Monthly State Let Maintenance Report For Wichita Falls District As Of Nov 13, 2018 Page 1 Of 1

Last Update: Tuesday, November 13, 2018
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWICHITA
HighwayIH0044
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6318-41-001
Proj IDRMC - 631841001
Work TypeDW ONCALL GRDRAIL/CABLE BARRIER REPAIR
 
0.0011038100.001206763.5599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged426
Percent Time Used58
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174011
Totals1038100.0049575.601206763.5599.9

CountyYOUNG
HighwayUS0380
FromFM 926 INTERSECTION IN NEWCASTLE
ToJACK COUNTY LINE
CSJ6319-45-001
Proj IDRMC - 631945001
Work TypeGUARDRAIL UPGRADE
 
0.001339981.00347053.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-04-18
Work Completed11-08-18
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged54
Percent Time Used98
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-45-001
VELASQUEZ CONCRETE (9.97)
Contract #03184201
Totals339981.0084.00347053.00100.0

CountyWICHITA
HighwayFM0368
From.716 MI SOUTH OF FM 1206
To1.329 MI SOUTH OF FM 1206
CSJ6320-20-001
Proj IDRMC - 632020001
Work TypeEROSION/DRAINAGE REPAIR
 
0.001578952.30571514.8798.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-16-18
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged45
Percent Time Used100
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6320-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174215
Totals578952.300.00571514.8798.7

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS IN WICHITA
ToWILBARGER, YOUNG & COOKE COUNTY
CSJ6322-09-001
Proj IDBPM - 632209001
Work TypeBRIDGE MAINTENANCE
 
0.001786175.00799772.4599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-12-18
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged124
Percent Time Used124
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6322-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174203
Totals786175.000.00799772.4599.9

CountyARCHER
HighwayUS0082
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6324-00-001
Proj IDRMC - 632400001
Work TypeROUTINE STREET SWEEPING
 
0.001590931.00169761.5028.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged245
Percent Time Used67
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6324-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174014
Totals590931.0018213.50169761.5028.7

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS IN COOKE CLAY
ToMONTAGUE WICHITA & WILBARGER COUNTY
CSJ6325-72-001
Proj IDRMC - 632572001
Work TypeDEBRIS REMOMVAL
 
0.001517830.00449310.0086.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-18
Work Completed
Time Computed00-00-00
Contract Working Days275
Addl Days Granted275
Working Days Charged245
Percent Time Used44
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6325-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184001
Totals517830.0050265.00449310.0086.7

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS IN CLAY, COOKE
ToMONTAGUE, WICHITA & WILBARGER COUNTY
CSJ6327-63-001
Proj IDRMC - 632763001
Work TypeONCALL CONCRETE PAVEMENT REPAIR
 
0.001777111.00670945.8986.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged149
Percent Time Used40
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184202
Totals777111.000.00670945.8986.3

CountyWICHITA
HighwayFM0367
FromRM 474+1.275
ToRM 486+.073
CSJ6328-05-001
Proj IDRMC - 632805001
Work TypeGUARDRAIL UPGRADE
 
0.001344345.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6328-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184004
Totals344345.500.000.000.0

CountyCOOKE
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToCOOKE AND CLAY COUNTY
CSJ6329-67-001
Proj IDRMC - 632967001
Work TypeCULVERT REPLACEMENT
 
0.001515403.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-12-18
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TALBRAN ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6329-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184005
Totals515403.600.000.000.0

CountyCLAY
HighwayFM0175
FromVARIOUS LOCATIONS IN CLAY
ToARCHER BAYLOR & THROCKMORTON CO
CSJ6329-68-001
Proj IDRMC - 632968001
Work TypeCULVERT REPAIR
 
0.001579763.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10184003
Totals579763.000.000.000.0

CountyWICHITA
HighwayUS0082
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6331-68-001
Proj IDRMC - 633168001
Work TypeDW ONCALL STRIPING
 
0.001781010.0014934.761.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6331-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184216
Totals781010.0014934.7614934.761.9

CountyYOUNG
HighwaySH0114
FromVARIOUS ROADWAYS IN
ToYOUNG & THROCKMORTON COUNTY
CSJ6333-99-001
Proj IDRMC - 633399001
Work TypeTREE TRIMMING & BRUSH REMOVAL
 
0.001332766.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6333-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10184201
Totals332766.000.000.000.0

CountyCOOKE
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToCOOKE AND MONTAGUE COUNTY
CSJ6335-42-001
Proj IDBPM - 633542001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.001661891.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6335-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10184202
Totals661891.500.000.000.0

CountyWICHITA
HighwayUS0082
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6335-50-001
Proj IDRMC - 633550001
Work TypeCRACK SEALING - HOT POUR
 
0.001588195.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-05-18
Work Completed
Time Computed00-00-00
Contract Working Days65
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6335-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09184017
Totals588195.150.000.000.0

page 1