Monthly State Let Construction Report For Amarillo District As Of Jun 15, 2016 Page 2 Of 3

Last Update: Wednesday, June 15, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPOTTER
Highway IH 40
From 0.15 MILES WEST OF WASHINGTON ST
To NELSON STREET
CSJ 0275-01-177
Proj ID NH 1602(189)
Work Type REHAB EXISTING ROADWAY
 
2.977 36259776.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 332
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-177
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163003
Totals 36259776.70 0.00 0.00 0.0

CountyGRAY
Highway IH 40
From ALANREED
To DONLEY COUNTY LINE
CSJ 0275-11-077
Proj ID NH 1502(079)
Work Type OVERLAY AND MINOR BRIDGE MAINTENANC
 
9.571 3565812.59 0.00 21000.00 0.5
Work Order 06-15-15
Work Began 00-00-00
Work Completed  
Time Computed 09-01-15
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-11-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153223
Totals 3565812.59 0.00 21000.00 0.5

CountyHANSFORD
Highway SH 15
From SH 136 IN GURVER
To SH 207 IN SPEARMAN
CSJ 0308-02-029
Proj ID STP 1602(139)
Work Type RESTORATION OF EXISTING ROADWAY
 
19.900 9135715.42 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0308-02-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163030
Totals 9135715.42 0.00 0.00 0.0

CountyLIPSCOMB
Highway SH 15
From FM 2172 IN DARROUZETT
To FM 1455
CSJ 0355-01-047
Proj ID STP 2015(639)
Work Type OVERLAY
 
6.099 1996781.26 0.00 2019106.50 99.9
CountyLIPSCOMB
Highway SH 15
From OCHILTREE COUNTY LINE
To FM 2172 IN DARROUZETT
CSJ 0355-02-030
Proj ID STP 2015(639)
Work Type OVERLAY
 
12.620 2960757.17 0.00 3031568.18 99.9
CountyOCHILTREE
Highway SH 15
From HANSFORD COUNTY LINE
To US 83 IN PERRYTON
CSJ 0355-04-039
Proj ID STP 2015(587)
Work Type RESTORATION OF EXISTING ROADWAY
 
18.117 8770353.11 70632.82 8703031.35 99.2
Work Order 03-06-15
Work Began 06-02-15
Work Completed  
Time Computed 06-01-15
Contract Working Days 122
Addl Days Granted 5
Working Days Charged 120
Percent Time Used 94
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-04-039
BARRICADES UNLIMITED (1.57%)
DUSTROL, INC.(0.60%)
HJC FARMS, INC.(0.90%)
O. TREVINO CONSTRUCTION, LLC (0.79%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.09%)
TEXAS ALTERNATIVE GRASSER, INC.(0.09%)
J C DIAZ TRUCKING(0.00%)
Contract # 01153026
Totals 13727891.54 70632.82 13753706.03 99.9

CountyLIPSCOMB
Highway SH 15
From FM 1455
To OKLAHOMA STATE LINE
CSJ 0355-01-048
Proj ID STP 1602(191)
Work Type OVERLAY
 
12.362 4980635.65 0.00 0.00 0.0
CountyLIPSCOMB
Highway SH 15
From OCHILTREE COUNTY LINE
To 1000' EAST OF COUNTY ROAD 4
CSJ 0355-02-031
Proj ID STP 1602(191)
Work Type OVERLAY
 
3.118 986876.40 0.00 0.00 0.0
CountyLIPSCOMB
Highway SH 23
From FM 377
To 11.05 MILES NORTH OF US 83
CSJ 1337-01-023
Proj ID STP 1602(191)
Work Type OVERLAY
 
10.063 2183107.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0355-01-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163023
Totals 8150619.80 0.00 0.00 0.0

CountyCARSON
Highway SH 207
From FM 293
To HUTCHINSON COUNTY LINE
CSJ 0356-02-043
Proj ID STP 2014(866)
Work Type RESTORATION OF EXISTING ROADWAY
 
19.102 8607481.82 787198.60 7503029.72 87.1
Work Order 09-30-14
Work Began 10-22-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 110
Addl Days Granted 9
Working Days Charged 113
Percent Time Used 94
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-043
BARRICADES UNLIMITED (1.16%)
E. DIAZ TRUCKING (4.32%)
DUSTROL, INC.(1.37%)
RICE ENVIRONMENTAL SERVICES(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.77%)
WEST TEXAS RUMBLE STRIP(0.32%)
Contract # 07143211
Totals 8607481.82 787198.60 7503029.72 87.1

CountyGRAY
Highway SH 152
From US 60
To WHEELER COUNTY LINE
CSJ 0397-01-043
Proj ID STP 2015(472)
Work Type OVERLAY
 
17.735 6779225.71 0.00 3148639.64 46.4
Work Order 02-11-15
Work Began 09-22-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 88
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0397-01-043
BARRICADES UNLIMITED (1.88%)
DUSTROL, INC.(0.41%)
HJC FARMS, INC.(4.71%)
Contract # 01153208
Totals 6779225.71 0.00 3148639.64 46.4

CountyROBERTS
Highway SH 70
From NORTH CANADIAN RIVER BRIDGE
To OCHILTREE COUNTY LINE
CSJ 0490-04-037
Proj ID STP 2014(579)
Work Type REHABILITATE EXISTING ROADWAY
 
5.848 5139086.58 0.00 2338710.50 45.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-14
Work Began 12-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 22
Working Days Charged 235
Percent Time Used 107
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99%)
HJC FARMS, INC.(3.77%)
HUDSON, INC. (0.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.84%)
WEST TEXAS RUMBLE STRIP(0.08%)
W.S. CONSTRUCTION COMPANY(5.84%)
E. DIAZ TRUCKING (2.85%)
Contract # 04143003
Totals 5139086.58 0.00 2338710.50 45.8

CountyRANDALL
Highway PR 5
From AT WATER CROSSINGS 3,4 AND 5
To WITHIN PALO DURO CANYON STATE PARK
CSJ 0534-01-020
Proj ID C 534-1-20
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.385 3768710.10 287942.80 3704606.09 98.2
Work Order 05-15-15
Work Began 06-08-15
Work Completed  
Time Computed 05-31-15
Contract Working Days 230
Addl Days Granted 10
Working Days Charged 218
Percent Time Used 90
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-020
ALTUS TRAFFIC MANAGEMENT LLC (1.58%)
WOLFE CONSTRUCTION GROUP, INC. (0.56%)
HUDSON, INC. (0.48%)
AMARILLO RMT ENTERPRISES, LLC(1.81%)
LONE STAR CONSTRUCTION (3.84%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.49%)
MCL CONTRACTING, LLC (0.26%)
L. A. FULLER & SONS CONSTRUCTION, LTD. (4.38%)
GSI HIGHWAY PRODUCTS (1.86%)
Contract # 04153034
Totals 3768710.10 287942.80 3704606.09 98.2

CountyMOORE
Highway SH 152
From DUMAS CITY LIMITS
To HUTCHINSON COUNTY LINE
CSJ 0557-01-028
Proj ID STP 2016(683)
Work Type RESTORATION
 
47.263 15561610.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-24-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0557-01-028
BARRICADES UNLIMITED (0.84%)
DUSTROL, INC.(0.00%)
W.S. CONSTRUCTION COMPANY(0.00%)
Contract # 02163003
Totals 15561610.53 0.00 0.00 0.0

CountyDALLAM
Highway FM 1727
From FM 3310
To 7 MI WEST OF FM 3489
CSJ 0794-01-018
Proj ID STP 1502(296)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
11.362 6170063.74 164623.45 1689945.90 27.3
Work Order 07-16-15
Work Began 02-24-16
Work Completed  
Time Computed 01-11-16
Contract Working Days 114
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 70
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0794-01-018
BARRICADES UNLIMITED (0.73%)
LANCO TURF & SEEDING, INC. (0.30%)
COWBELL TRAFFIC SERVICES, INC. (0.40%)
HJC FARMS, INC.(1.37%)
E. DIAZ TRUCKING (2.28%)
Contract # 06153218
Totals 6170063.74 164623.45 1689945.90 27.3

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-155
Proj ID STP 2015(588)
Work Type THERMOPLASTIC STRIPING
 
0.001 2103735.09 0.00 1933309.49 91.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 06-16-15
Work Completed  
Time Computed 06-16-15
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153017
Totals 2103735.09 0.00 1933309.49 91.8

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-159
Proj ID STP 2016(686)
Work Type THERMOPLASTIC STRIPING
 
347.994 1028988.72 242210.38 695726.10 67.6
Work Order 03-09-16
Work Began 04-04-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 38
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-159
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163211
Totals 1028988.72 242210.38 695726.10 67.6

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMARILLO
To .
CSJ 0904-00-160
Proj ID STP 2015(649)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2895601.55 25050.00 2232220.08 77.0
Work Order 05-08-15
Work Began 07-06-15
Work Completed  
Time Computed 05-24-15
Contract Working Days 274
Addl Days Granted 0
Working Days Charged 216
Percent Time Used 78
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
ONE WAY CONCRETE ( 56.56%)
BTA SERVICES, LTD. (1.91%)
Contract # 03153026
Totals 2895601.55 25050.00 2232220.08 77.0

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMA DISTRIC
To .
CSJ 0904-00-161
Proj ID STP 2016(150)
Work Type CONSTUCT CURB RAMPS
 
0.001 1946236.07 226710.30 875599.83 44.9
Work Order 12-10-15
Work Began 02-24-16
Work Completed  
Time Computed 12-11-15
Contract Working Days 210
Addl Days Granted 3
Working Days Charged 60
Percent Time Used 28
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-161
CLASSIC TEJAS CONSTRUCTION, INC. (5.30%)
Contract # 10153022
Totals 1946236.07 226710.30 875599.83 44.9

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE
CSJ 0904-00-168
Proj ID NH 2016(013)
Work Type ITS MAINTENANCE
 
0.100 225675.00 210735.00 210735.00 93.3
Work Order 10-22-15
Work Began 05-03-16
Work Completed  
Time Computed 11-02-15
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 35
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-168
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153225
Totals 225675.00 210735.00 210735.00 93.3

CountyPOTTER
Highway CR
From ON DEWEY AVE AT WEST AMARILLO CREEK
To .
CSJ 0904-02-037
Proj ID BR 2014(554)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.041 1220116.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-02-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163235
Totals 1220116.75 0.00 0.00 0.0

CountyHEMPHILL
Highway PW
From GENE HOWE WILDLIFE MANAGEMENT AREA
To .
CSJ 0904-03-017
Proj ID C 904-3-17
Work Type REHAB EXISTING RDWY
 
4.477 938346.79 0.00 14856.00 1.5
Work Order 09-22-15
Work Began 06-06-16
Work Completed  
Time Computed 10-21-15
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-03-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153063
Totals 938346.79 0.00 14856.00 1.5

CountyPOTTER
Highway RM 1061
From FM 2381
To 7.5 MILES NORTH OF FM 2381
CSJ 1245-02-043
Proj ID STP 1502(299)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
10.539 7907537.75 572566.18 3034407.32 38.3
CountyPOTTER
Highway RM 1061
From 10.50 MILES NORTH OF FM 2381
To OLDHAM COUNTY LINE
CSJ 1245-02-044
Proj ID STP 1502(355)
Work Type ADD PASSING LANES FOR SAFETY
 
12.837 2230786.34 -21521.36 471813.62 21.1
Work Order 08-20-15
Work Began 02-03-16
Work Completed  
Time Computed 08-03-15
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 32
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-043
BARRICADES UNLIMITED (1.85%)
HJC FARMS, INC.(1.25%)
W.S. CONSTRUCTION COMPANY(9.93%)
WILLIS ELECTRIC CO., LP(0.46%)
Contract # 06153245
Totals 10138324.09 551044.82 3506220.94 34.5

CountyLIPSCOMB
Highway SH 23
From FM 377
To 11.05 MI N OF US 83
CSJ 1337-01-022
Proj ID C 1337-1-22
Work Type REHAB & WIDEN EXISTING RDWY
 
10.063 5502012.06 9509.49 5617949.03 100.0
Work Order 11-19-12
Work Began 01-09-13
Work Completed 12-03-15
Time Computed 12-05-12
Contract Working Days 250
Addl Days Granted 262
Working Days Charged 512
Percent Time Used 100
Contractor(s)
MITCHELL ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1337-01-022
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.68%)
HJC FARMS, INC.(1.81%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.18%)
B&B SOLVENT, LTD.( 64.57%)
RICE CONSTRUCTION( 19.87%)
LEWIS CONSTRUCTION CO., INC. (0.68%)
LEWIS CONSTRUCTION CO., INC. (0.84%)
Contract # 07123220
Totals 5502012.06 9509.49 5617949.03 100.0

page 1 | page 2 | page 3