AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - ABILENE DISTRICT

Last Update: Tuesday, September 30, 2014
ITEMS 3269 2005 TO 3278 2124
Items Items Bid Code Range
0100 - 0192
0216 - 0265
0310 - 0354
0400 - 0496
0500 - 0560
0610 - 0677
0730 - 0730
1122 - 1122
2131 - 2131
3269 - 3278
5369 - 5993
6834 - 6834
8020 - 8945
3269 2005 - 3278 2124
Item No Description Units Sept 30, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
3269 2005 PFC (ASPHALT) A - R - BNDR TON     3,647.980 485.78026 3
3269 2007 PFC (AGGREGATE) (A - R MIX) SAC - A TON     27,547.000 114.07070 2
3269 2009 PFC (AGGREGATE) (A - R MIX) SAC - B TON     10,304.900 150.04000 1
3270 2011 SUPERPAVE MIXTURES SP - B PG64 - 22 TON     142,404.000 78.12610 4
3270 2048 SUPERPAVE MIXTURES SP - C SAC - B PG70 - 22 TON     18,030.000 90.27000 1
3270 2106 SUPERPAVE MIXTURES SP - D PG64 - 22 TON     9,116.000 109.93590 2
3270 2120 SUPERPAVE MIXTURES SP - D SAC - B PG70 - 22 TON     80,434.810 85.50161 3
3271 2041 STONE - MTRX - ASPH SMAR - F SAC - B TON     4,467.000 149.71000 1
3278 2001 ASPH (TIER I) GAL     709,126.000 2.87000 1
3278 2004 ASPH (TIER I) ALT 1X GAL     13,487.000 2.87000 1
3278 2062 AGGR (GR 4) ALT 1X CY     321.000 56.00000 1
3278 2092 AGGR (GR 4) CY     9,586.000 58.00000 1
3278 2123 AGGR (GR 3) SAC A CY     6,390.000 92.00000 1
3278 2124 AGGR (GR4) SAC A CY     1,069.000 88.00000 1