Monthly State Let Construction Report For Abilene District As Of Sep 15, 2016 Page 1 Of 2

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOWARD
Highway IH 20
From AT US 87 (NEW LOCATION)
To .
CSJ 0005-05-102
Proj ID DMO 2012(263)
Work Type CONSTRUCT NEW INTERCHANGE
 
2.719 18434933.58 192365.88 18175524.58 98.5
Work Order 08-19-13
Work Began 05-13-14
Work Completed  
Time Computed 01-01-14
Contract Working Days 470
Addl Days Granted 59
Working Days Charged 513
Percent Time Used 96
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-102
W.S. CONSTRUCTION COMPANY(8.38%)
COPPELL CONSTRUCTION CO., INC. (8.49%)
DRILL TECH DRILLING & SHORING, INC.( 16.58%)
PRICE CONSTRUCTION, LTD. ( 28.11%)
TEXAS SHAFTS, INC. (1.76%)
FELIX CHAVEZ & SON CONSTRUCTION(0.24%)
MARTIN GONZALES INCORPORATED (1.32%)
WILLIS ELECTRIC CO., LP(2.27%)
HJC FARMS, INC.(1.58%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
TEX OP CONSTRUCTION, LP(0.23%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.50%)
ARANDA`S TRUCKING(0.74%)
NOBLES ROAD CONSTRUCTION, INC. (0.26%)
AARON CONCRETE CONTRACTORS, L.P. (0.60%)
Contract # 05133202
Totals 18434933.58 192365.88 18175524.58 98.5

CountyNOLAN
Highway IH 20 ETC
From 0.037 MI W OF CR 104
To 1.1 MI E OF CR 104
CSJ 0006-02-112
Proj ID STP 2016(904)HES
Work Type HFC, TEXT CL & SHLDR, CHEVRONS
 
8.560 3498754.25 787226.30 787226.30 22.5
Work Order 05-12-16
Work Began 08-08-16
Work Completed  
Time Computed 06-11-16
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 14
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-112
J. H. STRAIN & SONS, INC.( 12.56%)
HJC FARMS, INC.(1.17%)
Contract # 04163029
Totals 3498754.25 787226.30 787226.30 22.5

CountyTAYLOR
Highway IH 20 ETC
From BI 20-Q (SFR ONLY)
To IH 20 EXIT RAMP 277
CSJ 0006-05-114
Proj ID STP 1602(551)HES
Work Type INSTALL ADV WARN SIGNS AND CHEVRONS
 
31.986 258628.42 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-05-114
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163009
Totals 258628.42 0.00 0.00 0.0

CountyTAYLOR
Highway US 84
From NEAR OLD BANKHEAD HWY
To NEAR US 83
CSJ 0006-18-055
Proj ID NH 2016(915)
Work Type SPOT REPAIR, MILL & OVERLAY
 
2.660 2371863.21 1324230.75 2199475.19 92.7
Work Order 05-19-16
Work Began 06-13-16
Work Completed  
Time Computed 06-18-16
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 91
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-18-055
A BROTHERS MILLING, LLC(2.53%)
D. I. J. CONSTRUCTION, INC.(2.25%)
CONTRACTORS SERVICE COMPANY(0.50%)
Contract # 04163231
Totals 2371863.21 1324230.75 2199475.19 92.7

CountyTAYLOR
Highway SH 351
From IH 20
To ABILENE EAST CITY LIMIT
CSJ 0011-01-030
Proj ID STP 1302(056)
Work Type FL BS, STRS, PCTB, C & G, SDWLK, DRVWY, SMA
 
1.768 6920469.81 221722.46 3958467.62 57.1
Work Order 04-10-15
Work Began 06-10-15
Work Completed  
Time Computed 06-10-15
Contract Working Days 270
Addl Days Granted 11
Working Days Charged 252
Percent Time Used 89
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-030
CONTRACTORS SERVICE COMPANY(0.59%)
WILLIS ELECTRIC CO., LP( 12.40%)
STRIPING TECHNOLOGY, L.P.(1.68%)
MARCOM"S MOWING SERVICE, LLC (0.26%)
O. TREVINO CONSTRUCTION, LLC (5.52%)
WOLFE CONSTRUCTION GROUP, INC. (0.91%)
BILL STARKS CONSTRUCTION COMPANY (3.42%)
JORDAN CONCRETE( 13.77%)
GONZALES CONCRETE CONTRACTORS, INC.(6.30%)
Contract # 03153036
Totals 6920469.81 221722.46 3958467.62 57.1

CountySHACKELFORD
Highway US 180 ETC
From @ US 283
To .
CSJ 0011-06-045
Proj ID STP 1602(560)HES
Work Type FLASH BEACON
 
2.390 467417.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 87
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0011-06-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163239
Totals 467417.10 0.00 0.00 0.0

CountyJONES
Highway US 83
From JUST SOUTH OF 13TH STREET IN ANSON
To NEAR US 277
CSJ 0033-04-065
Proj ID NH 2016(149)
Work Type PLANE, PVMNT REPR, UNDERSL, OVERLAY
 
2.432 4425888.54 100570.49 4189122.40 94.6
Work Order 11-24-15
Work Began 02-29-16
Work Completed  
Time Computed 02-29-16
Contract Working Days 152
Addl Days Granted 10
Working Days Charged 98
Percent Time Used 60
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-04-065
CONTRACTORS SERVICE COMPANY(0.36%)
DUSTROL, INC.(3.77%)
BONTKE BROTHERS CONSTRUCTION COMPANY (7.76%)
HJC FARMS, INC.(1.80%)
BARRICADES UNLIMITED (2.84%)
Contract # 10153018
Totals 4425888.54 100570.49 4189122.40 94.6

CountyTAYLOR
Highway BU 83-D
From HILL STREET
To NEAR IH 20
CSJ 0033-08-038
Proj ID NH 2016(916)
Work Type PLAN, STR RPR, UNDSL, ACP, MBGF, BR RL
 
7.394 9806711.43 920728.81 920728.81 9.3
Work Order 07-20-16
Work Began 08-29-16
Work Completed  
Time Computed 08-19-16
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 10
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-08-038
A BROTHERS MILLING, LLC(1.64%)
HJC FARMS, INC.(0.23%)
WILLIS ELECTRIC CO., LP(3.45%)
CONTRACTORS SERVICE COMPANY(0.45%)
BARRICADES UNLIMITED (2.35%)
Contract # 04163008
Totals 9806711.43 920728.81 920728.81 9.3

CountyTAYLOR
Highway US 84
From US 83
To COLEMAN COUNTY LINE
CSJ 0054-01-031
Proj ID NH 2016(917)
Work Type SPOT REPAIR, SEAL & OVERLAY
 
11.210 7380051.17 2054053.00 2066553.00 28.0
Work Order 05-19-16
Work Began 07-11-16
Work Completed  
Time Computed 06-17-16
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 47
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0054-01-031
A BROTHERS MILLING, LLC(1.60%)
BARRICADES UNLIMITED (2.33%)
CONTRACTORS SERVICE COMPANY(0.16%)
WEST TEXAS RUMBLE STRIP(0.50%)
Contract # 04163216
Totals 7380051.17 2054053.00 2066553.00 28.0

CountyHOWARD
Highway US 87
From MARTIN COUNTY LINE
To 4.929 MI E OF MARTIN C/L (NBL ONLY)
CSJ 0068-07-050
Proj ID NH 1502(194)
Work Type PLAN, UNDSL, SUPER PAVE, MBGF
 
28.052 12331796.40 79023.12 12283069.35 99.6
Work Order 06-16-15
Work Began 10-08-15
Work Completed  
Time Computed 10-05-15
Contract Working Days 126
Addl Days Granted 10
Working Days Charged 130
Percent Time Used 95
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0068-07-050
BARRICADES UNLIMITED (1.52%)
CONTRACTORS SERVICE COMPANY(0.47%)
HJC FARMS, INC.(0.68%)
TEX OP CONSTRUCTION, LP(1.07%)
WEST TEXAS RUMBLE STRIP(0.30%)
Contract # 05153008
Totals 12331796.40 79023.12 12283069.35 99.6

CountyJONES
Highway SH 6 ETC
From BU 277-G
To SHACKELFORD COUNTY LINE
CSJ 0107-01-036
Proj ID STP 2016(305)
Work Type SEAL COAT
 
225.805 5991840.62 375625.80 6320414.24 99.9
Work Order 12-04-15
Work Began 06-22-16
Work Completed  
Time Computed 06-09-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 68
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0107-01-036
FLATE LINE, INC. ( 11.46%)
Contract # 11153008
Totals 5991840.62 375625.80 6320414.24 99.9

CountyCALLAHAN
Highway SH 36
From TAYLOR CO. LINE
To FM 603
CSJ 0181-02-029
Proj ID STP 2016(676)
Work Type PLAN, FLEX PAV STR RPR, SUPER PAV ACP
 
6.216 5388974.29 391377.44 1162089.92 21.5
Work Order 04-01-16
Work Began 05-02-16
Work Completed  
Time Computed 05-01-16
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 41
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0181-02-029
CONTRACTORS SERVICE COMPANY(0.31%)
WOLFE CONSTRUCTION GROUP, INC. (0.11%)
JORDAN CONCRETE(0.00%)
HJC FARMS, INC.(1.13%)
WILLIS ELECTRIC CO., LP(3.82%)
DOUBLE A CONTRACTING, L.P. (3.81%)
MICA CORPORATION (1.63%)
LUZ LERMA CONSTRUCTION, INC. (2.47%)
Contract # 02163010
Totals 5388974.29 391377.44 1162089.92 21.5

CountyMITCHELL
Highway SH 208
From CR 633
To COKE COUNTY LINE
CSJ 0454-03-041
Proj ID STP 2016(372)
Work Type SPOT REPAIR, UNDERSEAL, 2" OV SP - D
 
5.319 2654056.80 29075.44 2437637.79 91.8
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 06-01-16
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 76
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0454-03-041
CONTRACTORS SERVICE COMPANY(0.26%)
DOUBLE A CONTRACTING, L.P. (2.02%)
HUDSON, INC. (1.13%)
HJC FARMS, INC.(3.87%)
Contract # 10153230
Totals 2654056.80 29075.44 2437637.79 91.8

CountyTAYLOR
Highway FM 1235
From MERKEL CITY LIMIT
To CR 392
CSJ 0663-03-027
Proj ID STP 2015(789)HES
Work Type FL BS, REWK BS MATL, 2CST, CMP & SET
 
11.020 4552099.47 135311.63 2118574.66 46.5
Work Order 06-08-15
Work Began 09-08-15
Work Completed  
Time Computed 09-07-15
Contract Working Days 280
Addl Days Granted 50
Working Days Charged 74
Percent Time Used 32
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0663-03-027
CONTRACTORS SERVICE COMPANY(1.01%)
DOUBLE A CONTRACTING, L.P. (2.37%)
HJC FARMS, INC.(2.91%)
BRENDA CONSTRUCTION( 11.84%)
Contract # 04153037
Totals 4552099.47 135311.63 2118574.66 46.5

CountyTAYLOR
Highway VA
From VARIOUS LOCATIONS IN KENT,SCURRY,
To STONEWALL,AND HASKELL COUNTIES
CSJ 0908-00-080
Proj ID NH 2016(677)
Work Type INSTALL HIGH MAST ILLUMINATION
 
1.000 448260.50 213631.50 328888.39 73.3
Work Order 03-14-16
Work Began 08-09-16
Work Completed  
Time Computed 04-13-16
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 30
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-080
MICA CORPORATION ( 61.37%)
BARRICADES UNLIMITED (4.22%)
Contract # 02163037
Totals 448260.50 213631.50 328888.39 73.3

CountyHOWARD
Highway VA
From RM 33
To IH 20
CSJ 0908-12-019
Proj ID BOR 2004(670)
Work Type CONSTRUCT NEW RELIEF ROUTE
 
8.456 44837998.95 100498.39 47200346.66 99.9
Work Order 03-12-14
Work Began 07-21-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 679
Addl Days Granted 0
Working Days Charged 538
Percent Time Used 79
Contractor(s)
SUNDT CONSTRUCTION, INC.
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-019
MJE, LLC (2.01%)
HARDY HOLE DRILLING(1.14%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.25%)
CMT ENGINEERING, INC.(0.11%)
MCL CONTRACTING, LLC (1.29%)
DUSTROL, INC.(0.95%)
OTTO TRUCKING, INC.(4.17%)
PENHALL COMPANY(0.03%)
DUSTIN ALLEN, INC. (0.27%)
WILLIS ELECTRIC CO., LP(0.61%)
DYNAMIC VISION CO., INC. (0.18%)
DIVERSIFIED HIGHWAY PRODUCTS AND SERVICES(0.06%)
ENERGY ELECTRIC SUPPLY, INC. (0.28%)
DOUBLE A CONTRACTING, L.P. (0.37%)
CRANE SERVICES, INC. (0.18%)
LONE STAR HIGHWAY PRODUCTS, INC. (4.86%)
SILVIO LOPEZ TRUCKING(0.49%)
VULCAN MATERIAL COMPANY_(ABILENE)(1.23%)
ROBERTO MENDOZA TRUCKING (0.39%)
MAX TRUCKING (0.19%)
P & S TRUCKING (0.09%)
LAREDO PAVING, INC.(0.11%)
CMT ENGINEERING, INC.(0.12%)
AARON CONCRETE CONTRACTORS, L.P. (0.10%)
GESCH CONTRACTING, INC.(0.00%)
INSTA TURF LAWNS (0.28%)
TEXOP CONSTRUCTION (0.02%)
Contract # 12133201
Totals 44837998.95 100498.39 47200346.66 99.9

CountyHOWARD
Highway VA
From IH 20
To FM 700
CSJ 0908-12-022
Proj ID DMO 1102(493)
Work Type CONSTRUCT NEW RELIEF ROUTE
 
8.623 0.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 680
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163001
Totals 0.00 0.00 0.00 0.0

CountyFISHER
Highway CR
From ON CR 183
To AT ROUGH CREEK (PSN 1)
CSJ 0908-23-037
Proj ID BR 2013(724)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.086 1781426.00 128122.40 1783774.58 99.9
Work Order 10-30-15
Work Began 01-04-16
Work Completed  
Time Computed 12-30-15
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 144
Percent Time Used 94
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-037
S&S BRIDGE PAINTING( 15.41%)
CONTRACTORS SERVICE COMPANY(0.35%)
MORRIS COUNTY CONTRACTORS, L.L.C.(4.20%)
Contract # 08153022
Totals 1781426.00 128122.40 1783774.58 99.9

CountyHOWARD
Highway FM 821
From FM 2183
To IH 20
CSJ 1156-02-021
Proj ID STP 2015(794)
Work Type SUBGR WIDN, FL BS, 2CST, STRS, SET, MBGF
 
11.542 9379399.55 701962.46 6677440.92 71.3
Work Order 05-19-15
Work Began 06-29-15
Work Completed  
Time Computed 06-19-15
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 268
Percent Time Used 104
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1156-02-021
J.V. CONCRETE CONSTRUCTION (2.36%)
CONTRACTORS SERVICE COMPANY(0.28%)
HJC FARMS, INC.(2.54%)
BARRICADES UNLIMITED (2.68%)
Contract # 04153002
Totals 9379399.55 701962.46 6677440.92 71.3

CountySCURRY
Highway FM 1606
From SH 350
To SH 208
CSJ 1526-02-009
Proj ID STP 1502(293)
Work Type SUBGR WIDEN, FL BS, STRS, 2CST, MBGF
 
7.101 6584662.31 220485.60 5791406.02 87.9
Work Order 08-24-15
Work Began 10-14-15
Work Completed  
Time Computed 10-14-15
Contract Working Days 194
Addl Days Granted 0
Working Days Charged 193
Percent Time Used 99
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1526-02-009
W.S. CONSTRUCTION COMPANY(8.07%)
BARRICADES UNLIMITED (1.33%)
DUSTIN ALLEN, INC. (1.64%)
BLACK JACK ENERGY SERVICES ( 48.00%)
MURRAY CONSTRUCTION(0.68%)
CONTRACTORS SERVICE COMPANY(0.22%)
Contract # 06153058
Totals 6584662.31 220485.60 5791406.02 87.9

page 1 | page 2