AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - ABILENE DISTRICT

Last Update: Friday, May 27, 2016
ITEMS 100 6001 TO 169 6004
Items Items Bid Code Range
0100 - 0169
0216 - 0251
0305 - 0360
0400 - 0496
0500 - 0560
0610 - 0690
0700 - 0784
3014 - 3014
4022 - 4022
6001 - 6156
100 6001 - 169 6004
Item No Description Units May 31, 2016 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 6001 PREPARING ROW AC     3.340 9,233.53293 2
100 6002 PREPARING ROW STA     3.600 10,447.30000 1
104 6009 REMOVING CONC (RIPRAP) SY     838.000 35.93212 6
104 6021 REMOVING CONC (CURB) LF     3,186.000 10.00000 2
104 6022 REMOVING CONC (CURB AND GUTTER) LF     997.000 12.00000 1
104 6054 REMOVING CONCRETE (MOW STRIP) LF     600.000 25.00000 1
104 6064 REMOVING CONC (MISC) CY     .500 5,000.00000 1
105 6020 REMOVING STAB BASE & ASPH PAV (12") SY     13,444.000 10.10000 1
105 6064 REMOV STAB BASE AND ASPH PAV (3" - 9") SY     29,312.000 26.00000 1
110 6001 EXCAVATION (ROADWAY) CY     12,548.000 16.05264 8
112 6001 SUBGRADE WIDENING (ORD COMP) STA     847.240 721.90606 2
132 6001 EMBANKMENT (FINAL) (ORD COMP) (TY A) CY     45.000 100.00000 1
132 6003 EMBANKMENT (FINAL) (ORD COMP) (TY B) CY     1,135.000 33.32687 5
132 6004 EMBANKMENT (FINAL) (DENS CONT) (TY B) CY     3,206.000 29.10671 3
132 6011 EMBANKMENT (ORIGINAL) (ORD COMP) (TY B) CY     7,696.000 12.00000 1
132 6013 EMBANKMENT (ORIGINAL) (ORD COMP) (TY C) CY     9,000.000 11.71667 2
134 6002 BACKFILL (TY B) STA     2,893.020 329.85999 8
150 6002 BLADING HR     304.000 131.25095 5
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY     5,459.000 5.29974 4
162 6002 BLOCK SODDING SY     680.000 5.00000 1
164 6001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY     4,725.000 2.00000 1
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY     237,599.000 .16255 3
164 6009 BROADCAST SEED (TEMP) (WARM) SY     117,616.000 .06000 1
164 6011 BROADCAST SEED (TEMP) (COOL) SY     144,190.000 .06885 2
164 6015 STRAW / HAY MLCH SEED (PERM) (RURAL) (CLAY) SY     2,131.000 1.25000 1
164 6033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY     224,940.000 .25000 1
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY     26,574.000 .20800 1
164 6041 DRILL SEEDING (TEMP) (WARM) SY     112,470.000 .07000 1
164 6043 DRILL SEEDING (TEMP) (COOL) SY     112,470.000 .07000 1
168 6001 VEGETATIVE WATERING MG     537.000 31.62011 3
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY     366.000 4.90000 1
169 6003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY     409.000 2.50000 1
169 6004 SOIL RETENTION BLANKETS (CL 1) (TY D) SY     690.000 5.00000 1