Monthly State Let Construction Report For Amarillo District As Of Sep 15, 2016 Page 1 Of 2

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyOCHILTREE
Highway US 83 ETC
From OKLAHOMA STATE LINE
To SH 15
CSJ 0030-01-031
Proj ID STP 2015(797)HES
Work Type CENTERLINE TEXTURING
 
240.957 1135663.16 0.00 795851.01 70.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-08-15
Work Began 05-14-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 96
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-01-031
RED 16 CONSTRUCTION( 21.46%)
Contract # 04153031
Totals 1135663.16 0.00 795851.01 70.0

CountyOCHILTREE
Highway US 83 ETC
From OKLAHOMA STATE LINE
To SH 15
CSJ 0030-01-032
Proj ID STP 2016(152)
Work Type SEALCOAT
 
223.251 7967738.81 3124435.54 6896333.10 86.5
Work Order 01-29-16
Work Began 07-18-16
Work Completed  
Time Computed 02-29-16
Contract Working Days 94
Addl Days Granted 0
Working Days Charged 85
Percent Time Used 90
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153025
Totals 7967738.81 3124435.54 6896333.10 86.5

CountyLIPSCOMB
Highway US 83
From OCHILTREE COUNTY LINE
To HEMPHILL COUNTY LINE
CSJ 0030-04-017
Proj ID STP 2015(471)
Work Type RESTORATION OF EXISTING ROADWAY
 
3.242 2804932.54 0.00 2890854.54 99.9
CountyHEMPHILL
Highway US 83
From HORSE CREEK
To US 60
CSJ 0030-05-063
Proj ID STP 2015(471)
Work Type RESTORATION
 
5.995 4693999.68 2054733.80 3852504.88 82.0
Work Order 03-03-15
Work Began 08-06-15
Work Completed  
Time Computed 07-01-15
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 88
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-05-063
ALTUS TRAFFIC MANAGEMENT LLC (0.20%)
BARRICADES UNLIMITED (0.70%)
DUSTROL, INC.(4.07%)
MARCOM"S MOWING SERVICE, LLC (0.29%)
ODUM SERVICES, L.P.(5.33%)
SCR CONSTRUCTION CO., INC. (0.63%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.09%)
TEXAS ALTERNATIVE GRASSER, INC.(0.33%)
VANCE BROTHERS, INC. (2.41%)
Contract # 01153003
Totals 7498932.22 2054733.80 6743359.42 89.9

CountyHEMPHILL
Highway US 60
From US 83/ US 60 INTERCHANGE
To CANADIAN
CSJ 0030-06-056
Proj ID NH 1502(077)
Work Type REHAB EXISTING ROADWAY
 
6.372 12716824.29 1479594.39 4708089.50 37.0
CountyHEMPHILL
Highway US 60
From US 83
To LIPSCOMB COUNTY LINE
CSJ 0170-01-032
Proj ID NH 1502(077)
Work Type REHAD EXISTING ROADWAY
 
13.300 6889749.10 369963.98 7644107.08 99.9
Work Order 07-10-15
Work Began 04-11-16
Work Completed  
Time Computed 05-01-16
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 54
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-056
BARRICADES UNLIMITED (0.93%)
HJC FARMS, INC.(5.33%)
HUDSON, INC. (1.75%)
INDUSTRIAL FABRICS, INC. (3.40%)
PRIMATE CONSTRUCTION, INC. (0.05%)
SAENZ TRANSPORT, LLC (0.00%)
SILVER CREEK CONSTRUCTION, INC.(3.12%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.07%)
TEXAS ALTERNATIVE GRASSER, INC.(0.06%)
ROCK HARD TRUCKING LLC (0.00%)
Contract # 05153004
Totals 19606573.39 1849558.37 12352196.58 63.0

CountyDALLAM
Highway US 87 ETC
From US 54
To LINCOLN STREET
CSJ 0040-03-059
Proj ID NH 1502(569)
Work Type UPGRADE TO STANDARDS NON - FREEWAY
 
4.356 26321210.00 845805.01 8179818.83 31.0
Work Order 02-02-16
Work Began 03-14-16
Work Completed  
Time Computed 03-03-16
Contract Working Days 443
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 11
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-059
BARRICADES UNLIMITED (0.31%)
A BROTHERS MILLING, LLC(1.02%)
TLJ LINING CO. (0.09%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.38%)
MCL CONTRACTING, LLC (0.02%)
G AND G OPERATORS, LTD.(4.59%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.32%)
J. LEE MILLIGAN, INC.( 16.97%)
PRIMATE CONSTRUCTION, INC. (0.71%)
BREDA COMPANY, INC.(0.74%)
KLP COMMERCIAL, LLC(4.23%)
FARR FOUNDATION, INC.(0.83%)
AR DANIEL CONSTRUCTION SERVICES, INC.(0.48%)
SIGNAL SERVICES GROUP INC. (2.60%)
Contract # 08153216
Totals 26321210.00 845805.01 8179818.83 31.0

CountyHARTLEY
Highway US 87
From DALHART
To HARTLEY
CSJ 0041-01-045
Proj ID NH 2015(298)
Work Type REHAB EXISTING ROADWAY
 
12.048 6272205.98 81056.24 6188653.79 98.6
CountyHARTLEY
Highway US 87
From DALHART
To HARTLEY
CSJ 0041-01-046
Proj ID NH 2015(298)
Work Type REHAB EXISITNG ROADWAY
 
12.002 2901153.68 180382.60 3622271.65 99.9
Work Order 01-02-15
Work Began 07-28-15
Work Completed  
Time Computed 07-28-15
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 95
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-01-045
BARRICADES UNLIMITED (1.62%)
HJC FARMS, INC.(1.64%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.29%)
TEXOP CONSTRUCTION (3.88%)
J C DIAZ TRUCKING(3.00%)
CF TRUCKING, LLC (1.28%)
Contract # 11143204
Totals 9173359.66 261438.84 9810925.44 99.9

CountyHARTLEY
Highway US 385
From SH 354 IN CHANNING
To US 87
CSJ 0041-02-014
Proj ID STP 2016(512)
Work Type OVERLAY
 
38.156 6104315.43 711383.05 6078406.54 99.5
Work Order 03-02-16
Work Began 05-23-16
Work Completed  
Time Computed 05-16-16
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 80
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-02-014
BARRICADES UNLIMITED (1.42%)
DUSTROL, INC.(6.10%)
DUSTIN ALLEN, INC. (0.76%)
SCR CONSTRUCTION CO., INC. (2.70%)
WOLFE CONSTRUCTION GROUP, INC. (0.56%)
DIAMOND SURFACE, INC.(0.33%)
Contract # 01163026
Totals 6104315.43 711383.05 6078406.54 99.5

CountyPOTTER
Highway US 87
From AT MOBLEY AVE
To .
CSJ 0041-07-100
Proj ID BR 2013(374)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 1688123.28 0.00 1833189.91 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-19-13
Work Began 06-07-13
Work Completed  
Time Computed 05-05-13
Contract Working Days 86
Addl Days Granted 11
Working Days Charged 78
Percent Time Used 80
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-100
HIGHWAY TECHNOLOGIES, INC. (0.58%)
L. A. FULLER & SONS CONSTRUCTION, LTD. (3.06%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.13%)
SCOTT DERR PAINTING CO (0.41%)
VANN/ELLI, INC.(7.15%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(0.57%)
NORTH TEXAS REBAR, LLC (0.24%)
WEST TEXAS BARRICADE AND LIGHT CO. (0.94%)
LANCO TURF & SEEDING, INC. (0.00%)
Contract # 02133224
Totals 1688123.28 0.00 1833189.91 99.9

CountyARMSTRONG
Highway US 287 ETC
From FM 294
To DONLEY COUNTY LINE
CSJ 0042-05-030
Proj ID STP 2014(461)HESG
Work Type TEXTURIZE SHOULDERS
 
146.790 268557.49 0.00 349963.87 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 10-27-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 34
Addl Days Granted 18
Working Days Charged 31
Percent Time Used 59
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-05-030
RED SIXTEEN CONSTRUCTION, INC( 29.96%)
Contract # 03143004
Totals 268557.49 0.00 349963.87 99.9

CountyMOORE
Highway US 287
From FM 281
To SHERMAN COUNTY LINE
CSJ 0066-04-074
Proj ID NH 2013(610)
Work Type REHABILITATION
 
2.256 3826918.47 22820.60 3334617.87 87.1
Work Order 09-24-14
Work Began 07-15-15
Work Completed  
Time Computed 04-06-15
Contract Working Days 77
Addl Days Granted 5
Working Days Charged 71
Percent Time Used 86
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0066-04-074
BARRICADES UNLIMITED (1.26%)
BARRICADES UNLIMITED (1.26%)
MPB, INC.(3.18%)
HJC FARMS, INC.(1.78%)
J C DIAZ TRUCKING(3.50%)
Contract # 07143031
Totals 3826918.47 22820.60 3334617.87 87.1

CountyOLDHAM
Highway IH 40
From 6.2 MI E OF NEW MEXICO STATE LINE
To 11.2 MI E OF NEW MEXICO STATE LINE
CSJ 0090-02-052
Proj ID IM 0401(210)
Work Type OVERLAY
 
5.016 2378425.51 0.00 2375088.23 99.9
CountyOLDHAM
Highway IH 40
From 0.23 MI WEST OF FM 2858
To 0.25 MI EAST OF SH 214
CSJ 0090-03-058
Proj ID IM 0401(210)
Work Type OVERLAY
 
6.662 3012317.95 0.00 3124738.68 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 12-15-14
Work Completed  
Time Computed 04-15-14
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 215
Percent Time Used 186
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-02-052
E. DIAZ TRUCKING (5.15%)
HOLMES CONSTRUCTION CO., L.P.(1.41%)
LANCO TURF & SEEDING, INC. (0.73%)
LONE STAR BARRIER SERVICES, LLC(2.57%)
A BROTHERS MILLING, LLC(0.98%)
BARRICADES UNLIMITED (1.57%)
COWBELL TRAFFIC SERVICES, INC. (0.52%)
Contract # 02143021
Totals 5390743.46 0.00 5499826.91 99.9

CountyPOTTER
Highway US 60
From ON BUCHANAN FROM 11TH TO 6TH
To ON 6TH FROM FILLMORE TO PIERCE
CSJ 0168-10-069
Proj ID STP 2014(103)TE
Work Type TRANSPORTION ENHANCEMENT
 
0.363 2147565.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-05-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-10-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163222
Totals 2147565.30 0.00 0.00 0.0

CountyROBERTS
Highway US 60 ETC
From .556 MI W OF RM 748
To GRAY COUNTY LINE
CSJ 0169-08-022
Proj ID STP 2016(515)HESG
Work Type CENTERLINE TEXTURING
 
227.625 996579.09 0.00 559683.06 56.1
Work Order 03-09-16
Work Began 03-21-16
Work Completed  
Time Computed 04-08-16
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 60
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0169-08-022
WEST TEXAS RUMBLE STRIP( 11.08%)
Contract # 01163237
Totals 996579.09 0.00 559683.06 56.1

CountyDEAF SMITH
Highway US 385
From .8 MILE SOUTH OF FM 1062
To 1 MILE SOUTH OF OLDHAM COUNTY LINE
CSJ 0226-04-025
Proj ID STP 2016(680)
Work Type RESTORATION
 
22.908 8318208.26 0.00 0.00 0.0
Work Order 03-08-16
Work Began 00-00-00
Work Completed  
Time Computed 03-08-16
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 29
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0226-04-025
BARRICADES UNLIMITED (0.99%)
DUSTROL, INC.(1.14%)
HJC FARMS, INC.(0.72%)
DIAMOND SURFACE, INC.(0.25%)
HARDY TREES, INC.(0.43%)
Contract # 02163229
Totals 8318208.26 0.00 0.00 0.0

CountySHERMAN
Highway US 54
From STRATFORD CITY LIMITS
To OKLAHOMA STATE LINE
CSJ 0238-06-029
Proj ID NH 2016(682)
Work Type OVERLAY
 
18.631 7825684.43 0.00 1126444.56 14.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 5
Contractor(s)
HIGHWAY CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-06-029
BARRICADES UNLIMITED (1.19%)
WOLFE CONSTRUCTION GROUP, INC. (0.27%)
WEST TEXAS RUMBLE STRIP(0.10%)
CUTTING EDGE MOWING SERVIES, LLC (0.00%)
STAN"S ASPHALT & CONSTRUCTION(1.57%)
TRIPLE F TRUCKING, LLC (3.37%)
Contract # 02163007
Totals 7825684.43 0.00 1126444.56 14.3

CountyPOTTER
Highway IH 40
From LP 335
To COULTER ST
CSJ 0275-01-160
Proj ID NH 1402(018)
Work Type RELOCATE ENTRANCE AND EXIT RAMPS
 
0.972 5438822.45 0.00 4289860.37 78.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-04-14
Work Began 02-02-15
Work Completed  
Time Computed 11-20-14
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 85
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-160
ALAMO BROTHERS CONCRETE( 11.70%)
BARRICADES UNLIMITED (1.33%)
WILLIS ELECTRIC CO., LP(3.75%)
MICA CORPORATION (1.91%)
Contract # 08143238
Totals 5438822.45 0.00 4289860.37 78.9

CountyPOTTER
Highway IH 40 ETC
From HELIUM ROAD
To EAST OF SL 335
CSJ 0275-01-166
Proj ID NH 1502(372)
Work Type RELOCATE ENTRANCE AND EXIT RAMPS
 
5.179 26403959.25 1682327.48 12744362.76 48.2
Work Order 10-06-15
Work Began 01-25-16
Work Completed  
Time Computed 11-02-15
Contract Working Days 560
Addl Days Granted 12
Working Days Charged 147
Percent Time Used 25
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-166
ALAMO BROTHERS CONCRETE(4.85%)
DUSTIN ALLEN, INC. (0.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.47%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.23%)
WILLIS ELECTRIC CO., LP( 10.58%)
MCL CONTRACTING, LLC (0.16%)
MICA CORPORATION (3.01%)
L. A. FULLER & SONS CONSTRUCTION, LTD. ( 19.71%)
SCOTT DERR PAINTING CO, LLC(0.16%)
BREDA COMPANY, INC.(2.66%)
BARRICADES UNLIMITED (0.95%)
TRUMBLE CRANE & RIGGING(0.23%)
A BROTHERS MILLING, LLC(0.23%)
WOLFE CONSTRUCTION GROUP, INC. (0.04%)
TRI-STATE OILFIELD SERVICES, INC.(0.02%)
JOSH FRANKLIN DRILLING, LLC(0.04%)
OSCAR ORDUNO, INC. (1.84%)
MCL CONTRACTING, LLC (0.01%)
ALAMO BROTHERS CONCRETE(0.20%)
Contract # 07153253
Totals 26403959.25 1682327.48 12744362.76 48.2

CountyPOTTER
Highway IH 40
From AT SL335 (LAKESIDE)
To .
CSJ 0275-01-168
Proj ID NH 1502(349)
Work Type CONSTRUCT TURNAROUNDS
 
0.340 2519584.25 -1310456.11 2957500.10 99.9
CountyRANDALL
Highway SL 335
From 0.13 MILES EAST OF GEORGIA ST.
To 0.26 MILES WEST OF FM 1541
CSJ 2635-02-028
Proj ID STP 2013(605)
Work Type CONVERT NON - FREEWAY TO FREEWAY
 
0.808 17821897.20 2399627.79 12572727.25 70.0
Work Order 07-31-15
Work Began 08-10-15
Work Completed  
Time Computed 08-10-15
Contract Working Days 460
Addl Days Granted 0
Working Days Charged 260
Percent Time Used 56
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-028
TRUMBLE CRANE & RIGGING(0.21%)
DUSTIN ALLEN, INC. (1.07%)
L. A. FULLER & SONS CONSTRUCTION, LTD. ( 22.92%)
WILLIS ELECTRIC CO., LP(1.80%)
OSCAR ORDUNO, INC. (3.65%)
BARRICADES UNLIMITED (0.65%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.67%)
INDUS CONSTRUCTION, L.P. (1.34%)
MCL CONTRACTING, LLC (0.13%)
BREDA COMPANY, INC.(3.57%)
ALAMO BROTHERS CONCRETE(0.42%)
CINTEREX US, INC.(0.21%)
WOLFE CONSTRUCTION GROUP, INC. (0.07%)
A BROTHERS MILLING, LLC(0.64%)
PENHALL COMPANY(0.09%)
LLOYD D. NABORS DEMOLITION LLC (0.62%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
J. LEE MILLIGAN, INC.(0.55%)
DISCOUNT FENCE COMPANY (0.10%)
Contract # 04153057
Totals 20341481.45 1089171.68 15530227.35 75.9

CountyPOTTER
Highway IH 40
From 0.15 MILES WEST OF WASHINGTON ST
To NELSON STREET
CSJ 0275-01-177
Proj ID NH 1602(189)
Work Type REHAB EXISTING ROADWAY
 
2.977 36259776.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 332
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-177
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163003
Totals 36259776.70 0.00 0.00 0.0

CountyGRAY
Highway IH 40
From ALANREED
To DONLEY COUNTY LINE
CSJ 0275-11-077
Proj ID NH 1502(079)
Work Type OVERLAY AND MINOR BRIDGE MAINTENANC
 
9.571 3565812.59 3146991.00 3167991.00 88.8
Work Order 06-15-15
Work Began 08-01-16
Work Completed  
Time Computed 09-01-15
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 52
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-11-077
BARRICADES UNLIMITED (2.13%)
HJC FARMS, INC.(1.19%)
O. TREVINO CONSTRUCTION, LLC (5.61%)
TEX OP CONSTRUCTION, LP(1.79%)
WEST TEXAS RUMBLE STRIP(0.11%)
Contract # 05153223
Totals 3565812.59 3146991.00 3167991.00 88.8

page 1 | page 2