
HighwayFM3370
FromFM 3370
To@ AQUILLA ISD
CSJ6299-28-001
Proj IDRMC - 629928001
Work TypeADD SHOULDER AND WIDEN EXISTING ROADWAY
 
0.100216593.00208312.40100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-13-16
Work Began06-20-16
Work Completed08-01-16
Time Computed06-15-16
Contract Working Days31
Addl Days Granted0
Working Days Charged9
Percent Time Used29
Contractor(s)
BRETT CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6299-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160901
Totals216593.000.00208312.40100.0

CountyCORYELL
HighwaySH0009
FromINTERSECTION OF SH 9 AND
ToFM 116
CSJ6300-02-001
Proj IDRMC - 630002001
Work TypeTRAFFIC SIGNAL INSTALLATION
 
0.100196235.20200754.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-16
Work Began09-08-16
Work Completed
Time Computed05-31-16
Contract Working Days50
Addl Days Granted0
Working Days Charged46
Percent Time Used92
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160902
Totals196235.200.00200754.0499.9

CountyBELL
HighwayUS0190
FromVAR. RDWYS IN BELL, BOSQUE, HILL, FALLS,
ToCORYELL,HAMILTON, LIMESTONE, & MCLENNAN
CSJ6303-05-001
Proj IDRMC - 630305001
Work TypeRAISED PAVEMENT MARKERS - DISTRICTWIDE
 
0.010191536.00155416.6481.1
Work Order03-09-17
Work Began03-27-17
Work Completed
Time Computed03-27-17
Contract Working Days63
Addl Days Granted0
Working Days Charged29
Percent Time Used46
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11160902
Totals191536.000.00155416.6481.1

CountyMCLENNAN
HighwaySH0006
FromVARIOUS ROADWAYS IN MCLENNAN, BELL,
ToHAMILTON AND LIMESTONE COUNTIES
CSJ6306-28-001
Proj IDRMC - 630628001
Work TypeSTORM SEWER & INLET CLEANING
 
0.010239901.5012255.755.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-11-17
Work Completed
Time Computed00-00-00
Contract Working Days74
Addl Days Granted45
Working Days Charged75
Percent Time Used63
Contractor(s)
H. T. S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11160903
Totals239901.501753.0012255.755.1

CountyMCLENNAN
HighwaySH0006
FromVARIOUS ROADWAYS IN
ToMCLENNAN COUNTY
CSJ6306-31-001
Proj IDRMC - 630631001
Work TypeTREE TRIMMING AND REMOVAL
 
0.010105037.5042017.5040.0
Work Order10-24-17
Work Began12-11-17
Work Completed
Time Computed11-20-17
Contract Working Days57
Addl Days Granted14
Working Days Charged31
Percent Time Used43
Contractor(s)
RAFTER JK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6306-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170901
Totals105037.5033317.5042017.5040.0

CountyCORYELL
HighwayUS0084
FromVARIOUS ROADWAYS IN CORYELL, BOSQUE
ToAND HAMILTON COUNTIES
CSJ6306-32-001
Proj IDRMC - 630632001
Work TypeTREE TRIMMIMG AND TREE REMOVAL
 
0.010190139.0036978.5019.4
Work Order00-00-00
Work Began11-13-17
Work Completed
Time Computed10-02-17
Contract Working Days97
Addl Days Granted0
Working Days Charged44
Percent Time Used45
Contractor(s)
KASPARIAN UNDERGROUND, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6306-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170902
Totals190139.0019130.0036978.5019.4

CountyHILL
HighwayUS0077
FromVARIOUS ROADWAYS IN HILL
ToAND FALL COUNTIES
CSJ6306-33-001
Proj IDRMC - 630633001
Work TypeTREE TRIMMING AND TREE REMOVAL
 
0.010173013.00196044.0099.9
Work Order09-29-17
Work Began10-03-17
Work Completed
Time Computed10-02-17
Contract Working Days90
Addl Days Granted0
Working Days Charged50
Percent Time Used55
Contractor(s)
KASPARIAN UNDERGROUND, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6306-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170903
Totals173013.007700.00196044.0099.9

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN
ToBELL COUNTY
CSJ6306-35-001
Proj IDRMC - 630635001
Work TypeCLEANING & SWEEPING
 
0.010296226.00169686.0057.2
Work Order05-16-17
Work Began05-22-17
Work Completed
Time Computed05-22-17
Contract Working Days176
Addl Days Granted0
Working Days Charged26
Percent Time Used14
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170901
Totals296226.0014602.00169686.0057.2

CountyFALLS
HighwaySH0007
FromVARIOUS ROADWAYS IN FALLS, HILL AND
ToLIMESTONE COUNTIES
CSJ6306-36-001
Proj IDRMC - 630636001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01046343.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170902
Totals46343.100.000.000.0

CountyHAMILTON
HighwaySH0036
FromVARIOUS ROADWAYS IN BOSQUE,CORYELL,
To& HAMILTON COUNTIES
CSJ6306-37-001
Proj IDRMC - 630637001
Work TypeCLEANING & SWEEPING
 
0.01085083.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days148
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170903
Totals85083.680.000.000.0

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN
ToMCLENNAN COUNTY
CSJ6306-38-001
Proj IDRMC - 630638001
Work TypeSWEEPING HIGHWAY
 
0.010125042.6561485.2349.1
Work Order07-07-17
Work Began07-16-17
Work Completed
Time Computed07-16-17
Contract Working Days240
Addl Days Granted0
Working Days Charged29
Percent Time Used12
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170904
Totals125042.6514338.8561485.2349.1

CountyBELL
HighwaySL0121
FromLAWN AND GROUNDS MAINTENANCE
ToFOR BELL COUNTY COMPLEX
CSJ6307-01-001
Proj IDSUP - 630701001
Work TypeLAWN AND GROUNDS MAINTENANCE
 
0.01014405.0013430.0093.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160932
Totals14405.000.0013430.0093.2

CountyCORYELL
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6307-02-001
Proj IDSUP - 630702001
Work TypeLAWN AND GROUNDS
 
0.01015545.009860.0063.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160933
Totals15545.000.009860.0063.4

CountyHAMILTON
HighwayFM0218
FromVARIOUS
ToVARIOUS
CSJ6307-03-001
Proj IDSUP - 630703001
Work TypeLAWN AND GROUNDS
 
0.0106280.005865.0093.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160934
Totals6280.000.005865.0093.3

CountyHILL
HighwaySH0081
FromVARIOUS
ToVARIOUS
CSJ6307-04-001
Proj IDSUP - 630704001
Work TypeLAWN AND GROUNDS MAINTENANCE
 
0.0109890.006150.0062.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160935
Totals9890.000.006150.0062.1

CountyCORYELL
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6307-12-001
Proj IDSUP - 630712001
Work TypePICNIC AREA MAINTENANCE
 
0.01047770.0039845.0083.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160942
Totals47770.000.0039845.0083.4

CountyHAMILTON
HighwayUS0281
FromVARIOUS
ToVARIOUS
CSJ6307-13-001
Proj IDSUP - 630713001
Work TypePICNIC AREA MAINTENANCE
 
0.01044370.0032375.0072.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160943
Totals44370.000.0032375.0072.9

CountyHILL
HighwaySH0081
FromVARIOUS
ToVARIOUS
CSJ6307-14-001
Proj IDSUP - 630714001
Work TypePICNIC AREA MAINTENANCE
 
0.01044300.0035905.0081.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160944
Totals44300.000.0035905.0081.0

CountyMCLENNAN
HighwayFM3476
FromVARIOUS ROADWAYS IN
ToMCLENNAN COUNTY
CSJ6307-16-001
Proj IDSUP - 630716001
Work TypeLITTER PICK UP AND DISPOSAL
 
0.01062824.5452596.12100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160946
Totals62824.540.0052596.12100.0

CountyBELL
HighwaySL0121
FromVARIOUS ROADWAYS IN
ToBELL COUNTY
CSJ6307-19-001
Proj IDSUP - 630719001
Work TypeLITTER PICK UP AND DISPOSAL
 
0.01094581.0488125.0593.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160949
Totals94581.040.0088125.0593.1

page 1 | page 2 | page 3 | page 4 | page 5