Monthly State Let Construction Report For Wichita Falls District As Of Oct 16, 2017 Page 1 Of 2

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMONTAGUE ETC
HighwayUS 81 ETC
FromRED RIVER
ToNEAR SL 19
CSJ0013-02-021
Proj IDNH 2017(269)
Work TypeSEAL COAT
 
180.0975209700.385402120.28100.0
Work Order12-13-16
Work Began07-21-17
Work Completed10-03-17
Time Computed01-12-17
Contract Working Days74
Addl Days Granted0
Working Days Charged77
Percent Time Used104
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0013-02-021
VIZCAINO, L.P. (25.49)
BARRICADES PLUS, LLC (1.61)
Contract #11163224
Totals5209700.38135542.795402120.28100.0

CountyMONTAGUE ETC
HighwayUS 81 ETC
FromSL 19
ToBLACKMAN RD
CSJ0013-03-035
Proj IDNH 2017(603)
Work TypeREHABILITATION OF EXISTING ROAD
 
38.085758517.00780757.8099.9
Work Order03-15-17
Work Began06-13-17
Work Completed
Time Computed04-14-17
Contract Working Days50
Addl Days Granted0
Working Days Charged60
Percent Time Used120
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0013-03-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173044
Totals758517.00103101.60780757.8099.9

CountyMONTAGUE
HighwayUS 81
FromFRUITLAND ROAD
ToWISE COUNTY LINE (NBL)
CSJ0013-05-058
Proj IDNH 1602(199)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
4.9873543752.803370250.6895.1
Work Order08-03-16
Work Began02-07-17
Work Completed
Time Computed09-02-16
Contract Working Days102
Addl Days Granted0
Working Days Charged86
Percent Time Used84
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-058
ALTUS TRAFFIC MANAGEMENT LLC (0.19)
WOLFE CONSTRUCTION GROUP, INC. (0.28)
TEXOP CONSTRUCTION (0.30)
O. TREVINO CONSTRUCTION, LLC (3.76)
DUSTROL, INC. (0.22)
SYNERGY SIGNS & SERVICES, LLC (0.99)
TOTAL HIGHWAY MAINTENANCE, LLC (0.70)
W.O.E. CONSTRUCTION (0.21)
WATTS EXCAVT (0.83)
Contract #06163217
Totals3543752.8038953.383370250.6895.1

CountyMONTAGUE
HighwayUS 81
From0.410 MI N OF SS 511
ToWISE CO LINE
CSJ0013-05-060
Proj IDSTP 1702(123)HES
Work TypeHAZARD ELIMINATION SAFETY
 
2.3623439171.431207034.7635.0
Work Order06-14-17
Work Began07-14-17
Work Completed
Time Computed07-14-17
Contract Working Days100
Addl Days Granted0
Working Days Charged38
Percent Time Used38
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-060
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (6.32)
W.S. CONSTRUCTION COMPANY (1.34)
PRIMATE CONSTRUCTION, INC. (0.79)
LINDAMOOD CONSTRUCTION COMPANY, INC. (0.28)
THE LANE CONSTRUCTION CORPORATION (12.55)
DUSTROL, INC. (0.84)
COX PAVING OF TEXAS, INC. (2.33)
BOWMAN ENGINEERING & CONSULTING, INC (1.10)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99)
WOLFE CONSTRUCTION GROUP, INC. (0.28)
Contract #05173027
Totals3439171.43429305.641207034.7635.0

CountyWILBARGER
HighwayUS 70
FromFM 433
ToAT US 70/287
CSJ0043-06-084
Proj IDBR 1702(470)
Work TypeBRIDGE REHABILITATION OR WIDENING
 
0.5303149693.500.000.0
Work Order08-08-17
Work Began00-00-00
Work Completed
Time Computed09-07-17
Contract Working Days204
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-06-084
ALTUS TRAFFIC MANAGEMENT LLC (0.54)
MCL CONTRACTING, LLC (0.44)
Contract #07173229
Totals3149693.500.000.000.0

CountyWILBARGER
HighwayUS 287
FromNEAR SH 240
ToNEAR BU 287H
CSJ0043-07-109
Proj IDNH 2017(140)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.4022490919.292487714.9399.8
Work Order11-22-16
Work Began04-20-17
Work Completed
Time Computed12-22-16
Contract Working Days102
Addl Days Granted10
Working Days Charged95
Percent Time Used84
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-07-109
CONTRACTORS SERVICE COMPANY (0.48)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.30)
STRIPING TECHNOLOGY, L.P. (1.50)
W.S. CONSTRUCTION COMPANY (1.42)
ZACK BURKETT CO. (54.49)
STRIPING SYSTEMS, INC. (0.00)
Contract #10163025
Totals2490919.2920391.982487714.9399.8

CountyWICHITA
HighwayUS 287
FromAT WELLINGTON LANE
To.
CSJ0043-09-126
Proj IDBR 1602(577)
Work TypeBRIDGE REPLACEMENT
 
0.3112454758.602285332.8593.0
Work Order10-12-16
Work Began12-20-16
Work Completed
Time Computed11-11-16
Contract Working Days185
Addl Days Granted0
Working Days Charged179
Percent Time Used96
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-126
COMEN ENTERPRISE LLC (2.39)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.33)
MARCOM"S MOWING SERVICE, LLC (1.21)
ZACK BURKETT CO. (6.28)
TOTAL HIGHWAY MAINTENANCE, LLC (1.43)
A BROTHERS MILLING, LLC (0.61)
Contract #08163208
Totals2454758.60184229.002285332.8593.0

CountyWICHITA
HighwayUS 287
FromAT RIFLE RANGE ROAD
To.
CSJ0043-09-130
Proj IDBR 1702(594)
Work TypeBRIDGE REPLACEMENT
 
0.3482398060.270.000.0
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed09-10-17
Contract Working Days214
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-130
MORRIS COUNTY CONTRACTORS, LLC (3.20)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.65)
WOLFE CONSTRUCTION GROUP, INC. (1.31)
STRIPING TECHNOLOGY, L.P. (0.65)
STRIPING SYSTEMS, INC. (0.00)
ZACK BURKETT CO. (11.24)
MICA CORPORATION (3.08)
TEXOP CONSTRUCTION (1.47)
ALTUS TRAFFIC MANAGEMENT LLC (0.63)
Contract #07173249
Totals2398060.270.000.000.0

CountyWICHITA
HighwaySL 11
FromLOOP 11 AT WICHITA RIVER
To.
CSJ0043-14-024
Proj IDBR 2017(880)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.076351296.40343762.9397.8
Work Order04-12-17
Work Began06-05-17
Work Completed
Time Computed05-12-17
Contract Working Days51
Addl Days Granted0
Working Days Charged50
Percent Time Used98
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-14-024
DUSTIN ALLEN, INC. (4.26)
ALTUS TRAFFIC MANAGEMENT LLC (0.45)
Contract #03173004
Totals351296.40208801.34343762.9397.8

CountyWICHITA
HighwayBU 287J
FromJOHNSON ROAD.
ToFM 368/ YOSEMITE ST.
CSJ0043-17-030
Proj IDNH 2017(399)
Work TypeOVERLAY
 
7.6283440613.521576381.7446.2
Work Order01-17-17
Work Began08-22-17
Work Completed
Time Computed02-16-17
Contract Working Days51
Addl Days Granted0
Working Days Charged65
Percent Time Used127
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-17-030
W.S. CONSTRUCTION COMPANY (3.09)
TEXAS ALTERNATIVE GRASSER, INC. (0.29)
DUSTROL, INC. (4.84)
STRIPE-A-ZONE, INC. (3.32)
HJC FARMS, INC. (1.42)
CONTRACTORS SERVICE COMPANY (0.51)
Contract #12163012
Totals3440613.521203626.031576381.7446.2

CountyCLAY
HighwayUS 82 ETC
FromUS 82 EASTBOUND AT DUCK CREEK
To.
CSJ0044-02-079
Proj IDBR 2016(355)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
24.6745938095.15938163.4715.7
Work Order03-31-16
Work Began06-05-17
Work Completed
Time Computed05-01-16
Contract Working Days197
Addl Days Granted14
Working Days Charged76
Percent Time Used36
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-02-079
W.S. CONSTRUCTION COMPANY (14.24)
COTHRAN TRUCKING, LLC (0.95)
WOLFE CONSTRUCTION GROUP, INC. (0.42)
DUSTROL, INC. (17.02)
HALL BROTHERS, INC. (7.12)
DUSTIN ALLEN, INC. (4.55)
TOTAL HIGHWAY MAINTENANCE, LLC (1.83)
ALTUS TRAFFIC MANAGEMENT LLC (0.47)
Contract #01163022
Totals5938095.1583729.66938163.4715.7

CountyMONTAGUE
HighwayUS 82
FromHANSON ROAD
ToNEAR NOCONA WEST CITY LIMITS
CSJ0044-04-059
Proj IDNH 2017(401)
Work TypeRESTORATION
 
20.9514894838.283635673.6474.2
Work Order05-18-17
Work Began06-28-17
Work Completed
Time Computed06-17-17
Contract Working Days71
Addl Days Granted0
Working Days Charged48
Percent Time Used67
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-059
ALTUS TRAFFIC MANAGEMENT LLC (0.13)
LANCO TURF & SEEDING, INC. (0.56)
DUSTROL, INC. (0.94)
TOTAL HIGHWAY MAINTENANCE, LLC (4.86)
DIAMOND SURFACE, INC. (0.90)
Contract #04173235
Totals4894838.281281499.693635673.6474.2

CountyMONTAGUE
HighwayUS 82
FromSH 175
ToGRAYSON ST.
CSJ0044-04-060
Proj IDNH 1702(173)
Work TypeTRAFFIC SIGNAL
 
0.215268000.000.000.0
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed11-12-17
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-060
ROAD MASTER STRIPING LLC (1.50)
Contract #05173041
Totals268000.000.000.000.0

CountyCOOKE
HighwayUS 82
FromNEAR WEBER DRIVE
ToNEAR IH 35
CSJ0044-08-067
Proj IDNH 2016(693)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.3214684274.464951840.5899.9
Work Order05-18-16
Work Began08-29-16
Work Completed
Time Computed06-17-16
Contract Working Days192
Addl Days Granted59
Working Days Charged231
Percent Time Used92
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-08-067
DALLAS LIGHT & BARRICADES (0.87)
MARCOM"S MOWING SERVICE, LLC (0.39)
DUSTROL, INC. (1.65)
DRILL TECH DRILLING & SHORING, INC. (4.89)
METRO CUTTING AND SEALING, INC. (3.55)
STRIPING TECHNOLOGY, L.P. (1.97)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION, LTD. (0.00)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.88)
W.O.E. CONSTRUCTION (0.59)
FARR FOUNDATION, INC. (5.16)
JSS BORI GROUP, LLC (3.56)
OSCAR ORDUNO, INC. (6.19)
JND & SONS BARRIER, LLC (2.01)
Contract #02163209
Totals4684274.46347909.314951840.5899.9

CountyWILBARGER
HighwayUS 183
FromBEAVER CREEK
ToNEAR FM 2585
CSJ0124-04-031
Proj IDSTP 2017(141)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.0976688994.613118599.4246.6
Work Order11-22-16
Work Began01-03-17
Work Completed
Time Computed12-22-16
Contract Working Days208
Addl Days Granted0
Working Days Charged139
Percent Time Used66
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0124-04-031
CONTRACTORS SERVICE COMPANY (0.23)
HJC FARMS, INC. (1.75)
W.S. CONSTRUCTION COMPANY (11.63)
TOTAL HIGHWAY MAINTENANCE, LLC (1.21)
WEST TEXAS RUMBLE STRIP (0.13)
ZACK BURKETT CO. (45.77)
Contract #10163005
Totals6688994.61289569.223118599.4246.6

CountyTHROCKMORTON
HighwayUS 283
FromONE MILE NORTH OF FM 2584
ToFM 209
CSJ0125-03-046
Proj IDSTP 2018(185)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.1961720296.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days136
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0125-03-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173215
Totals1720296.450.000.000.0

CountyARCHER
HighwayUS 277
From2.083 MILES WEST OF FM 2846
To1.69 MILES WEST OF FM 368
CSJ0156-05-049
Proj IDNH 1302(006)
Work TypeWIDEN NON-FREEWAY
 
4.00514393280.5712713254.8588.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-15
Work Began06-18-15
Work Completed
Time Computed06-21-15
Contract Working Days313
Addl Days Granted15
Working Days Charged340
Percent Time Used103
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-049
W.S. CONSTRUCTION COMPANY (11.44)
ALTUS TRAFFIC MANAGEMENT LLC (0.19)
BARRICADES UNLIMITED (0.94)
MARCOM"S MOWING SERVICE, LLC (0.39)
WEST TEXAS RUMBLE STRIP (0.02)
ZACK BURKETT CO. (24.93)
SPIRES LANDSCAPING, INC. (0.40)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (2.95)
Contract #04153007
Totals14393280.570.0012713254.8588.4

CountyWICHITA
HighwayIH 44
From0.023 MI. S OF SH 240
ToOKLAHOMA STATE LINE
CSJ0156-07-109
Proj IDSTP 1702(401)HES
Work TypeHAZARD ELIMINATION SAFETY
 
2.5001167403.500.000.0
Work Order07-20-17
Work Began10-11-17
Work Completed
Time Computed08-19-17
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-07-109
CONTRACTORS SERVICE COMPANY (0.85)
AARON CONCRETE CONTRACTORS, L.P. (6.60)
Contract #06173038
Totals1167403.500.000.000.0

CountyCOOKE
HighwayIH 35 ETC
FromON IH 35
ToAT FM 51 (NB & SB)
CSJ0195-01-099
Proj IDNH 1502(347)
Work TypeMISCELLANEOUS
 
1.0392144827.682483501.83100.0
Work Order11-10-15
Work Began01-25-16
Work Completed10-06-17
Time Computed11-10-15
Contract Working Days200
Addl Days Granted40
Working Days Charged289
Percent Time Used120
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0195-01-099
ALTUS TRAFFIC MANAGEMENT LLC (0.78)
EROSION CONTROL MANAGEMENT SERVICES (0.22)
STRIPING TECHNOLOGY, L.P. (4.44)
S & S BRIDGE PAINTING, INC. (9.11)
HJC FARMS, INC. (18.98)
TEXAS CUTTING & CORING, INC. (1.37)
PENHALL COMPANY (0.31)
Contract #06153016
Totals2144827.68936.562483501.83100.0

CountyARCHER
HighwayUS 281
FromSH 25
ToJACK COUNTY LINE
CSJ0249-04-039
Proj IDSTP 2013(624)
Work TypeREHABLIITAITION OF EXISTING ROAD
 
8.73710168493.2210162678.44100.0
Work Order05-08-15
Work Began07-13-15
Work Completed09-18-17
Time Computed05-24-15
Contract Working Days345
Addl Days Granted3
Working Days Charged318
Percent Time Used91
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0249-04-039
W.S. CONSTRUCTION COMPANY (6.30)
CROSSROADS, L.P. (0.23)
STRIPING TECHNOLOGY, L.P. (1.55)
DUSTROL, INC. (2.47)
WOLFE CONSTRUCTION GROUP, INC. (0.85)
MARCOM"S MOWING SERVICE, LLC (0.35)
WEST TEXAS RUMBLE STRIP (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.30)
TRP CONSTRUCTION GROUP, LLC (0.73)
Contract #03153034
Totals10168493.2297375.3710162678.44100.0

page 1 | page 2