Monthly State Let Construction Report For Amarillo District As Of Feb 11, 2016 Page 1 Of 4

Last Update: Thursday, February 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyOCHILTREE
Highway US 83 ETC
From OKLAHOMA STATE LINE
To SH 15
CSJ 0030-01-031
Proj ID STP 2015(797)HES
Work Type CENTERLINE TEXTURING
 
240.957 1135663.16 0.07 789855.58 69.5
Work Order 05-08-15
Work Began 05-14-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 96
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-01-031
RED 16 CONSTRUCTION( 21.46%)
Contract # 04153031
Totals 1135663.16 0.07 789855.58 69.5

CountyOCHILTREE
Highway US 83 ETC
From OKLAHOMA STATE LINE
To SH 15
CSJ 0030-01-032
Proj ID STP 2016(152)
Work Type SEALCOAT
 
223.251 7967738.81 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 94
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153025
Totals 7967738.81 0.00 0.00 0.0

CountyOCHILTREE
Highway US 83
From 6TH AVE
To 13TH AVE
CSJ 0030-02-042
Proj ID STP 2011(262)TE
Work Type PERRYTON MAIN ST ENHANCEMENT II
 
0.494 1347836.50 0.00 1420003.44 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-26-12
Work Began 05-14-12
Work Completed 10-16-15
Time Computed 05-12-12
Contract Working Days 150
Addl Days Granted 33
Working Days Charged 411
Percent Time Used 224
Contractor(s)
B&B SOLVENT, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-042
B & G ELECTRIC ( 55.08%)
Contract # 02123231
Totals 1347836.50 0.00 1420003.44 100.0

CountyOCHILTREE
Highway US 83
From WOLF CREEK BRIDGE
To 1.4 MILES N OF NORTHUP CREEK
CSJ 0030-03-023
Proj ID STP 2011(209)ES
Work Type REHABILITATE EXISTING ROADWAY
 
6.535 5839756.54 0.00 6706097.04 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-06-10
Work Began 01-25-11
Work Completed 01-12-15
Time Computed 12-22-10
Contract Working Days 259
Addl Days Granted 129
Working Days Charged 497
Percent Time Used 128
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0030-03-023
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(1.70%)
CUTRELL TRUCKING COMPANY, INC. (4.54%)
JONA CONTRACTING, INC. (0.74%)
TEXAS ALTERNATIVE GRASSER, INC.(0.86%)
G. B. & G TRANSPORT, LLP (1.38%)
E. DIAZ TRUCKING (0.00%)
Contract # 10103004
Totals 5839756.54 0.00 6706097.04 100.0

CountyOCHILTREE
Highway US 83
From 1.4 MILES N OF NORTHUP CREEK
To LIPSCOMB COUNTY LINE
CSJ 0030-03-025
Proj ID STP 1102(341)
Work Type REHABILITATE EXISTING ROADWAY
 
11.232 11848782.75 0.00 12174086.68 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-19-11
Work Began 09-06-11
Work Completed 06-05-14
Time Computed 09-04-11
Contract Working Days 300
Addl Days Granted 162
Working Days Charged 581
Percent Time Used 125
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0030-03-025
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.96%)
CUTRELL TRUCKING COMPANY, INC. (3.86%)
G. B. & G TRANSPORT, LLP (3.78%)
J. V. CONSTRUCTION (2.53%)
TEXAS ALTERNATIVE GRASSER, INC.(0.97%)
COLORADO DOUBLE D CONSTRUCTION LLC (1.25%)
E. DIAZ TRUCKING (1.36%)
Contract # 06113248
Totals 11848782.75 0.00 12174086.68 100.0

CountyLIPSCOMB
Highway US 83
From OCHILTREE COUNTY LINE
To HEMPHILL COUNTY LINE
CSJ 0030-04-017
Proj ID STP 2015(471)
Work Type RESTORATION OF EXISTING ROADWAY
 
3.242 2804932.54 0.00 2890854.54 99.9
CountyHEMPHILL
Highway US 83
From HORSE CREEK
To US 60
CSJ 0030-05-063
Proj ID STP 2015(471)
Work Type RESTORATION
 
5.995 4693999.68 0.00 1004787.03 21.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-03-15
Work Began 08-06-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 48
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-05-063
ALTUS TRAFFIC MANAGEMENT LLC (0.20%)
BARRICADES UNLIMITED (0.70%)
DUSTROL, INC.(4.07%)
MARCOM"S MOWING SERVICE, LLC (0.29%)
ODUM SERVICES, L.P.(5.33%)
SCR CONSTRUCTION CO., INC. (0.63%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.09%)
TEXAS ALTERNATIVE GRASSER, INC.(0.33%)
Contract # 01153003
Totals 7498932.22 0.00 3895641.57 51.9

CountyHEMPHILL
Highway US 83
From LIPSCOMB COUNTY LINE
To HORSE CREEK
CSJ 0030-05-062
Proj ID STP 2013(003)
Work Type REHAB EXISTING RDWY
 
6.267 4019598.98 0.00 3854539.98 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-09-12
Work Began 04-11-13
Work Completed 06-05-14
Time Computed 11-25-12
Contract Working Days 85
Addl Days Granted 60
Working Days Charged 172
Percent Time Used 118
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-05-062
KOSS CONSTRUCTION COMPANY( 24.72%)
O. TREVINO CONSTRUCTION, LLC (5.11%)
AMARILLO RMT ENTERPRISE(0.54%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(2.65%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (1.46%)
Contract # 09123220
Totals 4019598.98 0.00 3854539.98 100.0

CountyHEMPHILL
Highway US 83
From US 60
To FM 277
CSJ 0030-06-054
Proj ID STP 2014(267)
Work Type REHAB EXISTING ROADWAY
 
7.727 3013000.70 0.00 3335678.35 100.0
CountyHEMPHILL
Highway US 83
From FM 277
To 1.66 MILES SOUTH OF FM 277
CSJ 0030-07-018
Proj ID STP 2014(267)
Work Type REHAB EXISTING ROADWAY
 
1.662 503833.28 0.00 494317.95 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 06-11-14
Work Completed 10-31-14
Time Computed 02-02-14
Contract Working Days 50
Addl Days Granted 5
Working Days Charged 53
Percent Time Used 96
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-054
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
BARRICADES UNLIMITED (1.88%)
DUSTROL, INC.(0.49%)
LANCO TURF & SEEDING, INC. (0.69%)
TEX OP CONSTRUCTION, LP(0.70%)
Contract # 12133015
Totals 3516833.98 0.00 3829996.30 100.0

CountyHEMPHILL
Highway US 60
From US 83/ US 60 INTERCHANGE
To CANADIAN
CSJ 0030-06-056
Proj ID NH 1502(077)
Work Type REHAB EXISTING ROADWAY
 
6.372 12716824.29 0.00 0.00 0.0
CountyHEMPHILL
Highway US 60
From US 83
To LIPSCOMB COUNTY LINE
CSJ 0170-01-032
Proj ID NH 1502(077)
Work Type REHAD EXISTING ROADWAY
 
13.300 6889749.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-10-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153004
Totals 19606573.39 0.00 0.00 0.0

CountyHEMPHILL
Highway US 83
From 1.66 MILES SOUTH OF FM 277
To WHEELER COUNTY LINE
CSJ 0030-07-017
Proj ID STP 2013(236)
Work Type REHAB EXISTING ROADWAY
 
3.671 1972769.95 0.00 1893858.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-13
Work Began 06-10-13
Work Completed 10-08-14
Time Computed 03-22-13
Contract Working Days 64
Addl Days Granted 70
Working Days Charged 223
Percent Time Used 166
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0030-07-017
BARRICADES UNLIMITED (3.06%)
COWBELL TRAFFIC SERVICES, INC. (0.45%)
E. DIAZ TRUCKING (2.80%)
TEXAS ALTERNATIVE GRASSER, INC.(0.36%)
TEX OP CONSTRUCTION, LP(1.79%)
Contract # 12123020
Totals 1972769.95 0.00 1893858.50 100.0

CountyDALLAM
Highway US 87 ETC
From NEW MEXICO STATE LINE
To 3.6 MILES N OF FM 3110
CSJ 0040-01-046
Proj ID NH 2014(059)
Work Type SEAL COAT
 
308.345 10070696.74 0.00 9976282.26 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 06-16-14
Work Completed 12-16-14
Time Computed 02-28-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 100
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0040-01-046
FLAT LINE, INC.(4.26%)
FLASHER EQUIPMENT COMPANY(1.22%)
Contract # 10133003
Totals 10070696.74 0.00 9976282.26 100.0

CountyDALLAM
Highway US 87 ETC
From 3.6 MILES NW OF FM 3110
To 0.9 MILES001007051 1879
CSJ 0040-02-021
Proj ID NH 2015(054)
Work Type SEALCOAT
 
304.766 9457160.58 0.00 9271478.63 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-05-15
Work Began 06-25-15
Work Completed 10-30-15
Time Computed 01-21-15
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 100
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-02-021
COX PAVING COMPANY OF TEXAS, INC.( 18.00%)
FLAT LINE, INC.(4.53%)
Contract # 09143202
Totals 9457160.58 0.00 9271478.63 100.0

CountyDALLAM
Highway US 87 ETC
From US 54
To LINCOLN STREET
CSJ 0040-03-059
Proj ID NH 1502(569)
Work Type UPGRADE TO STANDARDS NON - FREEWAY
 
4.356 26321210.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-02-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 443
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153216
Totals 26321210.00 0.00 0.00 0.0

CountyHARTLEY
Highway US 87
From DALHART
To HARTLEY
CSJ 0041-01-045
Proj ID NH 2015(298)
Work Type REHAB EXISTING ROADWAY
 
12.048 6272205.98 0.00 3608560.30 57.5
CountyHARTLEY
Highway US 87
From DALHART
To HARTLEY
CSJ 0041-01-046
Proj ID NH 2015(298)
Work Type REHAB EXISITNG ROADWAY
 
12.002 2901153.68 0.00 141264.64 4.8
Work Order 01-02-15
Work Began 07-28-15
Work Completed  
Time Computed 07-28-15
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 47
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-01-045
BARRICADES UNLIMITED (1.62%)
HJC FARMS, INC.(1.64%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.29%)
TEXOP CONSTRUCTION (3.88%)
J C DIAZ TRUCKING(3.00%)
Contract # 11143204
Totals 9173359.66 0.00 3749824.94 40.8

CountyHARTLEY
Highway US 385
From SH 354 IN CHANNING
To US 87
CSJ 0041-02-014
Proj ID STP 2016(512)
Work Type OVERLAY
 
38.156 6104315.43 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-02-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163026
Totals 6104315.43 0.00 0.00 0.0

CountyPOTTER
Highway US 87
From AT CANADIAN RIVER
To .
CSJ 0041-05-047
Proj ID BR 2013(774)
Work Type REPLACE BRIDGE & APPR
 
0.161 3326900.41 0.00 3412543.11 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-22-13
Work Began 09-09-13
Work Completed 09-23-15
Time Computed 09-07-13
Contract Working Days 290
Addl Days Granted 15
Working Days Charged 305
Percent Time Used 100
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0041-05-047
L. A. FULLER & SONS CONSTRUCTION, LTD. ( 17.61%)
TEXAS ALTERNATIVE GRASSER, INC.(0.22%)
BARRICADES UNLIMITED (1.45%)
E. DIAZ TRUCKING (0.63%)
HJC FARMS, INC.(1.87%)
MCL CONTRACTING, LLC (3.30%)
SCOTT DERR PAINTING CO (0.29%)
WEST TEXAS RUMBLE STRIP(0.11%)
SHINN & GREGORY, INC.(2.51%)
TEX OP CONSTRUCTION, LP(0.75%)
PRIMATE CONSTRUCTION, INC. (0.37%)
Contract # 06133219
Totals 3326900.41 0.00 3412543.11 100.0

CountyPOTTER
Highway US 87
From AT LP 335 (ST FRANCIS AVE)
To .
CSJ 0041-07-097
Proj ID BR 2012(362)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.126 2245899.16 0.00 2229293.89 100.0
CountyPOTTER
Highway US 87
From AT WILLOW CREEK DR
To .
CSJ 0041-07-098
Proj ID BR 2012(362)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.099 1135322.53 0.00 1186252.35 100.0
CountyPOTTER
Highway US 87
From AT CHERRY AVE
To .
CSJ 0041-07-099
Proj ID BR 2012(362)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.102 1164718.11 0.00 1199357.09 100.0
CountyPOTTER
Highway US 87
From AT FM 1719
To .
CSJ 0041-07-101
Proj ID BR 2012(362)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.093 1115502.85 0.00 1124424.25 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-17-12
Work Began 06-04-12
Work Completed 08-26-14
Time Computed 05-03-12
Contract Working Days 556
Addl Days Granted 0
Working Days Charged 547
Percent Time Used 98
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-097
HOLMES CONSTRUCTION CO., L.P.(7.77%)
HOUSTON SAWING & DRILLING(0.19%)
LANCO TURF & SEEDING, INC. (0.08%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.80%)
RAY ELECTRIC COMPANY (0.15%)
SCOTT DERR PAINTING CO (0.62%)
SHINN & GREGORY, INC.(1.50%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.57%)
DUSTIN ALLEN, INC. (2.49%)
GARY A. CRAIN, INC.(0.09%)
NORTH TEXAS REBAR, LLC (0.34%)
Contract # 03123209
Totals 5661442.65 0.00 5739327.58 100.0

CountyPOTTER
Highway US 87
From AT MOBLEY AVE
To .
CSJ 0041-07-100
Proj ID BR 2013(374)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 1688123.28 0.00 1833189.91 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-19-13
Work Began 06-07-13
Work Completed  
Time Computed 05-05-13
Contract Working Days 86
Addl Days Granted 11
Working Days Charged 78
Percent Time Used 80
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-100
HIGHWAY TECHNOLOGIES, INC. (0.58%)
L. A. FULLER & SONS CONSTRUCTION, LTD. (3.06%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.13%)
SCOTT DERR PAINTING CO (0.41%)
VANN/ELLI, INC.(7.15%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(0.57%)
NORTH TEXAS REBAR, LLC (0.24%)
WEST TEXAS BARRICADE AND LIGHT CO. (0.94%)
LANCO TURF & SEEDING, INC. (0.00%)
Contract # 02133224
Totals 1688123.28 0.00 1833189.91 99.9

CountyPOTTER
Highway US 87
From LP 335
To AMARILLO CREEK
CSJ 0041-07-102
Proj ID NH 2014(754)
Work Type OVERLAY (SB LANES)
 
8.953 2545207.72 9026.85 2701525.60 99.9
Work Order 08-13-14
Work Began 09-22-15
Work Completed  
Time Computed 08-03-15
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 61
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-102
BARRICADES UNLIMITED (1.74%)
ALTUS TRAFFIC MANAGEMENT LLC (0.90%)
DUSTROL, INC.(3.73%)
LANCO TURF & SEEDING, INC. (0.79%)
CF TRUCKING, LLC (3.00%)
Contract # 06143035
Totals 2545207.72 9026.85 2701525.60 99.9

CountyPOTTER
Highway US 87
From 11TH STREET IN AMARILLO
To SL 335
CSJ 0041-07-104
Proj ID NH 1502(078)
Work Type OVERLAY
 
2.800 2367194.77 0.00 15104.00 0.6
Work Order 06-15-15
Work Began 00-00-00
Work Completed  
Time Computed 07-16-15
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153041
Totals 2367194.77 0.00 15104.00 0.6

page 1 | page 2 | page 3 | page 4