Monthly State Let Construction Report For Yoakum District As Of Nov 13, 2018 Page 5 Of 6

Last Update: Tuesday, November 13, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDEWITT
HighwayVA
FromVARIOUS LOCATIONS
ToVICTORIA AREA OFFICE
CSJ0913-00-103
Proj IDSTP 2019(098)
Work TypeMILL AND INLAY
 
5.7463289679.410.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10183011
Totals3289679.410.000.000.0

CountyWHARTON
HighwayCR
FromAT WEST MUSTANG CREEK CR 372
To(CR 372) STR # AA06-59-001
CSJ0913-09-053
Proj IDBR 2012(407)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.074629675.00597441.4098.0
Work Order07-07-15
Work Began11-11-15
Work Completed
Time Computed10-06-15
Contract Working Days75
Addl Days Granted0
Working Days Charged108
Percent Time Used144
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-053
HEMPHILL PILE DRIVING CO., A CORP. (4.74)
ODUM SERVICES, L.P. (3.89)
JUST GROOVING, LTD. (0.25)
CEN TEX HYDROSEED, INC. (0.33)
Contract #05153048
Totals629675.000.00597441.4098.0

CountyWHARTON
HighwayCR
FromAT GUM TREE BRANCH # 2
To(CR 252) STR # AA03-17-003
CSJ0913-09-059
Proj IDBR 2012(412)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.164746501.30726662.5097.3
Work Order05-11-17
Work Began11-29-17
Work Completed
Time Computed06-12-17
Contract Working Days120
Addl Days Granted0
Working Days Charged72
Percent Time Used60
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-059
LONESTAR TRAFFIC SAFETY, LLC (0.62)
JMHP, INC. (5.97)
MESA ROD BUSTERS, INC. (0.00)
Contract #04173029
Totals746501.300.00726662.5097.3

CountyWHARTON
HighwayCR
FromAT DRAW CR 214
ToSTR # AA03-20-001
CSJ0913-09-062
Proj IDBR 2014(697)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.061324876.00304118.3893.6
Work Order01-10-18
Work Began07-02-18
Work Completed
Time Computed02-10-18
Contract Working Days60
Addl Days Granted0
Working Days Charged57
Percent Time Used95
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-062
SPECIALTY DRILLING, LTD. (10.19)
LONE STAR PAVING COMPANY (7.40)
CEN TEX HYDROSEED, INC. (0.56)
HOUSTON SAWING & DRILLING (0.53)
Contract #12173021
Totals324876.0045792.38304118.3893.6

CountyWHARTON
HighwayCR
FromAT EAST FORK JONES CREEK CR 461
To(CR 461) STR # AA06-47-002
CSJ0913-09-065
Proj IDBR 2014(682)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100320804.30258240.4280.4
Work Order09-18-17
Work Began11-28-17
Work Completed
Time Computed12-17-17
Contract Working Days60
Addl Days Granted0
Working Days Charged41
Percent Time Used68
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-065
BATTEN DRILLING, INC. (9.03)
Contract #08173027
Totals320804.3012623.66258240.4280.4

CountyWHARTON
HighwayCR
FromAT BLUE CREEK #2 CR 400
To(CR 421) STR # AA04-00-002
CSJ0913-09-066
Proj IDBR 2019(301)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.074542104.500.000.0
CountyWHARTON
HighwayCR
FromAT BLUE CREEK (132410AA0442001)
ToWCR 407 (AA1053)
CSJ0913-09-078
Proj IDBR 1502(199)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.056325927.500.000.0
CountyJACKSON
HighwayCR
FromAT FIVEMILE BRANCH CR 472
ToSTR AA02-34-001
CSJ0913-18-032
Proj IDBR 2017(801)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.066226266.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days190
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10183209
Totals1094298.000.000.000.0

CountyWHARTON
HighwayCR
FromAT JONES CREEK CR 648
To(CR 457) STR # AA06-48-001
CSJ0913-09-071
Proj IDBR 2014(681)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.068441100.21439341.1799.6
Work Order05-10-16
Work Began07-18-16
Work Completed
Time Computed08-08-16
Contract Working Days75
Addl Days Granted0
Working Days Charged75
Percent Time Used100
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-071
JUST GROOVING, LTD. (0.22)
ODUM SERVICES, L.P. (2.53)
SPECIALTY DRILLING, LTD. (10.09)
CEN TEX HYDROSEED, INC. (1.78)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.13)
Contract #02163031
Totals441100.210.00439341.1799.6

CountyWHARTON
HighwayCR
FromAT TRES PALACIOS RIVER
ToWCR 410 STR AA04-40-001
CSJ0913-09-073
Proj IDBR 2017(100)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.170980970.40521997.3753.2
Work Order06-14-18
Work Began07-17-18
Work Completed
Time Computed07-14-18
Contract Working Days144
Addl Days Granted0
Working Days Charged64
Percent Time Used44
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-073
JMHP, INC. (3.34)
LONESTAR TRAFFIC SAFETY, LLC (0.71)
MAIN LANE INDUSTRIES LTD. (0.39)
Contract #05183049
Totals980970.4095620.00521997.3753.2

CountyWHARTON
HighwayCR
FromAT PEACH CREEK (132410AA0294001)
ToWCR 253 (AA0253)
CSJ0913-09-076
Proj IDBR 1502(198)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.130670423.18656767.8197.9
Work Order07-13-16
Work Began09-02-16
Work Completed
Time Computed10-11-16
Contract Working Days120
Addl Days Granted0
Working Days Charged85
Percent Time Used70
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-076
HEMPHILL WBE PILE DRIVING CO. (5.60)
LONESTAR TRAFFIC SAFETY, LLC (0.85)
BRANNAN PAVING CO., LTD. (4.91)
Contract #05163204
Totals670423.180.00656767.8197.9

CountyWHARTON
HighwayCS
FromVARIOUS LOC. ALONG AVE I& NORRIS ST
ToIN THE CITY OF EL CAMPO
CSJ0913-09-081
Proj IDSTP 1602(475)TAPS
Work TypeCONSTRUCT SIDEWALKS
 
1.202311986.00316064.6099.9
Work Order02-09-17
Work Began04-28-17
Work Completed
Time Computed05-10-17
Contract Working Days45
Addl Days Granted0
Working Days Charged45
Percent Time Used100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173226
Totals311986.000.00316064.6099.9

CountyWHARTON
HighwayCR
FromAT DRAW CR 303
ToSTR AA04-62-001
CSJ0913-09-083
Proj IDBR 1602(017)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2591499626.26951406.1763.4
Work Order11-16-17
Work Began03-05-18
Work Completed
Time Computed12-16-17
Contract Working Days225
Addl Days Granted0
Working Days Charged144
Percent Time Used64
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-083
SHINN AND GREGORY, INC. (1.56)
FLASHER LIMITED (0.84)
BEAIRD DRILLING (3.54)
CP REBAR AND PT INSTALLATION (0.18)
DIIBS SPECIALISTS (4.72)
PENHALL COMPANY (AUSTIN) (0.57)
WILLIAMS ROAD, LLC (0.96)
Contract #10173211
Totals1499626.2610975.00951406.1763.4

CountyDEWITT
HighwayCR
FromAT DRAW CHARCO RD
ToSTR # AA01-16-001
CSJ0913-17-041
Proj IDBR 1502(365)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.067323694.00297070.0095.7
Work Order08-25-16
Work Began10-31-16
Work Completed
Time Computed10-23-16
Contract Working Days45
Addl Days Granted0
Working Days Charged67
Percent Time Used148
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07163213
Totals323694.000.00297070.0095.7

CountyAUSTIN
HighwayCR
FromAT DRAW
To(NELIUS RD) STR # AA03-26-001
CSJ0913-20-084
Proj IDBR 1102(474)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.071525692.63460588.8388.8
Work Order01-02-15
Work Began02-23-15
Work Completed
Time Computed02-23-15
Contract Working Days60
Addl Days Granted0
Working Days Charged71
Percent Time Used118
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-084
ENVIRONMENTAL SAFETY SERVICES, INC. (3.76)
DALLAS LITE AND BARRICADE INC. (0.32)
Contract #11143206
Totals525692.630.00460588.8388.8

CountyAUSTIN
HighwayCR
FromAT DRY CREEK CR 328
To(KIESEWETTER RD) STR AA03-28-001
CSJ0913-20-090
Proj IDBR 2018(207)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.071410493.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-090
BATTEN DRILLING, INC. (11.98)
LONESTAR TRAFFIC SAFETY, LLC (0.55)
Contract #07183009
Totals410493.120.000.000.0

CountyGONZALES
HighwayCR
FromAT PEACH CREEK CR 353
To(CR 353) STR # AA03-53-003
CSJ0913-22-047
Proj IDBR 1602(616)
Work TypeREHABILITATE EXISTING BRIDGE
 
0.075773075.76223719.7328.9
Work Order05-17-18
Work Began08-20-18
Work Completed
Time Computed08-15-18
Contract Working Days111
Addl Days Granted0
Working Days Charged29
Percent Time Used26
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-047
VOGES DRILLING CO. (7.59)
Contract #04183014
Totals773075.7651888.92223719.7328.9

CountyCOLORADO
HighwayCR
FromAT STEIN BRANCH CR 138
To(STOKES ROAD) STR # AA01-38-001
CSJ0913-26-058
Proj IDBR 2012(731)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.053233008.00240195.0099.9
Work Order05-18-17
Work Began09-11-17
Work Completed
Time Computed08-16-17
Contract Working Days40
Addl Days Granted0
Working Days Charged33
Percent Time Used82
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-26-058
LONE STAR PAVING COMPANY (19.03)
LONESTAR TRAFFIC SAFETY, LLC (0.68)
DIIBS SPECIALISTS (5.30)
Contract #04173210
Totals233008.000.00240195.0099.9

CountyVICTORIA
HighwayCR
FromAT SPRING CREEK CR 46
To(OLIVER ROAD) STR AA01-71-001
CSJ0913-27-061
Proj IDBR 2018(876)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3661477750.04509407.7034.4
Work Order04-18-18
Work Began06-25-18
Work Completed
Time Computed05-18-18
Contract Working Days300
Addl Days Granted0
Working Days Charged48
Percent Time Used16
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-061
BEAIRD DRILLING (5.85)
ENVIRONMENTAL SAFETY SERVICES, INC. (6.67)
FLASHER LIMITED (0.70)
HEMPHILL WBE PILE DRIVING CO. (1.86)
LONE STAR EROSION CONTROL (4.10)
Contract #03183004
Totals1477750.0473698.90509407.7034.4

CountyLAVACA
HighwayCR
FromAT NAVIDAD RIVER
ToSTR# AA05-22-001 (CR 14)
CSJ0913-29-031
Proj IDBR 2007(370)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.138567765.26542383.1296.8
Work Order08-16-17
Work Began11-06-17
Work Completed
Time Computed11-14-17
Contract Working Days75
Addl Days Granted0
Working Days Charged87
Percent Time Used116
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-031
FLASHER EQUIPMENT COMPANY (0.92)
FUQUAY, INC. (1.49)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.01)
BEAIRD DRILLING (17.10)
Contract #06173222
Totals567765.260.00542383.1296.8

CountyLAVACA
HighwayCR
FromAT SMOTHERS CREEK CR 183
To(CR 183) STR AA01-02-004
CSJ0913-29-033
Proj IDBR 2007(372)
Work TypeREHABILITATE EXISTING BRIDGE
 
0.300733626.26259305.8435.3
Work Order08-08-17
Work Began01-03-18
Work Completed
Time Computed11-06-17
Contract Working Days60
Addl Days Granted0
Working Days Charged23
Percent Time Used38
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-033
S & S BRIDGE PAINTING, INC. (20.80)
FLASHER LIMITED (0.51)
FUQUAY, INC. (1.08)
CHOCTAW ERECTORS, INC. (17.03)
Contract #07173215
Totals733626.261411.87259305.8435.3

CountyLAVACA
HighwayCR
FromAT LAVACA RIVER CR 260
To(CR 260) #AA01-69-001
CSJ0913-29-035
Proj IDBR 2018(794)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.135573001.80428335.5074.7
Work Order03-14-18
Work Began06-05-18
Work Completed
Time Computed06-12-18
Contract Working Days90
Addl Days Granted0
Working Days Charged54
Percent Time Used60
Contractor(s)
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-035
VOGES DRILLING CO. (6.05)
LONE STAR PAVING COMPANY (7.83)
HOUSTON SAWING & DRILLING (0.38)
FUQUAY, INC. (0.73)
D. I. J. CONSTRUCTION, INC. (0.89)
DIIBS SPECIALISTS (2.42)
KOHLENBERG WELDING, INC. (1.11)
TEXAS CUTTING & CORING GP, INC. (0.34)
Contract #02183020
Totals573001.8053620.00428335.5074.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6