Monthly State Let Maintenance Report For Wichita Falls District As Of Feb 09, 2018 Page 1 Of 1

Last Update: Friday, February 09, 2018
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWICHITA
HighwayUS0082
FromVARIOUSE BRIDGES IN COOKE
ToWICHITA & YOUNG COUNTY
CSJ6304-34-001
Proj IDBPM - 630434001
Work TypeBRIDGE MAINTENANCE
 
0.001589293.70584150.6999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged109
Percent Time Used145
Contractor(s)
RESTEK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174201
Totals589293.701500.00584150.6999.9

CountyCOOKE
HighwayIH0035
FromVARIOUS ROADWAYS IN
ToCOOKE AND MONTAGUE COUNTY
CSJ6308-65-001
Proj IDRMC - 630865001
Work TypeROUTINE STREET SWEEPING
 
0.001288904.00267104.0092.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-28-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged246
Percent Time Used67
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6308-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164202
Totals288904.0062492.00267104.0092.4

CountyWICHITA
HighwayIH0044
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6318-41-001
Proj IDRMC - 631841001
Work TypeDW ONCALL GRDRAIL/CABLE BARRIER REPAIR
 
0.0011038100.00492040.0047.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174011
Totals1038100.00163378.50492040.0047.3

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6318-68-001
Proj IDRMC - 631868001
Work TypeTRUCK MOUNTED ATTENUATORS (TMA)
 
0.001384890.0047516.4312.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6318-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174203
Totals384890.0012981.2947516.4312.3

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6318-84-001
Proj IDRMC - 631884001
Work TypeONCALL STRIPING & RPM
 
0.0011010918.00246513.8724.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6318-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174002
Totals1010918.0053312.60246513.8724.5

CountyCLAY
HighwaySS0510
FromSP 510 UNDERPASS
ToUNDER RR
CSJ6318-92-001
Proj IDRMC - 631892001
Work TypeDRAINAGE IMPORVEMENT
 
0.001227990.00168306.6673.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-18
Work Completed
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged16
Percent Time Used30
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-92-001
DRS CONSTRUCTION, INC. (0.00)
Contract #10174202
Totals227990.00168306.66168306.6673.8

CountyWICHITA
HighwayFM0368
From.716 MI SOUTH OF FM 1206
To1.329 MI SOUTH OF FM 1206
CSJ6320-20-001
Proj IDRMC - 632020001
Work TypeEROSION/DRAINAGE REPAIR
 
0.001578952.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6320-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174215
Totals578952.300.000.000.0

CountyCOOKE
HighwayFM1630
FromVARIOUS LOCATIONS IN COOKE CLAY
ToMONTAGUE WICHITA & WILBARGER COUNTY
CSJ6321-72-001
Proj IDRMC - 632172001
Work TypeCRACK SEAL - HOT POUR RUBBER
 
0.001252205.0079545.0031.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-11-17
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged17
Percent Time Used38
Contractor(s)
SELECT STRIPING LLC
SUBCONTRACTOR(S) FOR CCSJ: 6321-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174010
Totals252205.0050425.0079545.0031.5

CountyARCHER
HighwaySH0079
FromVARIOUS LOCATION IN ARCHER BAYLOR
ToCLAY THROCKMORTON & YOUNG COUNTY
CSJ6321-73-001
Proj IDRMC - 632173001
Work TypeCRACK SEAL - HOT POUR RUBBER
 
0.001226758.7424078.6010.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-03-18
Work Completed
Time Computed00-00-00
Contract Working Days37
Addl Days Granted0
Working Days Charged3
Percent Time Used8
Contractor(s)
BRIGGS BROTHERS ENTERPRISES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6321-73-001
SETT CONSTRUCTION (54.00)
Contract #09174001
Totals226758.7424078.6024078.6010.6

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS IN WICHITA
ToWILBARGER, YOUNG & COOKE COUNTY
CSJ6322-09-001
Proj IDBPM - 632209001
Work TypeBRIDGE MAINTENANCE
 
0.001786175.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6322-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174203
Totals786175.000.000.000.0

CountyARCHER
HighwayUS0082
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6324-00-001
Proj IDRMC - 632400001
Work TypeROUTINE STREET SWEEPING
 
0.001590931.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6324-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174014
Totals590931.000.000.000.0

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS IN COOKE CLAY
ToMONTAGUE WICHITA & WILBARGER COUNTY
CSJ6325-72-001
Proj IDRMC - 632572001
Work TypeDEBRIS REMOMVAL
 
0.001517830.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days275
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6325-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184001
Totals517830.000.000.000.0

CountyWICHITA
HighwayUS0082
FromVARIOUS LOCATIONS IN CLAY, COOKE
ToMONTAGUE, WICHITA & WILBARGER COUNTY
CSJ6327-63-001
Proj IDRMC - 632763001
Work TypeONCALL CONCRETE PAVEMENT REPAIR
 
0.001777111.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184202
Totals777111.000.000.000.0

page 1