Monthly State Let Maintenance Report For Wichita Falls District As Of Jun 08, 2018 Page 1 Of 1

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWICHITA
HighwayIH0044
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6318-41-001
Proj IDRMC - 631841001
Work TypeDW ONCALL GRDRAIL/CABLE BARRIER REPAIR
 
0.0011038100.00776977.2574.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174011
Totals1038100.0081210.00776977.2574.8

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6318-68-001
Proj IDRMC - 631868001
Work TypeTRUCK MOUNTED ATTENUATORS (TMA)
 
0.001384890.00130617.6933.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6318-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174203
Totals384890.0038908.88130617.6933.9

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6318-84-001
Proj IDRMC - 631884001
Work TypeONCALL STRIPING & RPM
 
0.0011010918.00408588.8740.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged271
Percent Time Used74
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6318-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174002
Totals1010918.0051311.95408588.8740.6

CountyCLAY
HighwaySS0510
FromSP 510 UNDERPASS
ToUNDER RR
CSJ6318-92-001
Proj IDRMC - 631892001
Work TypeDRAINAGE IMPORVEMENT
 
0.001227990.00376326.3999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-18
Work Completed
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged46
Percent Time Used88
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-92-001
DRS CONSTRUCTION, INC. (0.00)
Contract #10174202
Totals227990.000.00376326.3999.9

CountyYOUNG
HighwayUS0380
FromFM 926 INTERSECTION IN NEWCASTLE
ToJACK COUNTY LINE
CSJ6319-45-001
Proj IDRMC - 631945001
Work TypeGUARDRAIL UPGRADE
 
0.001339981.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-04-18
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03184201
Totals339981.000.000.000.0

CountyWICHITA
HighwayFM0368
From.716 MI SOUTH OF FM 1206
To1.329 MI SOUTH OF FM 1206
CSJ6320-20-001
Proj IDRMC - 632020001
Work TypeEROSION/DRAINAGE REPAIR
 
0.001578952.30569954.8798.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-16-18
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged45
Percent Time Used100
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6320-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174215
Totals578952.30158480.74569954.8798.4

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS IN WICHITA
ToWILBARGER, YOUNG & COOKE COUNTY
CSJ6322-09-001
Proj IDBPM - 632209001
Work TypeBRIDGE MAINTENANCE
 
0.001786175.00371121.9047.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-12-18
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged62
Percent Time Used62
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6322-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174203
Totals786175.0082034.25371121.9047.2

CountyARCHER
HighwayUS0082
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6324-00-001
Proj IDRMC - 632400001
Work TypeROUTINE STREET SWEEPING
 
0.001590931.00110631.5018.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6324-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174014
Totals590931.0016607.50110631.5018.7

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS IN COOKE CLAY
ToMONTAGUE WICHITA & WILBARGER COUNTY
CSJ6325-72-001
Proj IDRMC - 632572001
Work TypeDEBRIS REMOMVAL
 
0.001517830.00137615.0026.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-18
Work Completed
Time Computed00-00-00
Contract Working Days275
Addl Days Granted0
Working Days Charged92
Percent Time Used33
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6325-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184001
Totals517830.0061485.00137615.0026.5

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS IN CLAY, COOKE
ToMONTAGUE, WICHITA & WILBARGER COUNTY
CSJ6327-63-001
Proj IDRMC - 632763001
Work TypeONCALL CONCRETE PAVEMENT REPAIR
 
0.001777111.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184202
Totals777111.000.000.000.0

page 1