Monthly State Let Construction Report For Abilene District As Of Aug 16, 2016 Page 1 Of 2

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOWARD
Highway IH 20
From AT US 87 (NEW LOCATION)
To .
CSJ 0005-05-102
Proj ID DMO 2012(263)
Work Type CONSTRUCT NEW INTERCHANGE
 
2.719 18434933.58 545168.26 17983158.70 97.5
Work Order 08-19-13
Work Began 05-13-14
Work Completed  
Time Computed 01-01-14
Contract Working Days 470
Addl Days Granted 59
Working Days Charged 492
Percent Time Used 93
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-102
W.S. CONSTRUCTION COMPANY(8.38%)
COPPELL CONSTRUCTION CO., INC. (8.49%)
DRILL TECH DRILLING & SHORING, INC.( 16.58%)
PRICE CONSTRUCTION, LTD. ( 28.11%)
TEXAS SHAFTS, INC. (1.76%)
FELIX CHAVEZ & SON CONSTRUCTION(0.24%)
MARTIN GONZALES INCORPORATED (1.32%)
WILLIS ELECTRIC CO., LP(2.27%)
HJC FARMS, INC.(1.58%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
TEX OP CONSTRUCTION, LP(0.23%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.50%)
ARANDA`S TRUCKING(0.74%)
NOBLES ROAD CONSTRUCTION, INC. (0.26%)
AARON CONCRETE CONTRACTORS, L.P. (0.60%)
Contract # 05133202
Totals 18434933.58 545168.26 17983158.70 97.5

CountyHOWARD
Highway BI 20-G ETC
From IH 20 WEST OF BIG SPRING
To NEAR JONES STREET
CSJ 0005-10-021
Proj ID NH 2016(203)
Work Type SEAL COAT
 
99.259 3396196.05 5000.00 3566430.40 99.9
Work Order 00-00-00
Work Began 05-09-16
Work Completed  
Time Computed 05-09-16
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 46
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-10-021
FLATE LINE, INC. ( 13.74%)
Contract # 10153218
Totals 3396196.05 5000.00 3566430.40 99.9

CountyNOLAN
Highway IH 20 ETC
From 0.037 MI W OF CR 104
To 1.1 MI E OF CR 104
CSJ 0006-02-112
Proj ID STP 2016(904)HES
Work Type HFC, TEXT CL & SHLDR, CHEVRONS
 
8.560 3498754.25 0.00 0.00 0.0
Work Order 05-12-16
Work Began 00-00-00
Work Completed  
Time Computed 06-11-16
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-112
J. H. STRAIN & SONS, INC.( 12.56%)
Contract # 04163029
Totals 3498754.25 0.00 0.00 0.0

CountyTAYLOR
Highway IH 20 ETC
From BI 20-Q (SFR ONLY)
To IH 20 EXIT RAMP 277
CSJ 0006-05-114
Proj ID STP 1602(551)HES
Work Type INSTALL ADV WARN SIGNS AND CHEVRONS
 
31.986 258628.42 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-05-114
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163009
Totals 258628.42 0.00 0.00 0.0

CountyTAYLOR
Highway US 84
From NEAR OLD BANKHEAD HWY
To NEAR US 83
CSJ 0006-18-055
Proj ID NH 2016(915)
Work Type SPOT REPAIR, MILL & OVERLAY
 
2.660 2371863.21 183512.19 875244.44 36.9
Work Order 05-19-16
Work Began 06-13-16
Work Completed  
Time Computed 06-18-16
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 54
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-18-055
A BROTHERS MILLING, LLC(2.53%)
D. I. J. CONSTRUCTION, INC.(2.25%)
CONTRACTORS SERVICE COMPANY(0.50%)
Contract # 04163231
Totals 2371863.21 183512.19 875244.44 36.9

CountyTAYLOR
Highway SH 351
From IH 20
To ABILENE EAST CITY LIMIT
CSJ 0011-01-030
Proj ID STP 1302(056)
Work Type FL BS, STRS, PCTB, C & G, SDWLK, DRVWY, SMA
 
1.768 6920469.81 74247.17 3736745.16 53.9
Work Order 04-10-15
Work Began 06-10-15
Work Completed  
Time Computed 06-10-15
Contract Working Days 270
Addl Days Granted 11
Working Days Charged 230
Percent Time Used 81
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-030
CONTRACTORS SERVICE COMPANY(0.59%)
WILLIS ELECTRIC CO., LP( 12.40%)
STRIPING TECHNOLOGY, L.P.(1.68%)
MARCOM"S MOWING SERVICE, LLC (0.26%)
O. TREVINO CONSTRUCTION, LLC (5.52%)
WOLFE CONSTRUCTION GROUP, INC. (0.91%)
BILL STARKS CONSTRUCTION COMPANY (3.42%)
JORDAN CONCRETE( 13.77%)
GONZALES CONCRETE CONTRACTORS, INC.(6.30%)
Contract # 03153036
Totals 6920469.81 74247.17 3736745.16 53.9

CountySHACKELFORD
Highway US 180 ETC
From @ US 283
To .
CSJ 0011-06-045
Proj ID STP 1602(560)HES
Work Type FLASH BEACON
 
2.390 467417.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 87
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0011-06-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163239
Totals 467417.10 0.00 0.00 0.0

CountyJONES
Highway US 83
From JUST SOUTH OF 13TH STREET IN ANSON
To NEAR US 277
CSJ 0033-04-065
Proj ID NH 2016(149)
Work Type PLANE, PVMNT REPR, UNDERSL, OVERLAY
 
2.432 4425888.54 332748.12 4088551.91 92.3
Work Order 11-24-15
Work Began 02-29-16
Work Completed  
Time Computed 02-29-16
Contract Working Days 152
Addl Days Granted 10
Working Days Charged 89
Percent Time Used 54
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-04-065
CONTRACTORS SERVICE COMPANY(0.36%)
DUSTROL, INC.(3.77%)
BONTKE BROTHERS CONSTRUCTION COMPANY (7.76%)
HJC FARMS, INC.(1.80%)
BARRICADES UNLIMITED (2.84%)
Contract # 10153018
Totals 4425888.54 332748.12 4088551.91 92.3

CountyTAYLOR
Highway BU 83-D
From HILL STREET
To NEAR IH 20
CSJ 0033-08-038
Proj ID NH 2016(916)
Work Type PLAN, STR RPR, UNDSL, ACP, MBGF, BR RL
 
7.394 9806711.43 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-20-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-08-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163008
Totals 9806711.43 0.00 0.00 0.0

CountyTAYLOR
Highway US 84
From US 83
To COLEMAN COUNTY LINE
CSJ 0054-01-031
Proj ID NH 2016(917)
Work Type SPOT REPAIR, SEAL & OVERLAY
 
11.210 7380051.17 12500.00 12500.00 0.1
Work Order 05-19-16
Work Began 07-11-16
Work Completed  
Time Computed 06-17-16
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 20
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0054-01-031
A BROTHERS MILLING, LLC(1.60%)
BARRICADES UNLIMITED (2.33%)
CONTRACTORS SERVICE COMPANY(0.16%)
WEST TEXAS RUMBLE STRIP(0.50%)
Contract # 04163216
Totals 7380051.17 12500.00 12500.00 0.1

CountyHOWARD
Highway US 87
From MARTIN COUNTY LINE
To 4.929 MI E OF MARTIN C/L (NBL ONLY)
CSJ 0068-07-050
Proj ID NH 1502(194)
Work Type PLAN, UNDSL, SUPER PAVE, MBGF
 
28.052 12331796.40 16600.00 12204046.23 98.9
Work Order 06-16-15
Work Began 10-08-15
Work Completed  
Time Computed 10-05-15
Contract Working Days 126
Addl Days Granted 10
Working Days Charged 125
Percent Time Used 91
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0068-07-050
BARRICADES UNLIMITED (1.52%)
CONTRACTORS SERVICE COMPANY(0.47%)
HJC FARMS, INC.(0.68%)
TEX OP CONSTRUCTION, LP(1.07%)
WEST TEXAS RUMBLE STRIP(0.30%)
Contract # 05153008
Totals 12331796.40 16600.00 12204046.23 98.9

CountyJONES
Highway SH 6 ETC
From BU 277-G
To SHACKELFORD COUNTY LINE
CSJ 0107-01-036
Proj ID STP 2016(305)
Work Type SEAL COAT
 
225.805 5991840.62 3069584.50 5944788.44 99.2
Work Order 12-04-15
Work Began 06-22-16
Work Completed  
Time Computed 06-09-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 56
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0107-01-036
FLATE LINE, INC. ( 11.46%)
Contract # 11153008
Totals 5991840.62 3069584.50 5944788.44 99.2

CountyCALLAHAN
Highway SH 36
From TAYLOR CO. LINE
To FM 603
CSJ 0181-02-029
Proj ID STP 2016(676)
Work Type PLAN, FLEX PAV STR RPR, SUPER PAV ACP
 
6.216 5388974.29 135697.45 770712.48 14.3
Work Order 04-01-16
Work Began 05-02-16
Work Completed  
Time Computed 05-01-16
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 28
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0181-02-029
CONTRACTORS SERVICE COMPANY(0.31%)
WOLFE CONSTRUCTION GROUP, INC. (0.11%)
JORDAN CONCRETE(0.00%)
HJC FARMS, INC.(1.13%)
WILLIS ELECTRIC CO., LP(3.82%)
DOUBLE A CONTRACTING, L.P. (3.81%)
MICA CORPORATION (1.63%)
LUZ LERMA CONSTRUCTION, INC. (2.47%)
Contract # 02163010
Totals 5388974.29 135697.45 770712.48 14.3

CountyMITCHELL
Highway SH 208
From CR 633
To COKE COUNTY LINE
CSJ 0454-03-041
Proj ID STP 2016(372)
Work Type SPOT REPAIR, UNDERSEAL, 2" OV SP - D
 
5.319 2654056.80 666719.54 2408562.35 90.7
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 06-01-16
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 73
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0454-03-041
CONTRACTORS SERVICE COMPANY(0.26%)
DOUBLE A CONTRACTING, L.P. (2.02%)
HUDSON, INC. (1.13%)
HJC FARMS, INC.(3.87%)
Contract # 10153230
Totals 2654056.80 666719.54 2408562.35 90.7

CountyTAYLOR
Highway FM 1235
From MERKEL CITY LIMIT
To CR 392
CSJ 0663-03-027
Proj ID STP 2015(789)HES
Work Type FL BS, REWK BS MATL, 2CST, CMP & SET
 
11.020 4552099.47 246525.88 1983263.03 43.5
Work Order 06-08-15
Work Began 09-08-15
Work Completed  
Time Computed 09-07-15
Contract Working Days 280
Addl Days Granted 50
Working Days Charged 59
Percent Time Used 25
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0663-03-027
CONTRACTORS SERVICE COMPANY(1.01%)
DOUBLE A CONTRACTING, L.P. (2.37%)
HJC FARMS, INC.(2.91%)
BRENDA CONSTRUCTION( 11.84%)
Contract # 04153037
Totals 4552099.47 246525.88 1983263.03 43.5

CountyTAYLOR
Highway VA
From VARIOUS LOCATIONS IN KENT,SCURRY,
To STONEWALL,AND HASKELL COUNTIES
CSJ 0908-00-080
Proj ID NH 2016(677)
Work Type INSTALL HIGH MAST ILLUMINATION
 
1.000 448260.50 11672.00 115256.89 25.7
Work Order 03-14-16
Work Began 00-00-00
Work Completed  
Time Computed 04-13-16
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-080
MICA CORPORATION ( 61.37%)
BARRICADES UNLIMITED (4.22%)
Contract # 02163037
Totals 448260.50 11672.00 115256.89 25.7

CountyHOWARD
Highway VA
From RM 33
To IH 20
CSJ 0908-12-019
Proj ID BOR 2004(670)
Work Type CONSTRUCT NEW RELIEF ROUTE
 
8.456 44837998.95 83234.60 47099848.27 99.9
Work Order 03-12-14
Work Began 07-21-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 679
Addl Days Granted 0
Working Days Charged 538
Percent Time Used 79
Contractor(s)
SUNDT CONSTRUCTION, INC.
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-019
MJE, LLC (2.01%)
HARDY HOLE DRILLING(1.14%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.25%)
CMT ENGINEERING, INC.(0.11%)
MCL CONTRACTING, LLC (1.29%)
DUSTROL, INC.(0.95%)
OTTO TRUCKING, INC.(4.17%)
PENHALL COMPANY(0.03%)
DUSTIN ALLEN, INC. (0.27%)
WILLIS ELECTRIC CO., LP(0.61%)
DYNAMIC VISION CO., INC. (0.18%)
DIVERSIFIED HIGHWAY PRODUCTS AND SERVICES(0.06%)
ENERGY ELECTRIC SUPPLY, INC. (0.28%)
DOUBLE A CONTRACTING, L.P. (0.37%)
CRANE SERVICES, INC. (0.18%)
LONE STAR HIGHWAY PRODUCTS, INC. (4.86%)
SILVIO LOPEZ TRUCKING(0.49%)
VULCAN MATERIAL COMPANY_(ABILENE)(1.23%)
ROBERTO MENDOZA TRUCKING (0.39%)
MAX TRUCKING (0.19%)
P & S TRUCKING (0.09%)
LAREDO PAVING, INC.(0.11%)
CMT ENGINEERING, INC.(0.12%)
AARON CONCRETE CONTRACTORS, L.P. (0.10%)
GESCH CONTRACTING, INC.(0.00%)
INSTA TURF LAWNS (0.28%)
TEXOP CONSTRUCTION (0.02%)
Contract # 12133201
Totals 44837998.95 83234.60 47099848.27 99.9

CountyFISHER
Highway CR
From ON CR 183
To AT ROUGH CREEK (PSN 1)
CSJ 0908-23-037
Proj ID BR 2013(724)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.086 1781426.00 163531.34 1655652.18 92.9
Work Order 10-30-15
Work Began 01-04-16
Work Completed  
Time Computed 12-30-15
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 130
Percent Time Used 85
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-037
S&S BRIDGE PAINTING( 15.41%)
CONTRACTORS SERVICE COMPANY(0.35%)
MORRIS COUNTY CONTRACTORS, L.L.C.(4.20%)
Contract # 08153022
Totals 1781426.00 163531.34 1655652.18 92.9

CountyHOWARD
Highway FM 821
From FM 2183
To IH 20
CSJ 1156-02-021
Proj ID STP 2015(794)
Work Type SUBGR WIDN, FL BS, 2CST, STRS, SET, MBGF
 
11.542 9379399.55 445854.86 5975478.46 63.7
Work Order 05-19-15
Work Began 06-29-15
Work Completed  
Time Computed 06-19-15
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 246
Percent Time Used 96
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1156-02-021
J.V. CONCRETE CONSTRUCTION (2.36%)
CONTRACTORS SERVICE COMPANY(0.28%)
HJC FARMS, INC.(2.54%)
BARRICADES UNLIMITED (2.68%)
Contract # 04153002
Totals 9379399.55 445854.86 5975478.46 63.7

CountySCURRY
Highway FM 1606
From SH 350
To SH 208
CSJ 1526-02-009
Proj ID STP 1502(293)
Work Type SUBGR WIDEN, FL BS, STRS, 2CST, MBGF
 
7.101 6584662.31 233920.20 5570920.42 84.6
Work Order 08-24-15
Work Began 10-14-15
Work Completed  
Time Computed 10-14-15
Contract Working Days 194
Addl Days Granted 0
Working Days Charged 174
Percent Time Used 89
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1526-02-009
W.S. CONSTRUCTION COMPANY(8.07%)
BARRICADES UNLIMITED (1.33%)
DUSTIN ALLEN, INC. (1.64%)
BLACK JACK ENERGY SERVICES ( 48.00%)
MURRAY CONSTRUCTION(0.68%)
CONTRACTORS SERVICE COMPANY(0.22%)
Contract # 06153058
Totals 6584662.31 233920.20 5570920.42 84.6

page 1 | page 2