Monthly State Let Maintenance Report For Yoakum District As Of Aug 23, 2019 Page 1 Of 3

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyVICTORIA
HighwayUS0059
FromVARIOUS ROADWAYS IN
ToVICTORIA, JACKSON & CALHOUN COUNTIES
CSJ6218-72-001
Proj IDRMC - 621872001
Work TypePERFORMANCE BASED VEGETATION MANAGEMENT
 
0.0011592011.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6218-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01114017
Totals1592011.000.000.000.0

CountyCOLORADO
HighwayUS0090
FromVARIOUS LIMITS
To.
CSJ6220-45-001
Proj IDRMC - 622045001
Work TypeMOWING HIGHWAY RIGHTS OF WAY
 
0.001171658.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
XTW ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6220-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01114026
Totals171658.640.000.000.0

CountyLAVACA
HighwayUS0077
FromVARIOUS ROADWAYS
To.
CSJ6220-49-001
Proj IDRMC - 622049001
Work TypeMOWING HIGHWAY RIGHTS OF WAY
 
0.001215727.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
XTW ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6220-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01114030
Totals215727.120.000.000.0

CountyWHARTON
HighwayUS0059
FromVARIOUS ROADWAYS IN WHARTON, MATAGORDA,
ToAND AUSTIN COUNTIES
CSJ6285-08-001
Proj IDRMC - 628508001
Work TypePERFORMANCE BASED VEGETATION MANAGEMENT
 
0.0013065000.004406743.2599.9
Work Order00-00-00
Work Began06-01-15
Work Completed
Time Computed06-01-15
Contract Working Days1,095
Addl Days Granted1,095
Working Days Charged1,523
Percent Time Used69
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6285-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04154211
Totals3065000.0085380.004406743.2599.9

CountyCOLORADO
HighwayIH0010
FromGONZALES, FAYETTE, COLORADO, AND
ToAUSTIN COUNTIES
CSJ6288-42-001
Proj IDRMC - 628842001
Work TypeINSTALLATION OF GUIDE SIGNS
 
0.001979897.06986242.0399.9
Work Order00-00-00
Work Began03-08-17
Work Completed
Time Computed03-15-17
Contract Working Days135
Addl Days Granted1
Working Days Charged180
Percent Time Used132
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6288-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164203
Totals979897.060.00986242.0399.9

CountyWHARTON
HighwayUS0059
FromWHARTON, JACKSON, AND
ToVICTORIA COUNTIES
CSJ6298-58-001
Proj IDRMC - 629858001
Work TypeLARGE GUIDE SIGNS
 
0.0011189410.751200789.9399.9
Work Order00-00-00
Work Began12-20-17
Work Completed
Time Computed01-16-18
Contract Working Days135
Addl Days Granted0
Working Days Charged229
Percent Time Used169
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174214
Totals1189410.752252.431200789.9399.9

CountyFAYETTE
HighwaySH0071
FromFAYETTE COUNTY
To.
CSJ6305-91-001
Proj IDRMC - 630591001
Work TypeEROSION REPAIRS
 
0.001352304.00576933.0099.9
Work Order00-00-00
Work Began03-08-17
Work Completed
Time Computed03-15-17
Contract Working Days45
Addl Days Granted0
Working Days Charged38
Percent Time Used84
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-91-001
HEMPHILL WBE PILE DRIVING CO. (10.78)
LONESTAR TRAFFIC SAFETY, LLC (0.70)
Contract #11164023
Totals352304.000.00576933.0099.9

CountyMATAGORDA
HighwaySH0060
FromAUSTIN, DEWITT, JACKSON, LAVACA, WHARTON
ToMATAGORDA, AND VICTORIA COUNTIES
CSJ6308-41-001
Proj IDRMC - 630841001
Work TypeSTRUCTURE IMPROVEMENTS
 
0.001827505.00783508.0097.2
Work Order00-00-00
Work Began04-09-18
Work Completed
Time Computed04-16-18
Contract Working Days90
Addl Days Granted0
Working Days Charged125
Percent Time Used138
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-41-001
JB PINNACLE GROUP, LLC (13.47)
Contract #09174005
Totals827505.000.00783508.0097.2

CountyDEWITT
HighwayUS0183
FromAUSTIN, DEWITT, FAYETTE, GONZALES,
ToLAVACA, AND COLORADO COUNTIES
CSJ6318-82-001
Proj IDRMC - 631882001
Work TypeON CALL THERMO PAVEMENT MARKINGS
 
0.001484590.00522694.3599.9
Work Order00-00-00
Work Began12-11-17
Work Completed
Time Computed12-11-17
Contract Working Days365
Addl Days Granted30
Working Days Charged369
Percent Time Used93
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6318-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174007
Totals484590.000.00522694.3599.9

CountyGONZALES
HighwayUA0090
FromDISTRICTWIDE
To.
CSJ6320-65-001
Proj IDRMC - 632065001
Work TypeON CALL SPOT REPAIRS
 
0.001792950.001487006.0499.9
Work Order00-00-00
Work Began06-11-18
Work Completed
Time Computed06-11-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6320-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174003
Totals792950.000.001487006.0499.9

CountyGONZALES
HighwayUA0090
FromDISTRICT WIDE
To.
CSJ6322-66-001
Proj IDRMC - 632266001
Work TypeBRIDGE JOINT - CALL OUT
 
0.001721216.001625860.9899.9
Work Order00-00-00
Work Began06-11-18
Work Completed
Time Computed06-11-18
Contract Working Days365
Addl Days Granted0
Working Days Charged119
Percent Time Used32
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174007
Totals721216.000.001625860.9899.9

CountyGONZALES
HighwayUA0090
FromDISTRICT WIDE
To.
CSJ6322-69-001
Proj IDRMC - 632269001
Work TypeCONCRETE PUNCH OUT - CALL OUT
 
0.0011045200.001218617.1899.9
Work Order00-00-00
Work Began05-07-18
Work Completed
Time Computed05-07-18
Contract Working Days365
Addl Days Granted0
Working Days Charged356
Percent Time Used97
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174208
Totals1045200.000.001218617.1899.9

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND
ToCALHOUN COUNTIES
CSJ6324-26-001
Proj IDRMC - 632426001
Work TypeON CALL FLAGGING OPERATIONS
 
0.001315500.00506237.5099.9
Work Order00-00-00
Work Began09-04-18
Work Completed
Time Computed09-04-18
Contract Working Days365
Addl Days Granted365
Working Days Charged325
Percent Time Used44
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6324-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184006
Totals315500.0068292.50506237.5099.9

CountyFAYETTE
HighwayIH0010
FromFAYETTE, COLORADO, DEWITT, GONZALES,
ToLAVACA COUNTIES
CSJ6324-45-001
Proj IDRMC - 632445001
Work TypeMETAL GUARDFENCE REPAIR (ON CALL)
 
0.001425765.001651929.3199.9
Work Order00-00-00
Work Began06-01-18
Work Completed
Time Computed06-01-18
Contract Working Days365
Addl Days Granted365
Working Days Charged420
Percent Time Used57
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6324-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03184006
Totals425765.0095383.991651929.3199.9

CountyVICTORIA
HighwayUS0077
FromDISTRICT WIDE
To.
CSJ6325-10-001
Proj IDRMC - 632510001
Work TypeTHERMOPLASTIC PAVEMENT MARKINGS
 
0.001759841.79937955.83100.0
Work Order10-29-18
Work Began10-29-18
Work Completed08-16-19
Time Computed11-05-18
Contract Working Days60
Addl Days Granted0
Working Days Charged28
Percent Time Used46
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184205
Totals759841.790.00937955.83100.0

CountyVICTORIA
HighwayUS0059
FromDISTRICTWIDE
To.
CSJ6326-76-001
Proj IDBPM - 632676001
Work TypeDISTRICTWIDE BEAM AND EROSION REPAIRS
 
0.001877085.00910495.4099.9
Work Order11-01-18
Work Began11-01-18
Work Completed
Time Computed11-08-18
Contract Working Days90
Addl Days Granted0
Working Days Charged89
Percent Time Used98
Contractor(s)
DRS CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184004
Totals877085.00139335.00910495.4099.9

CountyCOLORADO
HighwayIH0010
FromE. HINTON RD
To0.48 MI SOUTH OF E. HINTON RD
CSJ6327-53-001
Proj IDRMC - 632753001
Work TypeREHAB ROADWAY AND ACP OVERLAY
 
0.423299561.00297409.8399.2
Work Order00-00-00
Work Began09-24-18
Work Completed
Time Computed10-05-18
Contract Working Days45
Addl Days Granted0
Working Days Charged28
Percent Time Used62
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6327-53-001
AREA WIDE PROTECTIVE, INC. (1.40)
TRP CONSTRUCTION GROUP, LLC (3.09)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.73)
Contract #06184224
Totals299561.000.00297409.8399.2

CountyWHARTON
HighwayUS0059
FromWHARTON, MATAGORDA, AND
ToAUSTIN COUNTIES
CSJ6328-42-001
Proj IDRMC - 632842001
Work TypeMETAL GUARDFENCE REPAIR (ON CALL)
 
0.001417975.00255309.0061.0
Work Order00-00-00
Work Began09-24-18
Work Completed
Time Computed09-24-18
Contract Working Days730
Addl Days Granted0
Working Days Charged305
Percent Time Used41
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6328-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184007
Totals417975.0018227.00255309.0061.0

CountyVICTORIA
HighwayUS0059
FromVICTORIA, CALHOUN, AND
ToJACKSON COUNTIES
CSJ6328-43-001
Proj IDRMC - 632843001
Work TypeMETAL GUARDFENCE REPAIR (ON CALL)
 
0.001397172.00394435.0099.3
Work Order00-00-00
Work Began09-24-18
Work Completed
Time Computed09-24-18
Contract Working Days730
Addl Days Granted0
Working Days Charged282
Percent Time Used38
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6328-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184204
Totals397172.0025623.00394435.0099.3

CountyCOLORADO
HighwaySH0071
FromCOLORADO, WHARTON, MATAGORDA,
ToAND AUSTIN COUNTIES
CSJ6329-04-001
Proj IDRMC - 632904001
Work TypeON CALL FLAGGING OPERATIONS
 
0.001323892.50302892.2793.5
Work Order00-00-00
Work Began09-04-18
Work Completed
Time Computed09-04-18
Contract Working Days365
Addl Days Granted365
Working Days Charged351
Percent Time Used48
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6329-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184008
Totals323892.5026629.50302892.2793.5

page 1 | page 2 | page 3