AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - AMARILLO DISTRICT

Last Update: Friday, August 1, 2014
ITEMS 100 2002 TO 193 2001
Items Items Bid Code Range
0100 - 0193
0216 - 0260
0310 - 0361
0400 - 0496
0500 - 0560
0610 - 0690
0712 - 0751
1122 - 1122
3267 - 3271
5369 - 5910
6007 - 6834
8008 - 8999
100 2002 - 193 2001
Item No Description Units July 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 2002 PREPARING ROW STA 998.750 10.00000 2,592.720 160.04515 6
100 2004 PREPARING ROW (TREE) (12" TO 24" DIA) EA     1.000 1,270.00000 1
100 2007 PREP ROW (TREE) (GREATER THAN 24" DIA) EA     1.000 2,540.00000 1
100 2008 PREPARING ROW (TREE) (0" TO 6" DIA) EA     23.000 211.30435 3
100 2009 PREPARING ROW (TREE) (6" TO 24" DIA) EA     32.000 419.06250 4
100 2011 PREPARING ROW (TREE) (24" TO 36" DIA.) EA     4.000 985.00000 2
104 2001 REMOVING CONC (PAV) SY     1,837.000 15.00000 2
104 2009 REMOVING CONC (RIPRAP) SY     2,442.000 15.04259 3
104 2011 REMOVING CONC (MEDIANS) SY     181.000 15.00000 1
104 2017 REMOVING CONC (DRIVEWAYS) SY     243.000 15.00000 2
104 2022 REMOVING CONC (CURB AND GUTTER) LF     812.000 6.34483 2
104 2023 REMOVING CONC (CTB) LF     207.000 20.00000 1
104 2028 REMOVING CONC (MISC) SY     1,655.000 12.01813 2
104 2036 REMOVING CONC (SIDEWALK OR RAMP) SY     180.000 15.00000 1
105 2011 REMOVING STAB BASE AND ASPH PAV (2" - 6" SY     242.000 7.00000 1
105 2020 REMOVING STAB BASE & ASPH PAV (12") SY     791.000 30.00000 1
105 2061 REMOV STAB BASE & ASPH PAV (8" - 20") SY 7,584.000 10.50000 7,584.000 10.50000 1
105 2091 REMOVING STAB BASE & ASPH PAV (8" - 12") SY     3,807.000 15.00000 1
110 2001 EXCAVATION (ROADWAY) CY     197,645.000 6.52807 6
110 2002 EXCAVATION (CHANNEL) CY     3,396.000 10.16820 2
110 2003 EXCAVATION (SPECIAL) CY     172,636.000 2.25542 3
112 2002 SUBGRADE WIDENING (DENS CONT) STA 13.800 815.00000 1,167.820 244.53010 5
132 2002 EMBANKMENT (FINAL) (DENS CONT) (TY A) CY 1,700.000 28.30000 3,413.000 29.15324 2
132 2004 EMBANKMENT (FINAL) (DENS CONT) (TY B) CY     363,798.000 12.10849 5
132 2006 EMBANKMENT (FINAL) (DENS CONT) (TY C) CY     1,127.000 25.00000 1
132 2007 EMBANKMENT (FINAL) (ORD COMP) (TY D) CY     149,963.000 2.55000 1
134 2001 BACKFILL (TY A) STA 1,133.560 263.08188 4,029.890 187.95696 8
134 2004 BACKFILL (TY A OR B) STA     1,237.640 110.20584 3
150 2002 BLADING HR 466.000 262.50000 473.000 260.57082 3
158 2003 SPEC EXCAV WORK (HYD EXCAVATOR) HR 138.000 282.35000 138.000 282.35000 1
161 2008 EROSION CONTROL COMPOST (2") SY     9,174.000 3.00000 1
161 2015 COMPOST MANUF TOPSOIL (BOS OR PB) CY     483.000 42.40000 1
162 2002 BLOCK SODDING SY     1,361.000 7.87274 2
164 2002 BROADCAST SEED (PERM) (RURAL) (SANDY) AC 46.220 700.00000 46.450 704.45640 2
164 2004 BROADCAST SEED (PERM) (RURAL) (CLAY) AC     8.920 708.75000 1
164 2012 BROADCAST SEED (TEMP) (COOL) AC 46.220 600.00000 56.970 649.14955 3
164 2022 CELL FBR MLCH SEED (PERM) (RURAL) (SANDY) AC     3.700 2,421.62162 2
164 2024 CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) AC     20.540 1,460.00000 1
164 2033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY 156,391.000 .17000 173,203.000 .18947 3
164 2034 DRILL SEEDING (PERM) (RURAL) (SANDY) AC     154.480 589.04829 7
164 2036 DRILL SEEDING (PERM) (RURAL) (CLAY) AC     176.650 734.24285 3
164 2043 DRILL SEEDING (TEMP) (COOL) SY     2,967.000 .65000 1
164 2044 DRILL SEEDING (TEMP) (COOL) AC     99.370 501.99306 4
164 2051 DRILL SEED (TEMP) (WARM OR COOL) SY 156,391.000 .15000 170,236.000 .16220 2
164 2053 DRILL SEEDING (TEMP) (WARM OR COOL) AC     250.870 691.70945 5
168 2001 VEGETATIVE WATERING MG 9,036.000 13.54261 38,993.270 13.24084 17
169 2001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY     2,049.000 3.15000 1
169 2002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY     354.000 5.00000 1
169 2003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY     220.000 3.00000 1
169 2004 SOIL RETENTION BLANKETS (CL 1) (TY D) SY     9,210.000 1.94123 3
169 2005 SOIL RETENTION BLANKETS (CL 2) (TY E) SY     1,107.000 5.00000 1
169 2006 SOIL RETENTION BLANKETS (CL 2) (TY F) SY     761.000 6.00000 1
169 2007 SOIL RETENTION BLANKETS (CL 2) (TY G) SY     3,623.000 3.50000 1
192 2013 MULCH SY     921.000 7.90000 1
192 2016 PLANT BED PREPARATION SY     921.000 7.90000 1
192 2017 VEGETATION BARRIER SY     921.000 5.25000 1
192 2030 PLANT MATERIAL (3 GAL) (SHRUB) EA     570.000 94.50000 1
193 2001 PLANT MAINTENANCE MO     3.000 2,625.00000 1