Monthly State Let Construction Report For Amarillo District As Of Dec 10, 2014 Page 2 Of 3

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRANDALL
Highway US 60
From AT CR 214 (BUFFALO STD)
To .
CSJ 0168-09-163
Proj ID BR 2014(936)
Work Type REPLACE BRIDGE
 
0.059 2174375.39 321193.38 2065568.06 92.2
Work Order 08-20-14
Work Began 08-28-14
Work Completed  
Time Computed 09-05-14
Contract Working Days 84
Addl Days Granted 2
Working Days Charged 60
Percent Time Used 69
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-163
ALAMO BROTHERS CONCRETE(1.23%)
BARRICADES UNLIMITED (1.86%)
LANCO TURF & SEEDING, INC. (0.64%)
HOLMES CONSTRUCTION CO., L.P.( 19.60%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.49%)
MCL CONTRACTING, LLC (0.11%)
MCL CONTRACTING, LLC (0.42%)
HJC FARMS, INC.(2.25%)
E. DIAZ TRUCKING (0.19%)
Contract # 06143061
Totals 2174375.39 321193.38 2065568.06 92.2

CountyGRAY
Highway US 60
From SH 152
To ROBERTS COUNTY LINE
CSJ 0169-07-048
Proj ID NH 2014(755)
Work Type OVERLAY
 
8.595 3148491.58 10600.00 345690.50 10.9
Work Order 07-18-14
Work Began 00-00-00
Work Completed  
Time Computed 08-03-14
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 33
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0169-07-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143216
Totals 3148491.58 10600.00 345690.50 10.9

CountyDALLAM
Highway US 385
From SS 17
To SS 24
CSJ 0225-02-017
Proj ID STP 1102(299)
Work Type ADD TURN LANES
 
1.212 755030.70 0.00 0.00 0.0
CountyDALLAM
Highway US 54
From AT SS 24
To .
CSJ 0238-03-053
Proj ID NH 1102(424)
Work Type ADD TURN LANES
 
0.492 187838.42 0.00 475035.00 99.9
CountyDALLAM
Highway SS 24
From US 385
To US 54
CSJ 1702-02-001
Proj ID STP 1102(299)
Work Type NEW LOCATION 2 LANE RDWY
 
2.183 2132735.86 0.00 278072.42 13.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-04-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 20
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1702-02-001
(USE24847)BARRICADES UNLIMITED (2.21%)
Contract # 08133018
Totals 3075604.98 0.00 753107.42 24.4

CountyOLDHAM
Highway US 385
From B IH 40 C
To RM 1061
CSJ 0226-03-054
Proj ID STP 2014(342)
Work Type RESTORATION OF EXISTING ROADWAY
 
21.693 5497007.02 17673.60 2785035.73 51.4
Work Order 02-12-14
Work Began 06-26-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 165
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0226-03-054
ALTUS TRAFFIC MANAGEMENT LLC (0.24%)
DUSTY ALLEN, INC.(2.75%)
DUSTROL, INC.(0.28%)
FLAT LINE, INC.(1.57%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.14%)
Contract # 01143218
Totals 5497007.02 17673.60 2785035.73 51.4

CountyHARTLEY
Highway US 54
From AT PUNTA DE AGUA CREEK
To .
CSJ 0238-01-030
Proj ID BR 2013(952)
Work Type REPLACE BRIDGE & APPR
 
0.277 2427731.90 60867.35 2285468.25 94.1
CountyHARTLEY
Highway US 54
From AT RITA BLANCA CREEK
To .
CSJ 0238-02-035
Proj ID BR 2013(952)
Work Type REPLACE BRIDGE & APPR
 
0.124 1508289.77 102225.17 1497131.01 99.2
Work Order 11-08-13
Work Began 11-18-13
Work Completed  
Time Computed 11-24-13
Contract Working Days 245
Addl Days Granted 19
Working Days Charged 250
Percent Time Used 94
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-01-030
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.45%)
DUSTIN ALLEN, INC. (1.54%)
GARY A. CRAIN, INC.(0.30%)
HOLMES CONSTRUCTION CO., L.P.( 13.49%)
BARRICADES UNLIMITED (1.30%)
MH CIVIL CONSTRUCTORS, INC.(0.61%)
Contract # 08133233
Totals 3936021.67 163092.52 3782599.26 96.1

CountyDALLAM
Highway US 54
From DALHART CURB & GUTTER
To CHAMBERLIN
CSJ 0238-03-052
Proj ID C 238-3-52
Work Type REHAB EXIST RDWY & ADD PASSING LNS
 
23.304 6417952.72 0.00 6504060.69 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-05-12
Contract Working Days 172
Addl Days Granted 10
Working Days Charged 348
Percent Time Used 191
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-03-052
BARRICADES UNLIMITED-USE NEW NUMBER 24847 ON NEW SUBCONTRACT (2.73%)
DUSTROL, INC.(0.34%)
E. DIAZ TRUCKING (3.00%)
Contract # 06123007
Totals 6417952.72 0.00 6504060.69 99.9

CountySHERMAN
Highway US 54
From DALLAM COUNTY LINE
To US 287
CSJ 0238-05-039
Proj ID NH 2014(226)
Work Type REHAB EXIST RDWY & ADD PASSING LANE
 
6.141 3184352.73 502369.16 2567330.78 81.2
Work Order 01-08-14
Work Began 07-15-14
Work Completed  
Time Computed 03-18-14
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 113
Percent Time Used 122
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-05-039
(USE24847)BARRICADES UNLIMITED (1.86%)
Contract # 11133218
Totals 3184352.73 502369.16 2567330.78 81.2

CountyPOTTER
Highway IH 40
From LP 335
To COULTER ST
CSJ 0275-01-160
Proj ID NH 1402(018)
Work Type RELOCATE ENTRANCE AND EXIT RAMPS
 
0.972 5438822.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-04-14
Work Began 00-00-00
Work Completed  
Time Computed 11-20-14
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-160
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143238
Totals 5438822.45 0.00 0.00 0.0

CountyCARSON
Highway IH 40
From 3.0 MI EAST OF POTTER CO. LINE
To 3.7 MI WEST OF CONWAY
CSJ 0275-02-069
Proj ID IM 0401(208)
Work Type REHAB EXISTING ROADWAY
 
7.759 5177809.06 0.00 4796133.59 97.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-15-13
Work Began 10-28-13
Work Completed  
Time Computed 01-31-13
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 307
Percent Time Used 361
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-02-069
AMARILLO RMT ENTERPRISE(0.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.05%)
O. TREVINO CONSTRUCTION, LLC (7.18%)
TEX OP CONSTRUCTION, LP(1.36%)
WEST TEXAS RUMBLE STRIP(0.11%)
W.O.E. CONSTRUCTION(0.00%)
Contract # 11123206
Totals 5177809.06 0.00 4796133.59 97.4

CountyCARSON
Highway IH 40
From 3.2 MI WEST OF CONWAY
To 1.6 MI EAST OF CONWAY
CSJ 0275-03-062
Proj ID IM 0401(211)
Work Type REHAB EXISTING ROADWAY
 
4.876 3604723.24 0.00 3567867.81 99.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 04-28-14
Work Completed  
Time Computed 04-27-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 137
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-03-062
BARRICADES UNLIMITED-USE NEW NUMBER 24847 ON NEW SUBCONTRACT (1.10%)
HJC FARMS, INC.(0.95%)
TEX OP CONSTRUCTION, LP(1.58%)
WEST TEXAS RUMBLE STRIP(0.14%)
O. TREVINO CONSTRUCTION, LLC ( 10.62%)
BARRICADES UNLIMITED (0.00%)
Contract # 02143205
Totals 3604723.24 0.00 3567867.81 99.7

CountyOCHILTREE
Highway SH 15
From US 83
To LIPSCOMB COUNTY LINE
CSJ 0355-03-028
Proj ID STP 2013(442)
Work Type OVERLAY
 
15.205 3838624.15 0.00 4014488.94 99.9
CountyOCHILTREE
Highway SH 15
From PERRYTON C&G
To LIPSCOMB COUNTY LINE
CSJ 0355-03-029
Proj ID STP 2013(442)
Work Type OVERLAY
 
14.665 1443103.90 0.00 1350594.12 93.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-13
Work Began 08-28-13
Work Completed  
Time Computed 06-08-13
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 96
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-03-028
DUSTROL, INC.(0.34%)
FLAT LINE, INC.(0.95%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(4.59%)
J C DIAZ TRUCKING(3.54%)
BARRICADES UNLIMITED (0.30%)
Contract # 03133013
Totals 5281728.05 0.00 5365083.06 99.9

CountyHUTCHINSON
Highway SH 136
From AT ROCK CREEK
To .
CSJ 0356-01-091
Proj ID BR 2013(375)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.151 2716537.03 158739.54 2392884.60 90.5
Work Order 05-06-13
Work Began 07-30-13
Work Completed  
Time Computed 05-22-13
Contract Working Days 241
Addl Days Granted 0
Working Days Charged 326
Percent Time Used 135
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-091
SCOTT DERR PAINTING CO, LLC(0.44%)
MCL CONTRACTING, LLC (0.93%)
RUNNING HORSE CONSTRUCTION, INC. (2.30%)
TEX OP CONSTRUCTION, LP(0.58%)
SHINN & GREGORY, INC.( 10.12%)
PRIMATE CONSTRUCTION, INC. (0.28%)
LANCO TURF & SEEDING, INC. (0.27%)
HJC FARMS, INC.(2.03%)
DUSTROL, INC.(0.19%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(2.43%)
AOC ENVIRONMENTAL, INC.(1.90%)
Contract # 02133215
Totals 2716537.03 158739.54 2392884.60 90.5

CountyCARSON
Highway SH 207
From FM 293
To HUTCHINSON COUNTY LINE
CSJ 0356-02-043
Proj ID STP 2014(866)
Work Type RESTORATION OF EXISTING ROADWAY
 
19.102 8607481.82 592240.00 687568.35 7.9
Work Order 09-30-14
Work Began 10-22-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 22
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-043
BARRICADES UNLIMITED (1.16%)
E. DIAZ TRUCKING (4.32%)
DUSTROL, INC.(1.37%)
RICE ENVIRONMENTAL SERVICES(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.77%)
WEST TEXAS RUMBLE STRIP(0.32%)
Contract # 07143211
Totals 8607481.82 592240.00 687568.35 7.9

CountyHARTLEY
Highway US 87
From EAST OF US 385 INTERCHANGE
To MOORE COUNTY LINE
CSJ 0425-01-019
Proj ID C 425-1-19
Work Type REHAB EXISTING RDWY & PASSING LANES
 
22.251 21250815.26 5915.77 12770766.55 61.1
Work Order 10-24-12
Work Began 11-19-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 370
Addl Days Granted 5
Working Days Charged 463
Percent Time Used 123
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0425-01-019
HIGHWAY TECHNOLOGIES, INC. (0.14%)
TEXAS ALTERNATIVE GRASSER, INC.(0.02%)
DUSTROL, INC.(1.94%)
HOLMES CONSTRUCTION CO., L.P.( 10.19%)
HJC FARMS, INC.(0.95%)
BALLOU PAVEMENT SOLUTIONS INC. ( 14.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.51%)
BRUSH EATERS, INC. (0.12%)
KOSS CONSTRUCTION COMPANY( 14.78%)
WILLIS ELECTRIC CO., LP(0.09%)
Contract # 08123002
Totals 21250815.26 5915.77 12770766.55 61.1

CountyROBERTS
Highway SH 70
From NORTH CANADIAN RIVER BRIDGE
To OCHILTREE COUNTY LINE
CSJ 0490-04-037
Proj ID STP 2014(579)
Work Type REHABILITATE EXISTING ROADWAY
 
5.848 5139086.58 0.00 37500.00 0.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 13
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99%)
HJC FARMS, INC.(3.77%)
HUDSON, INC. (0.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.84%)
WEST TEXAS RUMBLE STRIP(0.08%)
W.S. CONSTRUCTION COMPANY(5.84%)
E. DIAZ TRUCKING (2.85%)
Contract # 04143003
Totals 5139086.58 0.00 37500.00 0.7

CountyRANDALL
Highway PR 5
From AT WATER CROSS 1,2,6 AND BURNT DRAW
To IN PALO DURO CANYON STATE PARK
CSJ 0534-01-019
Proj ID C 534-1-19
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.576 3956849.00 215037.91 3456383.35 89.8
Work Order 11-04-13
Work Began 11-04-13
Work Completed  
Time Computed 11-20-13
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 263
Percent Time Used 111
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-019
ENVIRONMENTAL SAFETY SERVICES, INC.(3.98%)
HOLMES CONSTRUCTION CO., L.P.( 27.09%)
LANCO TURF & SEEDING, INC. (0.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
MH CIVIL CONSTRUCTORS, INC.(0.24%)
BARRICADES UNLIMITED (0.29%)
DAVIS CONSTRUCTION, INC. ( 27.81%)
AMARILLO RMT ENTERPRISE(1.81%)
Contract # 09133228
Totals 3956849.00 215037.91 3456383.35 89.8

CountyLIPSCOMB
Highway SH 305
From SP 188
To LIPSCOMB COUNTY LINE
CSJ 0582-02-018
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 6255144.40 490200.32 6367048.16 99.9
CountyHEMPHILL
Highway SH 305
From LIPSCOMB COUNTY LINE
To US 60
CSJ 0582-03-014
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 1439611.54 105097.27 1444785.60 99.9
Work Order 11-14-13
Work Began 04-15-14
Work Completed  
Time Computed 11-30-13
Contract Working Days 130
Addl Days Granted 5
Working Days Charged 112
Percent Time Used 82
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0582-02-018
BARRICADES UNLIMITED (1.55%)
HJC FARMS, INC.(0.88%)
SCR CONSTRUCTION CO., INC. (2.06%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(0.27%)
Contract # 10133018
Totals 7694755.94 595297.59 7811833.76 99.9

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS IN AMARILLO
To (ON SYSTEM)
CSJ 0904-00-148
Proj ID STP 2012(052)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2062945.48 0.00 1727254.99 93.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-03-12
Work Began 01-23-12
Work Completed  
Time Computed 01-19-12
Contract Working Days 175
Addl Days Granted 32
Working Days Charged 459
Percent Time Used 221
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-148
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(5.28%)
RAY ELECTRIC COMPANY (7.14%)
SECRET GARDENER(1.63%)
SPEEDY PAVING(2.25%)
Contract # 10113013
Totals 2062945.48 0.00 1727254.99 93.5

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-153
Proj ID STP 2014(389)G
Work Type THERMOPLASTIC STRIPING
 
442.233 1171697.78 0.00 1164209.43 99.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-10-14
Work Began 06-16-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 105
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-153
TOTAL HIGHWAY MAINTENANCE, LLC (6.81%)
Contract # 02143220
Totals 1171697.78 0.00 1164209.43 99.5

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To (ON SYSTEM)
CSJ 0904-00-154
Proj ID STP 2013(085)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2916208.80 17500.00 2247334.69 77.0
Work Order 12-04-12
Work Began 01-08-13
Work Completed  
Time Computed 12-20-12
Contract Working Days 206
Addl Days Granted 2
Working Days Charged 208
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(6.11%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 14.49%)
Contract # 10123029
Totals 2916208.80 17500.00 2247334.69 77.0

page 1 | page 2 | page 3