Monthly State Let Maintenance Report For Abilene District As Of Sep 15, 2016 Page 1 Of 1

Last Update: Thursday, September 15, 2016
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTAYLOR
Highway IH0020
From TAYLOR, CALLAHAN, SHACKELFORD,JONES
To HASKELL, STONEWALL COUNTIES
CSJ 6249-60-001
Proj ID RMC - 624960001
Work Type ON CALL MBGF
 
0.001 569199.42 0.00 1465034.11 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-26-13
Work Began 03-27-13
Work Completed 08-17-15
Time Computed 04-02-13
Contract Working Days 365
Addl Days Granted 456
Working Days Charged 787
Percent Time Used 95
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134041
Totals 569199.42 0.00 1465034.11 100.0

CountyHOWARD
Highway IH0020
From VARIOUS LOCATIONS IN
To THE ABILENE DISTRICT
CSJ 6264-37-001
Proj ID RMC - 626437001
Work Type SEAL COAT
 
0.010 4336163.04 0.00 4510717.44 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-21-14
Work Began 03-24-14
Work Completed 08-05-14
Time Computed 04-28-14
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 67
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-37-001
TOTAL HIGHWAY MAINTENANCE, LLC (0.59%)
FLAT LINE, INC.(0.00%)
Contract # 11134023
Totals 4336163.04 0.00 4510717.44 100.0

CountySCURRY
Highway US0180
From VARIOUS LOCATIONS: SCURRY, FISHER,
To HASKELL, JONES, KENT, STONEWALL
CSJ 6276-96-001
Proj ID RMC - 627696001
Work Type CLEAN AND SEAL CRACKS AND JOINTS
 
0.001 328636.80 0.00 241844.70 73.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 12-30-14
Work Completed  
Time Computed 01-05-15
Contract Working Days 87
Addl Days Granted 0
Working Days Charged 87
Percent Time Used 100
Contractor(s)
TEXAS ROAD MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6276-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10144208
Totals 328636.80 0.00 241844.70 73.5

CountyMITCHELL
Highway IH0020
From VARIOUS ROADWAYS
To IN THE ABILENE DISTRICT
CSJ 6279-54-001
Proj ID RMC - 627954001
Work Type DISTRICT SEAL COAT
 
0.010 3122767.92 0.00 2954554.82 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-04-15
Work Began 06-02-15
Work Completed 01-07-16
Time Computed 05-11-15
Contract Working Days 32
Addl Days Granted 2
Working Days Charged 41
Percent Time Used 120
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6279-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11144201
Totals 3122767.92 0.00 2954554.82 100.0

CountyNOLAN
Highway IH0020
From VARIOUS LOCATIONS IN
To THE ABILENE DISTRICT
CSJ 6280-01-001
Proj ID RMC - 628001001
Work Type NON - SITE SPECIFIC THERMOPLASTIC STRIPING
 
0.010 1796329.00 0.00 1743730.22 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-11-15
Work Began 05-18-15
Work Completed 10-31-15
Time Computed 05-18-15
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 98
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6280-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02154014
Totals 1796329.00 0.00 1743730.22 100.0

CountyTAYLOR
Highway IH0020
From TAYLOR, CALLAHAN
To AND SHACKELFORD COUNTIES
CSJ 6283-11-001
Proj ID RMC - 628311001
Work Type ON DEMAND MBGF
 
0.010 767384.50 0.00 810490.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-25-15
Work Began 03-24-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 365
Addl Days Granted 90
Working Days Charged 455
Percent Time Used 100
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6283-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02154217
Totals 767384.50 0.00 810490.00 99.9

CountyBORDEN
Highway FM1205
From FM 1205
To FM 1054
CSJ 6288-99-001
Proj ID RMC - 628899001
Work Type ROADWAY, RIPRAP AND BRIDGE REPAIRS
 
0.010 535681.00 0.00 526708.00 99.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-14-15
Work Began 12-22-15
Work Completed  
Time Computed 12-21-15
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 119
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10154003
Totals 535681.00 0.00 526708.00 99.1

CountyTAYLOR
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6289-02-001
Proj ID RMC - 628902001
Work Type DISTRICT SEAL COAT
 
0.010 1704426.97 1271285.85 1546102.39 90.7
Work Order 03-25-16
Work Began 06-20-16
Work Completed  
Time Computed 06-20-16
Contract Working Days 33
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 81
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11154011
Totals 1704426.97 1271285.85 1546102.39 90.7

CountyNOLAN
Highway IH0020
From VARIOUS LOCATIONS IN KENT AND NOLAN
To COUNTIES
CSJ 6292-42-001
Proj ID BPM - 629242001
Work Type VARIOUS BRIDGE REPAIRS
 
0.010 354475.00 210998.90 302435.40 85.3
Work Order 06-20-16
Work Began 00-00-00
Work Completed  
Time Computed 06-20-16
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 90
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-42-001
BARRICADES UNLIMITED (0.67%)
Contract # 04164004
Totals 354475.00 210998.90 302435.40 85.3

CountyTAYLOR
Highway IH0020
From VARIOUS LOCATIONS ACROSS
To THE ABILENE DISTRICT
CSJ 6297-43-001
Proj ID RMC - 629743001
Work Type TRAFFIC CONTROL IN THE ABILENE DISTRICT
 
0.010 3286000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02164217
Totals 3286000.00 0.00 0.00 0.0

CountyHOWARD
Highway IH0020
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6297-64-001
Proj ID RMC - 629764001
Work Type INSTALL THERMOPLASTIC PAVEMENT MARKINGS
 
0.010 1513910.68 400745.40 1797026.75 99.9
Work Order 03-14-16
Work Began 03-21-16
Work Completed  
Time Computed 03-21-16
Contract Working Days 72
Addl Days Granted 18
Working Days Charged 100
Percent Time Used 111
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6297-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01164214
Totals 1513910.68 400745.40 1797026.75 99.9

CountyNOLAN
Highway IH0020
From VARIOUS ABILENE DISTRICT LOCATIONS
To VARIOUS ABILENE DISTRICT LOCATIONS
CSJ 6297-65-001
Proj ID RMC - 629765001
Work Type INSTALLATION OF RAISED PAVEMENT MARKERS
 
0.010 323490.44 0.00 490324.09 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-22-16
Work Began 03-22-16
Work Completed  
Time Computed 03-29-16
Contract Working Days 48
Addl Days Granted 26
Working Days Charged 48
Percent Time Used 64
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02164004
Totals 323490.44 0.00 490324.09 99.9

CountyHOWARD
Highway IH0020
From HOWARD,MITCHELL,NOLAN,BORDEN,SCURRY,
To KENT,STONEWALL & FISHER COUNTIES
CSJ 6300-62-001
Proj ID RMC - 630062001
Work Type ON CALL MBGF CONTRACT
 
0.010 480620.33 0.00 109388.11 22.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 16
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-62-001
ONYX FARM CONSTRUCTION, LLC( 27.71%)
Contract # 04164005
Totals 480620.33 0.00 109388.11 22.7

CountyTAYLOR
Highway IH0020
From TAYLOR, CALLAHAN, SHACKELFORD,
To JONES AND HASKELL COUNTIES
CSJ 6300-63-001
Proj ID RMC - 630063001
Work Type ON CALL MBGF CONTRACT
 
0.010 828708.36 0.00 167332.93 20.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 16
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04164202
Totals 828708.36 0.00 167332.93 20.1

CountyTAYLOR
Highway IH0020
From VARIOUS LOCATIONS IN TAYLOR, CALLAHAN
To AND NOLAN COUNTIES
CSJ 6302-57-001
Proj ID RMC - 630257001
Work Type ON CALL TRAFFIC CONTROL
 
0.010 703500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6302-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08164005
Totals 703500.00 0.00 0.00 0.0

page 1