Monthly State Let Construction Report For Wichita Falls District As Of Nov 12, 2021 Page 1 Of 2

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMONTAGUE ETC
HighwayUS 81 ETC
FromRED RIVER
ToSL 19 (LANES ONLY)
CSJ0013-02-023
Proj IDSTP 2B20(301)
Work TypeSEAL COAT
 
198.7027507421.975013061.1867.3
Work Order12-11-20
Work Began06-14-21
Work Completed
Time Computed05-21-21
Contract Working Days50
Addl Days Granted0
Working Days Charged91
Percent Time Used182
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-02-023
BARRICADES PLUS, LLC (2.12)
CDM HOLDINGS, LLC (66.65)
Contract #11203210
Totals7507421.97855415.685013061.1867.3

CountyMONTAGUE ETC
HighwaySH 101 ETC
FromUS 81
ToFM 1749
CSJ0013-13-005
Proj IDF 2022(125)
Work TypeSEAL COAT
 
47.4808024250.280.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0013-13-005
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213206
Totals8024250.280.000.000.0

CountyWILBARGER ETC
HighwayUS 70 ETC
FromUS 287
ToLAURIE STREET
CSJ0043-05-110
Proj IDSTP 1902(143)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
54.1048701328.897111765.9481.9
Work Order09-25-19
Work Began05-28-20
Work Completed
Time Computed10-25-19
Contract Working Days263
Addl Days Granted0
Working Days Charged281
Percent Time Used106
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-05-110
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.50)
TOTAL HIGHWAY MAINTENANCE, LLC (0.60)
FABER TECHNOLOGIES USA, INC. (1.28)
Contract #08193007
Totals8701328.89659601.417111765.9481.9

CountyWILBARGER
HighwayUS 287
FromOKLAUNION
ToHARROLD
CSJ0043-07-119
Proj IDF 2021(700)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5165943.812078413.6640.2
Work Order09-15-21
Work Began09-17-21
Work Completed
Time Computed09-13-21
Contract Working Days136
Addl Days Granted0
Working Days Charged27
Percent Time Used19
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-07-119
JR WEST TEXAS CONCRETE LLC (5.12)
MARCOM"S MOWING SERVICE, LLC (1.85)
TEXAS PANHANDLE CONSTRUCTION, INC. (1.20)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.96)
DUSTROL, INC. (0.74)
TEXAS TRAFFIC AND BARRICADE, LLC (0.31)
DUSTIN ALLEN, INC. (0.24)
JENNINGS TRUCKING SERVICE, INC. (0.29)
Contract #07213215
Totals5165943.811698427.312078413.6640.2

CountyWICHITA
HighwayUS 287
From.
ToSB AND NB REST AREAS NEAR IOWA PARK
CSJ0043-08-084
Proj IDNH 2020(165)
Work TypeSAFETY REST AREA
 
0.7635141357.004172292.6881.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-20-19
Work Began01-20-20
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted18
Working Days Charged352
Percent Time Used110
Contractor(s)
ANTHONY INMAN CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-08-084
BUTLER & BUTLER CONSTRUCTION LLC (9.17)
WILSON CONTRACTING (8.12)
DALLAS LITE AND BARRICADE, INC. (0.13)
BREEGLE BUILDING PRODUCTS, INC. (4.08)
FERGUSON-VERESH, INC. (9.03)
ARMORED ROOFING COMPANY, INC. (2.51)
RHS STEEL CONSTRUCTORS, LLC (2.08)
SORGE CONTRACTING INC. (0.17)
WICHITA FALLS COMPLETE LAWN SERVICE, LLC (2.62)
BNR CONCRETE POLISHING, LLC (0.21)
CHENEY ELECTRIC, LLC (4.53)
COMMERCIAL & INDUSTRIAL ELECTRONICS, INC. (2.89)
B & R SERVICES (0.01)
Contract #10193028
Totals5141357.00104572.084172292.6881.8

CountyWICHITA
HighwayUS 287
FromBU 287H
To0.5 MI W OF JOHNSON RD
CSJ0043-08-085
Proj IDF 2021(514)
Work TypeREHABILITATION OF EXISTING ROAD
 
2590826.342514530.5497.0
CountyWICHITA
HighwayUS 287
From0.5MI W OF JOHNSON RD
ToBELL RD
CSJ0043-09-143
Proj IDF 2021(514)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.001550271.40532221.5296.7
Work Order06-10-21
Work Began07-19-21
Work Completed
Time Computed07-10-21
Contract Working Days85
Addl Days Granted0
Working Days Charged67
Percent Time Used78
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-08-085
HJC FARMS, INC. (12.44)
DUSTROL, INC. (5.23)
TOTAL HIGHWAY MAINTENANCE, LLC (1.91)
W. S. CONSTRUCTION COMPANY (0.79)
PINNACLE GRINDING AND GROOVING LLC (0.34)
TEXAS TRAFFIC AND BARRICADE, LLC (0.26)
LANCO TURF & SEEDING, INC. (0.21)
Contract #05213212
Totals3141097.74141253.363046752.0696.9

CountyWICHITA
HighwayIH 44
From8TH STREET
To6TH STREET
CSJ0043-09-144
Proj IDBR 2021(701)
Work TypeBRIDGE MAINTENANCE
 
380801.090.000.0
CountyWICHITA
HighwayUS 277
FromUS 82
To8TH STREET
CSJ0044-01-108
Proj IDBR 2021(701)
Work TypeBRIDGE MAINTENANCE
 
1044768.800.000.0
CountyWICHITA
HighwayUS 82
FromHOLLIDAY CREEK
ToLOOP 473
CSJ0044-01-109
Proj IDBR 2021(701)
Work TypeBRIDGE MAINTENANCE
 
1930691.090.000.0
Work Order09-16-21
Work Began00-00-00
Work Completed
Time Computed10-16-21
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-144
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213034
Totals3356260.980.000.000.0

CountyWICHITA
HighwaySL 11
FromUS 287
ToFM 367
CSJ0043-14-026
Proj IDNH 2B20(225)
Work TypeOVERLAY
 
2.1501360148.32660981.7848.5
Work Order12-04-20
Work Began10-11-21
Work Completed
Time Computed01-03-21
Contract Working Days51
Addl Days Granted0
Working Days Charged11
Percent Time Used21
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-14-026
DUSTROL, INC. (5.30)
W. S. CONSTRUCTION COMPANY (4.00)
HJC FARMS, INC. (3.58)
MPB, INC. (2.35)
TRP CONSTRUCTION GROUP, LLC (2.22)
LANCO TURF & SEEDING, INC. (0.63)
TOTAL HIGHWAY MAINTENANCE, LLC (0.33)
Contract #11203027
Totals1360148.32660981.78660981.7848.5

CountyMONTAGUE
HighwayUS 82
FromSH 175 / MONTAGUE STREET
ToNEAR FM 1816
CSJ0044-04-047
Proj IDF 2021(704)
Work TypeWIDEN NON-FREEWAY
 
6.10027683391.05339566.091.2
CountyMONTAGUE
HighwayUS 82
From0.5 MI EAST OF US 81
ToNEAR FM 1816
CSJ0044-04-049
Proj IDF 2021(704)
Work TypeWIDEN NON-FREEWAY
 
5.82920779023.04689.790.0
Work Order08-19-21
Work Began10-25-21
Work Completed
Time Computed09-20-21
Contract Working Days719
Addl Days Granted0
Working Days Charged8
Percent Time Used1
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-047
STRAIGHT LINE SAWING & SEALING, INC. (0.24)
PINNACLE GRINDING AND GROOVING LLC (0.03)
JR WEST TEXAS CONCRETE LLC (3.18)
AREA WIDE PROTECTIVE, INC. (0.25)
DUSTY ALLEN, INC. (0.28)
DUSTROL, INC. (0.25)
HAMMETT EXCAVATION, INC. (24.23)
STRIPING TECHNOLOGY, L.P. (0.97)
TEXAS SHAFTS, INC. (0.86)
L&H ELECTRICAL, LLC (0.70)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.84)
Contract #07213001
Totals48462414.09340255.88340255.880.7

CountyCOOKE
HighwayFM 1199
FromFM 3108
ToUS 82
CSJ0044-09-067
Proj IDF 2021(705)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1043643.1517350.001.6
CountyCOOKE
HighwayFM 3108
FromFM 1199
ToFM 1630
CSJ3192-01-007
Proj IDF 2021(705)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2775494.460.000.0
CountyCOOKE
HighwayFM 3108
FromFM 3108
ToAT ELM FORK TRINITY RIVER
CSJ3192-01-008
Proj IDBR 2021(706)
Work TypeBRIDGE REPLACEMENT
 
1208335.370.000.0
Work Order08-18-21
Work Began00-00-00
Work Completed
Time Computed09-17-21
Contract Working Days238
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-09-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213211
Totals5027472.9817350.0017350.000.3

CountyWILBARGER
HighwayUS 183
From0.992 MI S OF FM 1763
ToBAYLOR COUNTY LINE
CSJ0124-04-038
Proj IDSTP 2B20(074)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.68010036994.001885560.7018.7
CountyBAYLOR
HighwayUS 183
FromWILBARGER CL
To5.737 MI N OF US 82
CSJ0124-05-025
Proj IDSTP 2B20(074)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.2505079547.73773526.1015.2
Work Order11-19-20
Work Began01-21-21
Work Completed
Time Computed12-19-20
Contract Working Days359
Addl Days Granted0
Working Days Charged151
Percent Time Used42
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0124-04-038
BARRICADES UNLIMITED (1.89)
FC TRAFFIC CONTROL, INC. (0.22)
MARCOM"S MOWING SERVICE, LLC (0.28)
W. S. CONSTRUCTION COMPANY (9.26)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.41)
WEST TEXAS ROCK RESOURCES, LLC (0.11)
ZACK BURKETT CO. (36.83)
Contract #10203205
Totals15116541.7338694.082659086.8017.5

CountyBAYLOR
HighwaySH 114
FromBU 183B
ToUS 183
CSJ0133-05-030
Proj IDF 2021(515)
Work TypeOVERLAY
 
208298.760.000.0
CountyBAYLOR
HighwayBU 183B
FromSH 114
ToUS 82
CSJ0156-06-061
Proj IDF 2021(515)
Work TypeOVERLAY
 
182211.360.000.0
CountyBAYLOR
HighwayUS 82
FromBU 183B
ToUS 183
CSJ0156-06-062
Proj IDF 2021(515)
Work TypeOVERLAY
 
450401.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0133-05-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213029
Totals840911.260.000.000.0

CountyYOUNG
HighwaySH 251
FromSH 79
ToFM 926
CSJ0134-01-025
Proj IDSTP 2B20(075)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
11.3001754989.601827879.0499.9
CountyYOUNG
HighwaySH 16
FromCOUNTRY MEADOWS DR.
To0.7 MI E OF FM 1191
CSJ0362-01-052
Proj IDSTP 2B20(075)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.687277545.5013360.004.8
CountyTHROCKMORTON
HighwaySH 222
FromCABIN RD
To0.8 MI N OF OTTS ROAD
CSJ0982-03-016
Proj IDSTP 2B20(075)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.741266693.9029991.0011.2
Work Order09-16-20
Work Began11-09-20
Work Completed
Time Computed01-16-22
Contract Working Days253
Addl Days Granted40
Working Days Charged214
Percent Time Used73
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0134-01-025
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.77)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.00)
PEACHTREE CONSTRUCTION, LTD. (3.96)
STRIPING TECHNOLOGY, L.P. (0.80)
PINNACLE GRINDING AND GROOVING LLC (0.10)
FC TRAFFIC CONTROL, INC. (0.60)
TOTAL HIGHWAY MAINTENANCE, LLC (6.39)
MARCOM"S MOWING SERVICE, LLC (0.69)
W. S. CONSTRUCTION COMPANY (4.09)
Contract #08203029
Totals2299229.00221311.501871230.0481.3

CountyYOUNG
HighwayUS 380
From.350 MI E OF FM 926
ToFM 1769
CSJ0134-02-059
Proj IDSTP 2021(868)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.4914045567.020.000.0
Work Order09-16-21
Work Began00-00-00
Work Completed
Time Computed10-16-21
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0134-02-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213229
Totals4045567.020.000.000.0

CountyYOUNG
HighwayUS 380
FromFM 926
ToNEWCASTLE EAST CITY LIMITS
CSJ0134-02-060
Proj IDF 2022(135)
Work TypeOVERLAY
 
9.4362285264.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days46
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0134-02-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213024
Totals2285264.980.000.000.0

CountyWICHITA
HighwaySH 240
FromIH 44
ToNEAR ROBINSON ROAD
CSJ0156-02-033
Proj IDF 2021(707)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
701607.840.000.0
CountyWICHITA
HighwaySH 240
FromNEAR ROBINSON ROAD
To2ND STREET
CSJ0156-03-049
Proj IDF 2021(707)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1128031.000.000.0
Work Order08-25-21
Work Began00-00-00
Work Completed
Time Computed09-24-21
Contract Working Days152
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0156-02-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213019
Totals1829638.840.000.000.0

CountyWICHITA
HighwayUS 82
FromARCHER COUNTY LINE
ToBEGIN 4 LANE UNDIVIDED
CSJ0156-04-125
Proj IDF 2021(418)
Work TypeOVERLAY
 
363896.75984444.2199.9
CountyARCHER
HighwayUS 82
From1.95 MI E OF FM 2846
ToBU 82F (IN SECTIONS)
CSJ0156-05-062
Proj IDF 2021(418)
Work TypeOVERLAY
 
4362424.552291730.4452.5
CountyARCHER
HighwayUS 82
FromBU 82F
ToWICHITA COUNTY LINE
CSJ0156-17-030
Proj IDF 2021(418)
Work TypeOVERLAY
 
3.1002333112.551179557.5750.5
Work Order04-08-21
Work Began08-23-21
Work Completed
Time Computed05-08-21
Contract Working Days102
Addl Days Granted0
Working Days Charged98
Percent Time Used96
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-04-125
BARRICADES UNLIMITED (1.90)
CONTRACTORS SERVICE COMPANY (0.17)
A.L. CONSTRUCTION LLC (2.55)
DUSTIN ALLEN, INC. (2.34)
PINNACLE GRINDING AND GROOVING LLC (0.21)
M.A.R. TRUCKING (7.92)
Contract #03213205
Totals7059433.851551313.524455732.2263.1

CountyARCHER ETC
HighwayUS 82 ETC
FromBAYLOR COUNTY LINE
ToBU 82F
CSJ0156-05-061
Proj IDSTP 1902(036)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
46.6847252069.495303393.3673.1
Work Order09-25-19
Work Began03-11-20
Work Completed
Time Computed10-25-19
Contract Working Days346
Addl Days Granted0
Working Days Charged299
Percent Time Used86
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-061
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.50)
CONTRACTORS SERVICE COMPANY (0.65)
Contract #08193212
Totals7252069.49166185.215303393.3673.1

CountyARCHER
HighwayUS 82
From2.2 MI WEST OF FM 2846
To1.95 MI EAST OF FM 2846
CSJ0156-05-063
Proj IDF 2022(136)
Work TypeOVERLAY
 
4.9504706206.170.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days62
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213025
Totals4706206.170.000.000.0

CountyCOOKE
HighwayIH 35
From1.4 MI SOUTH OF SPRING CREEK ROAD
To0.2 MI SOUTH OF US 82
CSJ0195-01-119
Proj IDNH 2021(327)
Work TypeWIDEN FREEWAY
 
7.900208432431.1430225456.1714.4
CountyCOOKE
HighwayIH 35
From1.4 MI SOUTH OF SPRING CREEK ROAD
To0.2 MI SOUTH OF US 82
CSJ0195-01-120
Proj IDROW 0195-1-120
Work TypeRIGHT OF WAY
 
7.9001566682.22353840.0022.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-18-21
Work Began06-21-21
Work Completed
Time Computed00-00-00
Contract Working Days1,395
Addl Days Granted0
Working Days Charged107
Percent Time Used7
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0195-01-119
DOUBLE EE CONTRACTORS, LLC (0.01)
BARRICADES UNLIMITED (0.67)
ANTIGO CONSTRUCTION, INC. (0.24)
SOUTHERN CROSS CONTRACTORS, LLC (0.05)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.10)
FORTSON CONTRACTING, INC. (0.58)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.43)
SCOTT DERR PAINTING CO, LLC (0.06)
W.O.E. CONSTRUCTION, INC. (2.24)
TEXAS SHAFTS, INC. (0.67)
OSCAR ORDUNO, INC. (1.60)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.27)
MONARREZ TRUCKING LLC. (0.00)
DALE BROWN, INC. (0.00)
TIME STRIPING, INC. (0.05)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.17)
STRAIGHT LINE SAWING & SEALING, INC. (0.00)
WITHERS CONSTRUCTION, LLC (0.00)
FREIGHT OPERATION SERVICES, LLC, DBA FOS BROKERAGE SERVICES (0.00)
VENUS CONSTRUCTION COMPANY (0.78)
RAY"S THREADING AND FAB SHOP (1.40)
SKAGGS ROAD BORING, INC. (0.15)
HERMANOS STEEL, LLC (0.04)
ZACHRY CONSTRUCTION CORPORATION (0.00)
KHONSU ENTERPRISE LLC (0.36)
H & H CONCRETE ON DEMAND INC (0.56)
Contract #02213201
Totals209999113.369957485.0430579296.1714.5

page 1 | page 2