Monthly State Let Construction Report For Wichita Falls District As Of Aug 23, 2019 Page 1 Of 3

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWILBARGER ETC
HighwayUS 287 ETC
FromHARDEMAN COUNTY LINE
ToPEASE RIVER
CSJ0043-05-108
Proj IDNH 2019(735)
Work TypeREHABILITATION OF EXISTING ROAD
 
36.0006884724.000.000.0
Work Order06-04-19
Work Began00-00-00
Work Completed
Time Computed07-04-19
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-05-108
BARRICADES UNLIMITED (0.44)
DUSTROL, INC. (3.40)
STRIPE-A-ZONE, INC. (2.80)
SAENZ TRANSPORT, LLC (0.12)
JENNINGS TRUCKING SERVICE, INC. (0.06)
ROCK HARD TRUCKING LLC (0.00)
COTHRAN TRUCKING, LLC (0.00)
Contract #04193014
Totals6884724.000.000.000.0

CountyWILBARGER
HighwayUS 70
FromUS 287
ToLAURIE ST
CSJ0043-05-109
Proj IDNH 1802(485)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.801617244.500.000.0
CountyWILBARGER
HighwayBU 287F
FromUS 70
To0.100 MI S OF US 70
CSJ0043-20-021
Proj IDSTP 2019(412)HES
Work TypeHAZARD ELIMINATION SAFETY
 
0.100122270.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-25-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-05-109
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03193031
Totals739514.500.000.000.0

CountyWILBARGER ETC
HighwayUS 70 ETC
FromUS 287
ToLAURIE STREET
CSJ0043-05-110
Proj IDSTP 1902(143)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
54.1048701328.890.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days263
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-05-110
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193007
Totals8701328.890.000.000.0

CountyWILBARGER
HighwayUS 70
FromAT BNSF RAILROAD & DUGAN CREEK (SB)
To.
CSJ0043-06-088
Proj IDNH 2018(823)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.966388039.500.000.0
CountyWILBARGER
HighwayUS 70
From0.731 MI W OF SL 404
To0.245 MI E OF SL 404
CSJ0043-06-092
Proj IDSTP 1802(257)HES
Work TypeHAZARD ELIMINATION SAFETY
 
0.9761305665.000.000.0
Work Order12-21-18
Work Began00-00-00
Work Completed
Time Computed01-20-19
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-06-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183050
Totals1693704.500.000.000.0

CountyWILBARGER
HighwayUS 287
FromFM 1763
ToSH 240
CSJ0043-07-111
Proj IDSTP 1802(315)HES
Work TypeHAZARD ELIMINATION SAFETY
 
4.410524560.00523297.5499.9
Work Order08-17-18
Work Began11-08-18
Work Completed
Time Computed09-16-18
Contract Working Days68
Addl Days Granted0
Working Days Charged127
Percent Time Used186
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-07-111
FALLS CONCRETE, LLC (18.12)
COMEN ENTERPRISE LLC (15.50)
COMEN ENTERPRISE LLC (15.50)
FHL CONSTRUCTION GROUP LLC (7.38)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.37)
Contract #07183026
Totals524560.0076872.00523297.5499.9

CountyWICHITA
HighwayUS 287
FromNEAR BURNETT RANCH ROAD
To0.45 MI WEST OF JOHNSON ROAD
CSJ0043-08-075
Proj IDNH 1802(303)
Work TypeHAZARD ELIMINATION SAFETY
 
9.2792014723.351873135.2593.8
Work Order09-18-18
Work Began11-27-18
Work Completed
Time Computed10-18-18
Contract Working Days85
Addl Days Granted0
Working Days Charged107
Percent Time Used125
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-08-075
WOLFE CONSTRUCTION GROUP, INC. (1.07)
DIIBS SPECIALISTS (12.14)
TOTAL HIGHWAY MAINTENANCE, LLC (0.37)
Contract #08183027
Totals2014723.354308.751873135.2593.8

CountyWICHITA ETC
HighwayUS 287 ETC
From0.350 MI W OF FM 1739
To0.450 MI E OF 1739
CSJ0043-08-076
Proj IDSTP 2019(305)HES
Work TypeROADWAY ILLUMINATION UPGRADE
 
4.9671090136.6074280.776.8
Work Order02-20-19
Work Began00-00-00
Work Completed
Time Computed05-21-19
Contract Working Days109
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0043-08-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01193225
Totals1090136.6074280.7774280.776.8

CountyWICHITA
HighwayIH 44
From7TH STREET
To6TH STREET (EB FRONTAGE ROAD)
CSJ0043-09-135
Proj IDC 43-9-135
Work TypeREHABILITATION OF EXISTING ROAD
 
12.8607918746.451957211.9324.7
CountyWICHITA
HighwayIH 44
FromEAST RD
ToSH 240
CSJ0156-07-112
Proj IDC 156-7-112
Work TypeHAZARD ELIMINATION SAFETY
 
4.601912838.92301126.0032.9
Work Order07-17-18
Work Began10-02-18
Work Completed
Time Computed08-16-18
Contract Working Days119
Addl Days Granted0
Working Days Charged121
Percent Time Used101
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-135
HJC FARMS, INC. (25.83)
STRIPE-A-ZONE, INC. (1.74)
DUSTROL, INC. (5.98)
O. TREVINO CONSTRUCTION, LLC (0.87)
XROADS, L.P. (0.38)
BRENDA PRICE TRUCKING (0.04)
CHEROKEE SERVICES (0.50)
Contract #06183246
Totals8831585.37393672.462258337.9325.5

CountyWICHITA ETC
HighwayUS 287 ETC
FromEAST OF SPUR 325 ON RAMP
ToIH 44
CSJ0043-09-137
Proj IDNH 2019(331)
Work TypeREHABILITATION OF EXISTING ROAD
 
20.4646221093.620.000.0
Work Order02-20-19
Work Began00-00-00
Work Completed
Time Computed03-22-19
Contract Working Days128
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01193009
Totals6221093.620.000.000.0

CountyWICHITA ETC
HighwayBU 287J ETC
FromFM 1814
ToIH 44
CSJ0043-17-032
Proj IDSTP 1902(337)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
135.800761013.130.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-17-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193039
Totals761013.130.000.000.0

CountyCLAY
HighwayUS 82 ETC
FromUS 82 EASTBOUND AT DUCK CREEK
To.
CSJ0044-02-079
Proj IDBR 2016(355)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
24.6745938095.157598938.4899.9
Work Order03-31-16
Work Began06-05-17
Work Completed
Time Computed05-01-16
Contract Working Days197
Addl Days Granted54
Working Days Charged346
Percent Time Used137
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-02-079
W.S. CONSTRUCTION COMPANY (15.01)
COTHRAN TRUCKING, LLC (0.95)
WOLFE CONSTRUCTION GROUP, INC. (0.42)
DUSTROL, INC. (17.02)
HALL BROTHERS, INC. (7.12)
DUSTIN ALLEN, INC. (5.40)
TOTAL HIGHWAY MAINTENANCE, LLC (1.83)
ALTUS TRAFFIC MANAGEMENT LLC (0.47)
Contract #01163022
Totals5938095.15168125.007598938.4899.9

CountyMONTAGUE
HighwayUS 82
FromWCL OF SAINT JO
ToECL OF SAINT JO
CSJ0044-06-075
Proj IDNH 2019(956)
Work TypeOVERLAY
 
12.8344024790.810.000.0
Work Order06-17-19
Work Began00-00-00
Work Completed
Time Computed07-17-19
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-06-075
XROADS, L.P. (0.47)
DUSTROL, INC. (5.92)
LANCO TURF & SEEDING, INC. (0.01)
SOUTHERN CROSS CONTRACTORS, LLC (0.78)
TOTAL HIGHWAY MAINTENANCE, LLC (3.71)
MARCOM"S MOWING SERVICE, LLC (4.41)
Contract #05193223
Totals4024790.810.000.000.0

CountyCOOKE
HighwayUS 82
FromWCL OF MUENSTER
ToECL OF MUENSTER
CSJ0044-07-071
Proj IDNH 2019(217)
Work TypeOVERLAY
 
14.0714475654.574125999.8692.1
Work Order12-17-18
Work Began03-20-19
Work Completed
Time Computed01-16-19
Contract Working Days102
Addl Days Granted0
Working Days Charged57
Percent Time Used55
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-07-071
PEACHTREE CONSTRUCTION, LTD. (13.03)
XROADS, L.P. (0.60)
SOUTHERN CROSS CONTRACTORS, LLC (9.25)
TRP CONSTRUCTION GROUP, LLC (2.93)
DUSTROL, INC. (6.54)
Contract #11183226
Totals4475654.571370190.454125999.8692.1

CountyWICHITA ETC
HighwayBU 287J ETC
FromSP 213
ToCLAY COUNTY LINE
CSJ0044-11-002
Proj IDNH 2019(219)
Work TypeSEAL COAT
 
248.6978903751.772115394.7323.7
Work Order01-22-19
Work Began00-00-00
Work Completed
Time Computed05-01-19
Contract Working Days62
Addl Days Granted0
Working Days Charged35
Percent Time Used56
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0044-11-002
FLAT LINE, INC. (19.25)
RED SIXTEEN CONSTRUCTION, INC (1.57)
Contract #11183229
Totals8903751.770.002115394.7323.7

CountyWILBARGER
HighwayUS 183
FromTEXAS STREET
ToBU 287F
CSJ0124-03-062
Proj IDSTP 1902(047)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
0.12998020.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-17-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0124-03-062
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193214
Totals98020.000.000.000.0

CountyBAYLOR
HighwayUS 183
FromWICHITA RIVER
ToUS 82
CSJ0124-05-029
Proj IDC 124-5-29
Work TypeREHABILITATION OF EXISTING ROAD
 
12.5926052095.585788196.9796.4
Work Order07-25-18
Work Began09-12-18
Work Completed
Time Computed08-24-19
Contract Working Days165
Addl Days Granted10
Working Days Charged216
Percent Time Used123
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0124-05-029
CONTRACTORS SERVICE COMPANY (0.32)
A. L. CONSTRUCTION, LLC (4.46)
BARRICADES UNLIMITED (1.16)
HJC FARMS, INC. (2.64)
LANCO TURF & SEEDING, INC. (2.19)
WEST TEXAS ROCK RESOURCES, LLC (0.16)
W.S. CONSTRUCTION COMPANY (3.38)
FOUTSCO PAVING COMPANY, LLC (2.14)
DUININCK, INC. (29.15)
Contract #06183213
Totals6052095.58355946.085788196.9796.4

CountyTHROCKMORTON
HighwayUS 183
FromNORTH CITY LIMITS OF THROCKMORTON
ToCOLLEGE STREET
CSJ0125-02-033
Proj IDSTP 2018(350)
Work TypeOVERLAY
 
8.3251743252.561749124.8099.9
Work Order01-10-18
Work Began04-11-18
Work Completed
Time Computed02-09-18
Contract Working Days48
Addl Days Granted0
Working Days Charged54
Percent Time Used112
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0125-02-033
TEXAS ALTERNATIVE GRASSER, INC. (0.17)
BARRICADES UNLIMITED (2.98)
RONALD R. WAGNER & CO., LP (17.58)
CONTRACTORS SERVICE COMPANY (0.30)
A. L. HELMCAMP, INC. (0.10)
Contract #12173217
Totals1743252.56432992.771749124.8099.9

CountyARCHER
HighwaySH 114
FromBAYLOR COUNTY LINE
To0.7 MI E OF FM 210
CSJ0133-07-029
Proj IDNH 2019(736)
Work TypeOVERLAY
 
28.1007554037.740.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged15
Percent Time Used14
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0133-07-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193219
Totals7554037.740.000.000.0

CountyYOUNG
HighwayUS 380
FromFM 2179
ToJACK COUNTY LINE
CSJ0134-03-032
Proj IDSTP 2019(439)
Work TypeREHABILITATION OF EXISTING ROAD
 
8.6742678507.132692975.5799.9
Work Order02-20-19
Work Began05-30-19
Work Completed
Time Computed03-22-19
Contract Working Days54
Addl Days Granted1
Working Days Charged32
Percent Time Used58
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0134-03-032
XROADS, L.P. (0.37)
TOTAL HIGHWAY MAINTENANCE, LLC (2.36)
WEST TEXAS ROCK RESOURCES, LLC (0.40)
Contract #01193241
Totals2678507.13349874.112692975.5799.9

CountyCLAY
HighwayFM 174
From0.965 MI EAST OF SH 148
To1.965 MI EAST OF SH 148
CSJ0137-10-022
Proj IDSTP 2019(504)HES
Work TypeWIDEN NON-FREEWAY
 
1.0001019002.46358120.4735.1
CountyCLAY
HighwayFM 174
FromSH 148
ToFM 3077
CSJ0137-10-024
Proj IDC 137-10-24
Work TypeREHABILITATION OF EXISTING ROAD
 
3.4541309201.72223338.2517.0
Work Order03-18-19
Work Began04-25-19
Work Completed
Time Computed04-17-19
Contract Working Days170
Addl Days Granted0
Working Days Charged51
Percent Time Used30
Contractor(s)
BLYTHE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0137-10-022
ALTUS TRAFFIC MANAGEMENT LLC (0.72)
LUZ LERMA CONSTRUCTION, INC. (21.30)
BARRICADES UNLIMITED (1.17)
APEX HIGHWAY SERVICES, LLC (0.28)
WOLFE CONSTRUCTION GROUP, INC. (2.91)
MARCOM"S MOWING SERVICE, LLC (0.88)
Contract #02193020
Totals2328204.18201310.95581458.7224.9

page 1 | page 2 | page 3