Monthly State Let Construction Report For Yoakum District As Of Aug 23, 2019 Page 1 Of 7

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGONZALES
HighwayUS 90A
FromGUADALUPE C/L
To8.702 MI E OF GUADALUPE C/L
CSJ0025-05-021
Proj IDSTP 1802(494)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
16.2892179041.091243874.9357.0
Work Order09-18-18
Work Began01-14-19
Work Completed
Time Computed12-17-18
Contract Working Days192
Addl Days Granted27
Working Days Charged113
Percent Time Used51
Contractor(s)
MPB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-05-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183036
Totals2179041.09107402.211243874.9357.0

CountyGONZALES ETC
HighwaySH 97 ETC
From0.03 MI N OF US 90A
ToSH 304
CSJ0025-07-065
Proj IDSTP 2019(173)
Work TypeSEAL COAT
 
171.8457309912.807895476.3599.9
Work Order12-20-18
Work Began05-13-19
Work Completed
Time Computed05-13-19
Contract Working Days45
Addl Days Granted4
Working Days Charged33
Percent Time Used67
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-07-065
BATTERSON,LLP (13.62)
FLASHER EQUIPMENT COMPANY (0.04)
BRYDL CONTRACTING, INC. (0.66)
Contract #11183224
Totals7309912.801857596.967895476.3599.9

CountyGONZALES
HighwayUS 90
From0.013 MI W OF FM 1680
To0.01 MI W OF FAYETTE C/L
CSJ0026-01-027
Proj IDSTP 2018(604)
Work TypePAVEMENT REPAIR AND RESURFACING
 
6.4762613600.862733360.6299.9
Work Order04-18-18
Work Began06-26-18
Work Completed
Time Computed06-01-18
Contract Working Days135
Addl Days Granted0
Working Days Charged158
Percent Time Used117
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-01-027
ROADWAY SPECIALTIES, INC. (0.85)
CHEROKEE SERVICES (1.21)
FLASHER LIMITED (0.35)
TRP CONSTRUCTION GROUP, LLC (4.02)
UNDER CONSTRUCTION INC. (1.79)
PENHALL COMPANY (0.25)
Contract #03183221
Totals2613600.861901.202733360.6299.9

CountyFAYETTE
HighwayUS 90
FromAT MIDDLE CREEK
ToSTR # 0026-03-028
CSJ0026-03-042
Proj IDBR 2017(318)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.288831842.19814791.3299.9
Work Order01-10-17
Work Began03-03-17
Work Completed
Time Computed04-10-17
Contract Working Days60
Addl Days Granted0
Working Days Charged121
Percent Time Used201
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-042
DELGADO"S CONSTRUCTION (60.07)
EGGEMEYER LAND CLEARING, LLC (2.87)
ROADWAY SPECIALTIES, INC. (3.88)
FLASHER EQUIPMENT COMPANY (0.39)
PAVEMENT MARKINGS INC. (0.94)
Contract #12163022
Totals831842.190.00814791.3299.9

CountyFAYETTE ETC
HighwayUS 90 ETC
From@ FM 2672
To.
CSJ0026-03-045
Proj IDSTP 2019(416)HES
Work TypeINSTALL SAFETY LIGHTING
 
0.008235017.200.000.0
Work Order02-27-19
Work Began08-19-19
Work Completed
Time Computed05-28-19
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F & W ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-045
ALTUS TRAFFIC MANAGEMENT LLC (6.92)
Contract #01193035
Totals235017.200.000.000.0

CountyCOLORADO
HighwayUS 90
FromAT COLORADO RIVER
ToSTR # 0027-01-001
CSJ0027-01-040
Proj IDBR 2016(507)
Work TypeCONSTRUCT ONE WAY BRIDGE AND APPR
 
0.3647142388.401213197.0016.9
Work Order06-21-17
Work Began00-00-00
Work Completed
Time Computed09-19-17
Contract Working Days350
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-01-040
HIGHWAY 1, LLC (0.60)
LONESTAR TRAFFIC SAFETY, LLC (0.25)
HOUSTON SAWING & DRILLING (0.11)
W. W. FOUNDATION DRILLING, LTD. (6.76)
CHOCTAW ERECTORS, INC. (7.10)
Contract #05173011
Totals7142388.400.001213197.0016.9

CountyCOLORADO
HighwayUS 90
FromAT COLORADO RIVER BRIDGE
ToSTR # 0027-01-001
CSJ0027-01-044
Proj IDBR 2019(850)
Work TypeBRIDGE REPLACEMENT
 
0.3648244674.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-13-19
Work Began08-05-19
Work Completed
Time Computed08-05-19
Contract Working Days405
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0027-01-044
SEMPER STRIPING LLC (0.02)
HB FARMER FOUNDATION, LLC (12.51)
MCL CONTRACTING, LLC (0.81)
Contract #05193010
Totals8244674.880.000.000.0

CountyCOLORADO
HighwayUS 90A
FromFM 102 IN EAGLE LAKE
ToWHARTON COUNTY LINE
CSJ0027-03-071
Proj IDSTP 1702(426)
Work TypeCONSTRUCT SUPER 2 LANES
 
5.0284487326.994828085.7299.9
Work Order08-11-17
Work Began10-25-17
Work Completed
Time Computed11-09-17
Contract Working Days160
Addl Days Granted0
Working Days Charged159
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0027-03-071
AREA WIDE PROTECTIVE, INC. (0.26)
D. I. J. CONSTRUCTION, INC. (1.88)
D&S TEXAS ICON CONSTRUCTION (0.35)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.27)
RIOS TRUCKING CO. (1.40)
STRIPE-A-ZONE, INC. (0.27)
Contract #06173243
Totals4487326.990.004828085.7299.9

CountyVICTORIA
HighwayUS 59
FromBU 59T
ToGOLIAD C/L
CSJ0088-04-070
Proj IDNH 2018(158)
Work TypeACP OVERLAY
 
6.1794506272.523648734.3580.9
Work Order05-17-18
Work Began12-03-18
Work Completed
Time Computed06-17-18
Contract Working Days75
Addl Days Granted0
Working Days Charged71
Percent Time Used94
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-04-070
HIGHWAY BARRICADES AND SERVICES, LLC (3.91)
INTERSTATE BARRICADES & MARKINGS, INC. (0.16)
WEST TEXAS ROCK RESOURCES, LLC (0.24)
Contract #04183231
Totals4506272.52153027.243648734.3580.9

CountyVICTORIA
HighwayUS 59
From0.5 MI S OF FM 1686
ToSL 463
CSJ0088-05-085
Proj IDC 88-5-85
Work TypeCONSTRUCT FRONTAGE ROADS
 
2.76927884764.508983401.4932.2
CountyVICTORIA
HighwayUS 59
From0.5 MI S OF FM 1686
ToSL 463
CSJ0088-05-099
Proj IDROW 88-5-99
Work TypeUTILITY ONLY
 
3.329708858.20649405.4091.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-19-18
Work Began09-17-18
Work Completed
Time Computed00-00-00
Contract Working Days600
Addl Days Granted3
Working Days Charged152
Percent Time Used25
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-085
AREA WIDE PROTECTIVE, INC. (0.02)
THIRD COAST SERVICES LLC (5.43)
ANGEL BROTHERS HOLDINGS CORP. (28.20)
ADCOCK 4 INVESTMENTS, LLC (4.34)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.59)
TITO"S TRUCKING & SONS, LLC (0.00)
ROADWAY SPECIALTIES, INC. (1.60)
INSITUFORM TECHNOLOGIES, LLC (0.68)
MVA CONSTRUCTION LLC (0.00)
AIMS COMPANIES (0.03)
BORTUNCO (0.22)
FARR FOUNDATION, INC. (0.30)
Contract #05183003
Totals28593622.70728266.879632806.8933.6

CountyVICTORIA
HighwayUS 59
FromLP 463
ToSPUR 91
CSJ0088-05-091
Proj IDNH 2018(506)
Work TypeACP OVERLAY
 
10.5889267866.66975427.0610.5
Work Order03-15-18
Work Began06-10-19
Work Completed
Time Computed04-15-18
Contract Working Days165
Addl Days Granted0
Working Days Charged25
Percent Time Used15
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-091
AREA WIDE PROTECTIVE, INC. (0.09)
STRIPE-A-ZONE, INC. (0.36)
CHEROKEE SERVICES (3.28)
HIGHWAY BARRICADES AND SERVICES, LLC (4.79)
Contract #02183235
Totals9267866.66539317.70975427.0610.5

CountyVICTORIA
HighwayUS 59
From1.26 MI NORTH OF US 87
To1.73 MI NORTH OF US 87
CSJ0088-05-092
Proj IDC 88-5-92
Work TypeCONSTRUCT 4-LANE OVERPASS
 
0.4908914435.178828446.6799.0
Work Order11-23-16
Work Began07-06-17
Work Completed
Time Computed02-21-17
Contract Working Days165
Addl Days Granted34
Working Days Charged196
Percent Time Used98
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-092
HOUSTON SAWING & DRILLING (0.04)
LONE STAR EROSION CONTROL (0.18)
MCL CONTRACTING, LLC (0.34)
ROADWAY SPECIALTIES, INC. (0.96)
STRIPE LINES, INC. (0.74)
V.C. HUFF, L.L.C. (2.16)
WEST TEXAS RUMBLE STRIP (0.05)
W. W. FOUNDATION DRILLING, LTD. (2.31)
AARON CONCRETE CONTRACTORS, L.P. (2.83)
INDUS CONSTRUCTION, L.P. (0.25)
Contract #10163032
Totals8914435.173348.598828446.6799.0

CountyVICTORIA
HighwayBU 59-T
FromAT FM 236
To.
CSJ0088-06-004
Proj IDSTP 2018(836)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.400316189.28352549.1099.9
Work Order06-11-18
Work Began09-04-18
Work Completed
Time Computed09-09-18
Contract Working Days50
Addl Days Granted2
Working Days Charged51
Percent Time Used98
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0088-06-004
SPECIALTY DRILLING, LTD. (1.19)
INTERSTATE BARRICADES & MARKINGS, INC. (3.29)
ALTUS TRAFFIC MANAGEMENT LLC (3.66)
AAA ASPHALT PAVING, INC. (5.96)
Contract #05183216
Totals316189.280.00352549.1099.9

CountyVICTORIA
HighwayUS 59
From0.4 MI. EAST OF FM 1686
ToJACKSON C/L
CSJ0089-01-090
Proj IDNH 2016(965)
Work TypeACP OVERLAY
 
8.0107280415.337975017.8299.9
Work Order00-00-00
Work Began03-06-17
Work Completed
Time Computed05-31-16
Contract Working Days105
Addl Days Granted10
Working Days Charged191
Percent Time Used166
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-01-090
CHEROKEE SERVICES (2.45)
DIAMOND K SERVICES, INC. (0.24)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45)
Contract #04163208
Totals7280415.330.007975017.8299.9

CountyJACKSON
HighwayUS 59
FromFROM 0.5 MI. NORTH OF LAVACA RIVER
ToVICTORIA COUNTY LINE
CSJ0089-03-088
Proj IDNH 2016(508)
Work TypeACP OVERLAY
 
6.5646620873.226731776.2199.9
Work Order03-01-16
Work Began03-06-17
Work Completed
Time Computed03-16-16
Contract Working Days90
Addl Days Granted0
Working Days Charged126
Percent Time Used140
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-03-088
MPB, INC. (8.62)
DIAMOND SURFACE, INC. (0.24)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.37)
Contract #01163029
Totals6620873.220.006731776.2199.9

CountyJACKSON
HighwayUS 59
FromSH 111
ToVICTORIA C/L
CSJ0089-03-092
Proj IDSTP 1902(165)HES
Work TypeSFT
 
23.3581939359.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0089-03-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193026
Totals1939359.900.000.000.0

CountyWHARTON
HighwayUS 59
FromFM 647 (NORTHBOUND ONLY)
ToJACKSON COUNTY LINE
CSJ0089-06-079
Proj IDNH 2016(700)
Work TypePAVEMENT REPAIR & ACP OVERLAY
 
8.9743681313.693508904.7695.5
Work Order03-07-16
Work Began08-23-16
Work Completed
Time Computed03-19-16
Contract Working Days60
Addl Days Granted28
Working Days Charged95
Percent Time Used107
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-079
FLASHER EQUIPMENT COMPANY (2.62)
WEST TEXAS RUMBLE STRIP (0.18)
MPB, INC. (5.42)
Contract #02163029
Totals3681313.690.003508904.7695.5

CountyWHARTON
HighwayUS 59
FromBU 59 SOUTH OF EL CAMPO
ToFM 1163
CSJ0089-06-081
Proj IDNH 1502(476)
Work TypeCONSTRUCT FRONTAGE RO025809111
 
2.60218889263.0319591958.3599.9
Work Order04-07-16
Work Began06-14-16
Work Completed
Time Computed10-04-16
Contract Working Days324
Addl Days Granted45
Working Days Charged361
Percent Time Used97
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-081
ROADSAFE TRAFFIC SYSTEMS, INC. (0.64)
WILLOW CITY SIGN & RAIL, INC. (1.38)
MBN ENTERPRISES LLC (2.93)
SEMARCK LANDSCAPE SERVICES, INC. (0.69)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.23)
J & M CONTRACTING, COMPANY (6.90)
Contract #11153007
Totals18889263.030.0019591958.3599.9

CountyWHARTON
HighwayUS 59
FromLP 524 N. OF HILLJE (NB LANES ONLY)
To0.130 MI.N.OF FM 647(NB LANES ONLY)
CSJ0089-06-088
Proj IDNH 1702(485)
Work TypeACP OVERLAY
 
17.2038161719.844718690.2158.1
Work Order08-16-17
Work Began01-08-18
Work Completed
Time Computed11-14-17
Contract Working Days84
Addl Days Granted0
Working Days Charged109
Percent Time Used129
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-088
BATTERSON,LLP (3.59)
DEVTEX INC. (2.18)
A BROTHERS MILLING, LLC (1.99)
WEST TEXAS RUMBLE STRIP (0.17)
Contract #07173210
Totals8161719.840.004718690.2158.1

CountyWHARTON
HighwayUS 59
FromFM 1163
ToLP 524 N. OF HILLJE
CSJ0089-06-090
Proj IDC 89-6-90
Work TypeACP OVERLAY
 
8.4497009733.69244238.393.4
Work Order09-24-18
Work Began07-08-19
Work Completed
Time Computed04-01-19
Contract Working Days133
Addl Days Granted0
Working Days Charged11
Percent Time Used8
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-090
STRAIGHT LINE SAWING & SEALING, INC. (7.42)
DUSTROL, INC. (2.34)
(INACTIVE)WEST TEXAS RUMBLE STRIP (0.17)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.75)
PRIMATE CONSTRUCTION, LP (0.07)
Contract #08183021
Totals7009733.69236738.39244238.393.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7