Monthly State Let Maintenance Report For Waco District As Of Feb 14, 2020 Page 1 Of 3

Last Update: Friday, February 14, 2020
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMCLENNAN
Highway0000000
From100 SOUTH LOOP DR
ToWACO TX 76704
CSJ4704-01-518
Proj IDCBC - 470401518
Work TypeRENOVATION OR REPAIR
 
0.001448094.490.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TD INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-518
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164222
Totals448094.490.000.000.0

CountyFALLS
HighwaySH0014
FromVARIOUS ROADWAYS IN
ToFALLS COUNTY
CSJ6270-61-001
Proj IDRMC - 627061001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010670190.00658724.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-14
Work Began10-17-14
Work Completed12-31-14
Time Computed09-15-14
Contract Working Days60
Addl Days Granted0
Working Days Charged40
Percent Time Used66
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06144002
Totals670190.000.00658724.00100.0

CountyBOSQUE
HighwaySH0006
FromVARIOUS LOCATIONS IN BELL,BOSQUE,CORYELL
ToFALLS,HAMILTON,HILL,LIMSTONE & MCLENNAN
CSJ6279-70-001
Proj IDRMC - 627970001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.1001686130.002580334.8499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-23-15
Work Began02-02-15
Work Completed
Time Computed02-09-15
Contract Working Days365
Addl Days Granted109
Working Days Charged474
Percent Time Used100
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6279-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11144211
Totals1686130.000.002580334.8499.9

CountyMCLENNAN
HighwayIH0035
FromIH 35, IH 35E & IH 35W IN BELL, FALLS
ToHILL AND MCLENNAN COUNTIES
CSJ6285-72-001
Proj IDRMC - 628572001
Work TypePERFORMANCE BASED MAINT. OF HIGHWAYS
 
115.50020967966.0037604013.0999.9
Work Order08-24-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days1,095
Addl Days Granted365
Working Days Charged1,248
Percent Time Used85
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164007
Totals20967966.00695569.1537604013.0999.9

CountyFALLS
HighwaySH0006
FromVARIOUS ROADWAYS IN BELL, BOSQUE, FALLS,
ToCORYELL AND MCLENNAN COUNTIES
CSJ6285-76-001
Proj IDRMC - 628576001
Work TypeMISC. CONCRETE REPAIRS
 
0.010856608.20662481.89100.0
Work Order01-25-16
Work Began01-27-16
Work Completed07-21-17
Time Computed01-27-16
Contract Working Days50
Addl Days Granted100
Working Days Charged119
Percent Time Used79
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6285-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07154002
Totals856608.2028425.00662481.89100.0

CountyBELL
HighwayFS1237
FromBELL-BOSQUE-CORYELL-FALLS-HAMILTON
ToHILL-LIMESTONE-MCLENNAN
CSJ6292-90-001
Proj IDRMC - 629290001
Work TypeSEAL COAT
 
0.1003195392.723086596.79100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-31-16
Work Began06-06-16
Work Completed09-13-16
Time Computed05-23-16
Contract Working Days40
Addl Days Granted8
Working Days Charged54
Percent Time Used112
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6292-90-001
FLASHER EQUIPMENT COMPANY (2.45)
PAVEMENT MARKINGS INC. (17.74)
Contract #12154004
Totals3195392.720.003086596.79100.0

CountyHILL
HighwaySH0171
FromVARIOUS RDWAYS IN HILL-BELL-BOSQUE-
ToCORYELL-FALLS-HAMILTON-LIMESTON-MCLENNAN
CSJ6295-20-001
Proj IDRMC - 629520001
Work TypeDRIFT/DEBRIS REMOVAL
 
0.100493500.00230837.40100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-05-16
Work Began04-11-16
Work Completed05-25-18
Time Computed04-11-16
Contract Working Days210
Addl Days Granted0
Working Days Charged21
Percent Time Used10
Contractor(s)
M & S CONCRETE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6295-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154204
Totals493500.000.00230837.40100.0

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN BELL, BOSQUE,
ToCORYELL & HAMILTON COUNTIES
CSJ6295-40-001
Proj IDRMC - 629540001
Work TypeMBGF, CABLE BARRIER & BRIDGE RAIL REP/IN
 
0.010386912.50510132.02100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-10-16
Work Began03-14-16
Work Completed04-30-17
Time Computed03-14-16
Contract Working Days365
Addl Days Granted0
Working Days Charged345
Percent Time Used94
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6295-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164013
Totals386912.500.00510132.02100.0

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN
ToBELL COUNTY
CSJ6298-26-001
Proj IDRMC - 629826001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.1001855386.001536032.95100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-30-16
Work Began10-03-16
Work Completed01-26-17
Time Computed10-01-16
Contract Working Days80
Addl Days Granted0
Working Days Charged35
Percent Time Used43
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03164204
Totals1855386.000.001536032.95100.0

CountyBELL
HighwayFM2184
FromVAR RDWYS IN BELL, BOSQUE, CORYELL, HILL
ToFALLS, HAMILTON, LIMESTONE & MCLENNAN
CSJ6303-06-001
Proj IDRMC - 630306001
Work TypeSEAL COAT (DISTRICT WIDE)
 
0.0102877967.282762625.65100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-18-17
Work Completed06-06-17
Time Computed03-01-17
Contract Working Days45
Addl Days Granted0
Working Days Charged21
Percent Time Used46
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-06-001
D.I.J. CONSTRUCTION, INC (13.83)
Contract #11164021
Totals2877967.280.002762625.65100.0

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN BELL, CORYELL,
ToFALLS AND LIMESTONE COUNTIES
CSJ6304-35-001
Proj IDRMC - 630435001
Work TypePAVEMENT MARKINGS
 
0.010786813.83337289.86100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-16
Work Began10-18-16
Work Completed10-11-17
Time Computed10-10-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6304-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164007
Totals786813.830.00337289.86100.0

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN MCLENNAN, FALLS,
ToHILL AND LIMESTONE COUNTIES
CSJ6312-44-001
Proj IDRMC - 631244001
Work TypeMBGF, CABLE BARRIERS & BRIDGE RAIL/REP/I
 
0.010772842.001048543.00100.0
Work Order01-11-18
Work Began01-11-18
Work Completed11-20-19
Time Computed01-18-18
Contract Working Days365
Addl Days Granted0
Working Days Charged678
Percent Time Used185
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6312-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174202
Totals772842.0034755.001048543.00100.0

CountyBELL
HighwayUS0190
FromVARIOUS LOCATIONS IN BELL,BOSQUE,CORYELL
ToHAMILTON,HILL,LIMESTONE & MCLENNAN CO.
CSJ6314-14-001
Proj IDRMC - 631414001
Work TypeDISTRICT WIDE MAINTENANCE OF SIGNAL SYS.
 
0.010371098.67468527.73100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-18-17
Work Completed03-10-19
Time Computed09-12-17
Contract Working Days365
Addl Days Granted180
Working Days Charged544
Percent Time Used99
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174201
Totals371098.670.00468527.73100.0

CountyMCLENNAN
HighwayUS0084
FromVAR RDWYS IN BELL,BOSQUE,FALLS, HILL,
ToCORYELL, HAMILTON, LIMESTONE, MCLENNAN
CSJ6314-15-001
Proj IDRMC - 631415001
Work TypeDISTRICT WIDE ILLUMINATION SYSTEMS
 
0.010287880.10182981.98100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-15-17
Work Completed08-23-19
Time Computed10-10-17
Contract Working Days365
Addl Days Granted420
Working Days Charged774
Percent Time Used98
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05174002
Totals287880.100.00182981.98100.0

CountyBELL
HighwaySH0317
FromVARIOUS LOCATIONS IN BELL, CORYELL,
ToFALLS & LIMESTONE COUNTIES
CSJ6316-08-001
Proj IDRMC - 631608001
Work TypeDISTRICT WIDE PAVEMENT MARKINGS
 
0.010728653.50653563.23100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-16-17
Work Completed01-04-19
Time Computed10-16-17
Contract Working Days365
Addl Days Granted86
Working Days Charged445
Percent Time Used98
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6316-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174013
Totals728653.500.00653563.23100.0

CountyBOSQUE
HighwaySH0006
FromVAR RDWYS IN BOSQUE, BELL, CORYELL,HILL,
ToHAMILTON, FALLS, LIMESTONE & MCLENNAN
CSJ6318-15-001
Proj IDRMC - 631815001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0102234850.001977370.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began10-02-17
Work Completed11-30-18
Time Computed10-02-17
Contract Working Days365
Addl Days Granted61
Working Days Charged425
Percent Time Used99
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6318-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174212
Totals2234850.000.001977370.00100.0

CountyBELL
HighwayUS0190
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6320-89-001
Proj IDRMC - 632089001
Work TypeLARGE SIGN MAINTENANCE
 
0.010336750.000.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-29-18
Work Completed01-25-19
Time Computed01-29-18
Contract Working Days365
Addl Days Granted0
Working Days Charged361
Percent Time Used98
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6320-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174012
Totals336750.000.000.00100.0

CountyMCLENNAN
HighwayUS0084
FromVAR ROADWAYS IN BELL, CORYELL, FALLS,
ToHAMILTON, HILL, LIMESTONE & MCLENNAN CO
CSJ6324-94-001
Proj IDRMC - 632494001
Work TypeMISCELLANEOUS CONCRETE REPAIRS
 
0.010648174.38871209.9599.9
Work Order04-24-18
Work Began05-14-18
Work Completed
Time Computed05-14-18
Contract Working Days67
Addl Days Granted192
Working Days Charged251
Percent Time Used96
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6324-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184005
Totals648174.387611.19871209.9599.9

CountyMCLENNAN
HighwaySH0006
FromRDWYS IN BELL, BOSQUE, CORYELL, FALLS,
ToHILL, HAMILTON, LIMESTONE & MCLENNAN
CSJ6326-46-001
Proj IDRMC - 632646001
Work TypeDISTRICT WIDE PAVEMENT MARKINGS
 
0.0101217231.252270546.6999.9
Work Order12-18-18
Work Began01-02-19
Work Completed
Time Computed01-02-19
Contract Working Days365
Addl Days Granted365
Working Days Charged389
Percent Time Used53
Contractor(s)
PMI PAVEMENT MARKING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10184006
Totals1217231.25137702.892270546.6999.9

CountyBELL
HighwayUS0190
FromVAR RDWYS IN BELL, BOSQUE, CORYELL, HILL
ToFALLS, HAMILTON, LIMESTONE & MCLENNAN
CSJ6326-48-001
Proj IDRMC - 632648001
Work TypeD/W MAINTENCE OF SIGNAL SYSTEMS
 
0.010381915.0013370.003.5
Work Order05-06-19
Work Began00-00-00
Work Completed
Time Computed04-30-19
Contract Working Days365
Addl Days Granted0
Working Days Charged265
Percent Time Used72
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03194023
Totals381915.004400.0013370.003.5

page 1 | page 2 | page 3