Monthly State Let Construction Report For Yoakum District As Of Nov 12, 2021 Page 1 Of 7

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGONZALES
HighwayUA 90
FromAT SAN MARCOS RIVER, REL #1 & REL #2
ToSTR # 0026-06-050, -051 & -052
CSJ0025-06-056
Proj IDBR 2020(848)
Work TypeBRIDGE MAINTENANCE
 
0.3331505690.001519634.5299.9
CountyGONZALES
HighwayFM 2091
FromAT S. MARCOS REL,S. MARCOS,WICKSON
ToSTR # 2080-01-004, -005 & -006
CSJ2080-01-009
Proj IDBR 2020(848)
Work TypeBRIDGE MAINTENANCE
 
0.3761098083.77299656.8027.2
Work Order07-20-20
Work Began07-14-21
Work Completed
Time Computed10-18-20
Contract Working Days138
Addl Days Granted0
Working Days Charged92
Percent Time Used66
Contractor(s)
OLYMPUS PAINTING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-06-056
DIIBS SPECIALISTS, LLC (12.68)
TEX OP CONSTRUCTION, LP (0.30)
D. I. J. CONSTRUCTION, INC. (1.28)
ELITECURB & CONCRETE, LLC (16.37)
Contract #05203223
Totals2603773.77464308.021819291.3269.8

CountyGONZALES
HighwayUS 90
From0.013 MI W OF FM 1680
To0.01 MI W OF FAYETTE C/L
CSJ0026-01-027
Proj IDSTP 2018(604)
Work TypePAVEMENT REPAIR AND RESURFACING
 
6.4762613600.862755132.5899.9
Work Order04-18-18
Work Began06-26-18
Work Completed
Time Computed06-01-18
Contract Working Days135
Addl Days Granted9
Working Days Charged158
Percent Time Used109
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-01-027
ROADWAY SPECIALTIES, INC. (0.85)
CHEROKEE SERVICES (1.21)
FLASHER LIMITED (0.35)
TRP CONSTRUCTION GROUP, LLC (4.02)
UNDER CONSTRUCTION INC. (1.79)
PENHALL COMPANY (0.25)
Contract #03183221
Totals2613600.860.002755132.5899.9

CountyFAYETTE
HighwayUS 90
From0.12 MILES WEST OF SH 95
ToELM ST IN CITY OF FLATONIA
CSJ0026-02-034
Proj IDSTP 2021(586)
Work TypeRESTORATION
 
0.8072724321.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-04-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-02-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213018
Totals2724321.520.000.000.0

CountyFAYETTE
HighwayUS 90
FromAT FM 1295
To.
CSJ0026-02-035
Proj IDSTP 2020(914)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20047198.6444214.8493.6
CountyFAYETTE
HighwayFM 609
FromAT BLANKENBURG LANE
To.
CSJ0267-03-031
Proj IDSTP 2020(914)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20027685.0233951.3499.9
CountyVICTORIA
HighwayFM 1686
FromAT US 59/BU 59-T
To.
CSJ1132-01-032
Proj IDSTP 2020(914)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.13546595.9246442.1299.6
CountyWHARTON
HighwayFM 1160
FromAT FM 1300 W
To.
CSJ1302-01-026
Proj IDSTP 2020(914)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20019295.8420960.8199.9
Work Order08-03-20
Work Began04-05-21
Work Completed
Time Computed11-01-20
Contract Working Days45
Addl Days Granted0
Working Days Charged30
Percent Time Used66
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0026-02-035
STRIPE LINES, INC. (3.90)
Contract #06203039
Totals140775.420.00145569.1199.9

CountyFAYETTE ETC
HighwayUS 90 ETC
FromELM STREET
ToBRYANT RD
CSJ0026-02-036
Proj IDSTP 2021(113)
Work TypeSEAL COAT
 
334.97014992945.9412772307.6685.1
Work Order12-11-20
Work Began05-13-21
Work Completed
Time Computed06-01-21
Contract Working Days75
Addl Days Granted0
Working Days Charged66
Percent Time Used88
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0026-02-036
FLASHER EQUIPMENT COMPANY (1.52)
VIZCAINO, L.P. (19.34)
Contract #11203206
Totals14992945.94635620.3012772307.6685.1

CountyFAYETTE
HighwayUS 90
FromAT MIDDLE CREEK
ToSTR # 0026-03-028
CSJ0026-03-042
Proj IDBR 2017(318)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.288831842.19814791.3299.9
Work Order01-10-17
Work Began03-03-17
Work Completed
Time Computed04-10-17
Contract Working Days60
Addl Days Granted0
Working Days Charged121
Percent Time Used201
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-042
DELGADO"S CONSTRUCTION (60.07)
EGGEMEYER LAND CLEARING, LLC (2.87)
ROADWAY SPECIALTIES, INC. (3.88)
FLASHER EQUIPMENT COMPANY (0.39)
PAVEMENT MARKINGS INC. (0.94)
Contract #12163022
Totals831842.190.00814791.3299.9

CountyCOLORADO ETC
HighwayUS 90 ETC
FromFM 806
To0.056 MI W OF FRONT ST.
CSJ0026-06-035
Proj IDF 2022(093)
Work TypeSEAL COAT
 
314.60116624783.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213201
Totals16624783.200.000.000.0

CountyCOLORADO
HighwayUS 90
FromAT COLORADO RIVER BRIDGE
ToSTR # 0027-01-001
CSJ0027-01-044
Proj IDBR 2019(850)
Work TypeBRIDGE REPLACEMENT
 
0.3648244674.888837756.4199.9
Work Order06-13-19
Work Began08-05-19
Work Completed
Time Computed08-05-19
Contract Working Days405
Addl Days Granted0
Working Days Charged133
Percent Time Used32
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0027-01-044
SEMPER STRIPING LLC (0.02)
HB FARMER FOUNDATION, LLC (12.51)
MCL CONTRACTING, LLC (0.81)
DORAN STEEL, INC. (0.93)
A1 EROSION CONTROL (0.37)
CHOCTAW ERECTORS, INC. (8.27)
WILLOW CITY SIGN & RAIL, INC. (1.56)
GMJ PAVING CO. (2.99)
DORAN STEEL, INC. (0.54)
EAST - TEX PIPE AND FAB LLC (0.56)
Contract #05193010
Totals8244674.882409596.558837756.4199.9

CountyCOLORADO
HighwayUS 90A
FromFM 102 IN EAGLE LAKE
ToWHARTON COUNTY LINE
CSJ0027-03-071
Proj IDSTP 1702(426)
Work TypeCONSTRUCT SUPER 2 LANES
 
5.0284487326.994851429.9999.9
Work Order08-11-17
Work Began10-25-17
Work Completed
Time Computed11-09-17
Contract Working Days160
Addl Days Granted0
Working Days Charged159
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0027-03-071
AREA WIDE PROTECTIVE, INC. (0.26)
D. I. J. CONSTRUCTION, INC. (1.88)
D&S TEXAS ICON CONSTRUCTION (0.35)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.27)
RIOS TRUCKING CO. (1.40)
STRIPE-A-ZONE, INC. (0.27)
Contract #06173243
Totals4487326.990.004851429.9999.9

CountyCOLORADO ETC
HighwayFM 102 ETC
FromDOWNTOWN EAGLE LAKE
ToUS 90A
CSJ0027-03-073
Proj IDSTP 2020(052)
Work TypeOVERLAY
 
12.3403987940.974004276.9299.9
Work Order04-07-20
Work Began07-06-20
Work Completed
Time Computed04-23-20
Contract Working Days120
Addl Days Granted0
Working Days Charged108
Percent Time Used90
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0027-03-073
STRIPE LINES, INC. (4.36)
CAPSTONE TRUCKING (0.00)
A.J.J.A . TRUCKING, INC. (0.00)
Contract #09193006
Totals3987940.970.004004276.9299.9

CountyWHARTON
HighwayUA 90
From2.58 MI W OF FM 1164
ToSH 60
CSJ0027-04-041
Proj IDSTP 1902(164)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7.341496857.15542953.7999.9
CountyWHARTON
HighwayFM 640
FromFM 1161
ToFM 102
CSJ1260-03-013
Proj IDSTP 1902(168)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.014527561.27458038.6186.8
CountyWHARTON
HighwayFM 1161
FromFM 102
ToSH 60
CSJ1303-01-018
Proj IDSTP 1902(168)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.3991138794.901045769.9891.8
CountyMATAGORDA
HighwayFM 2540
FromSH 35
ToFM 457
CSJ2525-01-017
Proj IDSTP 1902(168)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.301448295.64373640.1883.3
Work Order10-21-19
Work Began11-20-19
Work Completed
Time Computed01-19-20
Contract Working Days210
Addl Days Granted0
Working Days Charged303
Percent Time Used144
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0027-04-041
A K FUQUAY CONSTRUCTION (2.24)
AREA WIDE PROTECTIVE, INC. (0.98)
RUCOBA & MAYA CONSTRUCTION, LLC (62.13)
TRAFFIC SIGNS & LINES, LLC (1.76)
Contract #09193204
Totals2611508.96418.752420402.5695.4

CountyWHARTON ETC
HighwayUS 90A ETC
FromCOLORADO C/L
ToSH 60
CSJ0027-04-042
Proj IDSTP 2021(545)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
30.9503775419.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-29-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0027-04-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213232
Totals3775419.000.000.000.0

CountyVICTORIA
HighwayUS 59
FromBU 59T
ToGOLIAD C/L
CSJ0088-04-070
Proj IDNH 2018(158)
Work TypeACP OVERLAY
 
6.1794506272.524551759.2799.9
Work Order05-17-18
Work Began12-03-18
Work Completed
Time Computed06-17-18
Contract Working Days75
Addl Days Granted11
Working Days Charged85
Percent Time Used98
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-04-070
HIGHWAY BARRICADES AND SERVICES, LLC (3.91)
INTERSTATE BARRICADES & MARKINGS, INC. (0.16)
WEST TEXAS ROCK RESOURCES, LLC (0.24)
Contract #04183231
Totals4506272.520.004551759.2799.9

CountyVICTORIA
HighwayUS 59
From0.5 MI S OF FM 1686
ToSL 463
CSJ0088-05-085
Proj IDC 88-5-85
Work TypeCONSTRUCT FRONTAGE ROADS
 
2.76927884764.5026380145.1494.6
CountyVICTORIA
HighwayUS 59
From0.5 MI S OF FM 1686
ToSL 463
CSJ0088-05-099
Proj IDROW 88-5-99
Work TypeUTILITY ONLY
 
3.329708858.20655277.2092.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-19-18
Work Began09-17-18
Work Completed
Time Computed00-00-00
Contract Working Days600
Addl Days Granted49
Working Days Charged620
Percent Time Used95
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-085
AREA WIDE PROTECTIVE, INC. (0.02)
THIRD COAST SERVICES LLC (5.43)
ANGEL BROTHERS HOLDINGS CORP. (28.20)
ADCOCK 4 INVESTMENTS, LLC (4.34)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.59)
TITO"S TRUCKING & SONS, LLC (0.00)
ROADWAY SPECIALTIES, INC. (1.60)
INSITUFORM TECHNOLOGIES, LLC (0.68)
MVA CONSTRUCTION LLC (0.00)
AIMS COMPANIES (0.03)
BORTUNCO (0.22)
FARR FOUNDATION, INC. (0.30)
HIGHWAY BARRICADES AND SERVICES, LLC (0.40)
MONTALVO BRIDGE SYSTEMS, LLC (0.11)
DUSTROL, INC. (1.14)
WEBER-BALKE FOUNDATION COMPANY, INC (0.40)
CURB PLANET INC. (0.00)
AARON CONCRETE CONTRACTORS, L.P. (1.52)
ROYAL REBAR (0.00)
Contract #05183003
Totals28593622.70753418.0827035422.3494.5

CountyVICTORIA
HighwayUS 59
FromLP 463
ToSPUR 91
CSJ0088-05-091
Proj IDNH 2018(506)
Work TypeACP OVERLAY
 
10.5889267866.6610210635.6499.9
Work Order03-15-18
Work Began06-10-19
Work Completed
Time Computed04-15-18
Contract Working Days165
Addl Days Granted20
Working Days Charged203
Percent Time Used109
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-091
AREA WIDE PROTECTIVE, INC. (0.09)
STRIPE-A-ZONE, INC. (0.36)
CHEROKEE SERVICES (3.28)
HIGHWAY BARRICADES AND SERVICES, LLC (4.79)
Contract #02183235
Totals9267866.662129.0110210635.6499.9

CountyVICTORIA
HighwayUS 59
FromUS 87
ToSH 185
CSJ0088-05-098
Proj IDC 88-5-98
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
1.13613531313.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-098
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213214
Totals13531313.250.000.000.0

CountyVICTORIA
HighwayUS 59
From0.450 MILES SOUTH OF SH 185
To0.391 MILES NORTH OF FM 1686
CSJ0088-05-104
Proj IDNH 2020(988)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.9885347548.722991349.1755.9
CountyVICTORIA
HighwayUS 59
From0.391 MILES NORTH OF FM 1686
To1.337 MILES NORTH OF FM 1686
CSJ0089-01-092
Proj IDNH 2020(988)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.9451531039.55992732.7664.8
Work Order08-20-20
Work Began01-12-21
Work Completed
Time Computed11-20-20
Contract Working Days255
Addl Days Granted0
Working Days Charged48
Percent Time Used18
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-104
PRIMATE CONSTRUCTION, LP (0.10)
ROADWAY SPECIALTIES, INC. (7.27)
LONE STAR EROSION CONTROL (0.40)
HIGHWAY BARRICADES AND SERVICES, LLC (0.73)
LONESTAR TRAFFIC SAFETY, LLC (0.40)
FLASHER EQUIPMENT COMPANY (0.14)
Contract #07203207
Totals6878588.2712194.543984081.9357.9

CountyJACKSON
HighwayUS 59
FromSH 111
To0.5 MI NORTH OF LAVACA RIVER
CSJ0089-03-091
Proj IDNH 2020(114)
Work TypeOVERLAY
 
12.02312833114.2513486391.7899.9
Work Order11-20-19
Work Began01-13-20
Work Completed
Time Computed06-01-20
Contract Working Days165
Addl Days Granted0
Working Days Charged118
Percent Time Used71
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-03-091
A BROTHERS MILLING, LLC (2.88)
CPAVE, INC. (3.21)
FLASHER EQUIPMENT COMPANY (0.12)
WEST TEXAS ROCK RESOURCES, LLC (0.15)
HIGHWAY BARRICADES AND SERVICES, LLC (3.93)
Contract #10193007
Totals12833114.250.0013486391.7899.9

CountyWHARTON
HighwayUS 59
FromLP 524 N. OF HILLJE (NB LANES ONLY)
To0.130 MI.N.OF FM 647(NB LANES ONLY)
CSJ0089-06-088
Proj IDNH 1702(485)
Work TypeACP OVERLAY
 
17.2038161719.848604914.5299.9
Work Order08-16-17
Work Began01-08-18
Work Completed
Time Computed11-14-17
Contract Working Days84
Addl Days Granted98
Working Days Charged192
Percent Time Used105
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-088
BATTERSON,LLP (3.59)
DEVTEX INC. (2.18)
A BROTHERS MILLING, LLC (1.99)
WEST TEXAS RUMBLE STRIP (0.17)
Contract #07173210
Totals8161719.8411858.468604914.5299.9

CountyWHARTON
HighwayUS 59
FromFM 1163
ToLP 524 N. OF HILLJE
CSJ0089-06-090
Proj IDC 89-6-90
Work TypeACP OVERLAY
 
8.4497009733.697113209.5699.9
Work Order09-24-18
Work Began07-08-19
Work Completed
Time Computed04-01-19
Contract Working Days133
Addl Days Granted0
Working Days Charged116
Percent Time Used87
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-090
STRAIGHT LINE SAWING & SEALING, INC. (7.42)
DUSTROL, INC. (2.34)
(INACTIVE)WEST TEXAS RUMBLE STRIP (0.17)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.75)
PRIMATE CONSTRUCTION, LP (0.07)
TOTAL HIGHWAY MAINTENANCE, LLC (0.06)
Contract #08183021
Totals7009733.690.007113209.5699.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7