Monthly State Let Construction Report For Amarillo District As Of Aug 12, 2014 Page 2 Of 3

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAM
Highway US 385
From SS 17
To SS 24
CSJ 0225-02-017
Proj ID STP 1102(299)
Work Type ADD TURN LANES
 
1.212 755030.70 0.00 0.00 0.0
CountyDALLAM
Highway US 54
From AT SS 24
To .
CSJ 0238-03-053
Proj ID NH 1102(424)
Work Type ADD TURN LANES
 
0.492 187838.42 0.00 475035.00 99.9
CountyDALLAM
Highway SS 24
From US 385
To US 54
CSJ 1702-02-001
Proj ID STP 1102(299)
Work Type NEW LOCATION 2 LANE RDWY
 
2.183 2132735.86 0.00 22552.50 1.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-04-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1702-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08133018
Totals 3075604.98 0.00 497587.50 16.1

CountyOLDHAM
Highway US 385
From B IH 40 C
To RM 1061
CSJ 0226-03-054
Proj ID STP 2014(342)
Work Type RESTORATION OF EXISTING ROADWAY
 
21.693 5497007.02 0.00 1624637.38 29.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 68
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0226-03-054
ALTUS TRAFFIC MANAGEMENT LLC (0.24%)
DUSTY ALLEN, INC.(2.75%)
DUSTROL, INC.(0.28%)
FLAT LINE, INC.(1.57%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.14%)
Contract # 01143218
Totals 5497007.02 0.00 1624637.38 29.5

CountyHARTLEY
Highway US 54
From AT PUNTA DE AGUA CREEK
To .
CSJ 0238-01-030
Proj ID BR 2013(952)
Work Type REPLACE BRIDGE & APPR
 
0.277 2427731.90 124230.00 1527003.59 62.8
CountyHARTLEY
Highway US 54
From AT RITA BLANCA CREEK
To .
CSJ 0238-02-035
Proj ID BR 2013(952)
Work Type REPLACE BRIDGE & APPR
 
0.124 1508289.77 149773.00 1310307.28 86.8
Work Order 11-08-13
Work Began 11-18-13
Work Completed  
Time Computed 11-24-13
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 171
Percent Time Used 69
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-01-030
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.45%)
DUSTIN ALLEN, INC. (1.54%)
GARY A. CRAIN, INC.(0.30%)
HOLMES CONSTRUCTION CO., L.P.( 13.49%)
BARRICADES UNLIMITED (1.30%)
MH CIVIL CONSTRUCTORS, INC.(0.61%)
Contract # 08133233
Totals 3936021.67 274003.00 2837310.87 72.0

CountyDALLAM
Highway US 54
From DALHART CURB & GUTTER
To CHAMBERLIN
CSJ 0238-03-052
Proj ID C 238-3-52
Work Type REHAB EXIST RDWY & ADD PASSING LNS
 
23.304 6417952.72 -14770.20 6247004.91 99.9
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-05-12
Contract Working Days 172
Addl Days Granted 10
Working Days Charged 347
Percent Time Used 190
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-03-052
BARRICADES UNLIMITED-USE NEW NUMBER 24847 ON NEW SUBCONTRACT (2.73%)
DUSTROL, INC.(0.34%)
E. DIAZ TRUCKING (3.00%)
Contract # 06123007
Totals 6417952.72 14770.20 6247004.91 99.9

CountySHERMAN
Highway US 54
From DALLAM COUNTY LINE
To US 287
CSJ 0238-05-039
Proj ID NH 2014(226)
Work Type REHAB EXIST RDWY & ADD PASSING LANE
 
6.141 3184352.73 166018.77 277142.77 8.7
Work Order 01-08-14
Work Began 00-00-00
Work Completed  
Time Computed 03-18-14
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 42
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-05-039
(USE24847)BARRICADES UNLIMITED (1.86%)
Contract # 11133218
Totals 3184352.73 166018.77 277142.77 8.7

CountyPOTTER
Highway IH 40
From LP 335
To COULTER ST
CSJ 0275-01-160
Proj ID NH 1402(018)
Work Type RELOCATE ENTRANCE AND EXIT RAMPS
 
0.972 5438822.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-160
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143238
Totals 5438822.45 0.00 0.00 0.0

CountyCARSON
Highway IH 40
From 3.0 MI EAST OF POTTER CO. LINE
To 3.7 MI WEST OF CONWAY
CSJ 0275-02-069
Proj ID IM 0401(208)
Work Type REHAB EXISTING ROADWAY
 
7.759 5177809.06 -73469.99 2128489.40 44.4
Work Order 01-15-13
Work Began 10-28-13
Work Completed  
Time Computed 01-31-13
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 261
Percent Time Used 307
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-02-069
AMARILLO RMT ENTERPRISE(0.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.05%)
O. TREVINO CONSTRUCTION, LLC (7.18%)
TEX OP CONSTRUCTION, LP(1.36%)
WEST TEXAS RUMBLE STRIP(0.11%)
W.O.E. CONSTRUCTION(0.00%)
Contract # 11123206
Totals 5177809.06 73469.99 2128489.40 44.4

CountyCARSON
Highway IH 40
From 3.2 MI WEST OF CONWAY
To 1.6 MI EAST OF CONWAY
CSJ 0275-03-062
Proj ID IM 0401(211)
Work Type REHAB EXISTING ROADWAY
 
4.876 3604723.24 330096.05 1535798.10 42.6
Work Order 04-11-14
Work Began 04-28-14
Work Completed  
Time Computed 04-27-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 78
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-03-062
BARRICADES UNLIMITED-USE NEW NUMBER 24847 ON NEW SUBCONTRACT (1.10%)
HJC FARMS, INC.(0.95%)
TEX OP CONSTRUCTION, LP(1.58%)
WEST TEXAS RUMBLE STRIP(0.14%)
O. TREVINO CONSTRUCTION, LLC ( 10.62%)
BARRICADES UNLIMITED (0.00%)
Contract # 02143205
Totals 3604723.24 330096.05 1535798.10 42.6

CountyOCHILTREE
Highway SH 15
From US 83
To LIPSCOMB COUNTY LINE
CSJ 0355-03-028
Proj ID STP 2013(442)
Work Type OVERLAY
 
15.205 3838624.15 0.00 4014488.94 99.9
CountyOCHILTREE
Highway SH 15
From PERRYTON C&G
To LIPSCOMB COUNTY LINE
CSJ 0355-03-029
Proj ID STP 2013(442)
Work Type OVERLAY
 
14.665 1443103.90 0.00 1350594.12 93.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-13
Work Began 08-28-13
Work Completed  
Time Computed 06-08-13
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 96
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-03-028
DUSTROL, INC.(0.34%)
FLAT LINE, INC.(0.95%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(4.59%)
J C DIAZ TRUCKING(3.54%)
BARRICADES UNLIMITED (0.30%)
Contract # 03133013
Totals 5281728.05 0.00 5365083.06 99.9

CountyHUTCHINSON
Highway SH 136
From AT ROCK CREEK
To .
CSJ 0356-01-091
Proj ID BR 2013(375)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.151 2716537.03 1005.29 1891158.99 69.7
Work Order 05-06-13
Work Began 07-30-13
Work Completed  
Time Computed 05-22-13
Contract Working Days 241
Addl Days Granted 0
Working Days Charged 245
Percent Time Used 101
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-091
SCOTT DERR PAINTING CO, LLC(0.44%)
MCL CONTRACTING, LLC (0.93%)
RUNNING HORSE CONSTRUCTION, INC. (2.30%)
TEX OP CONSTRUCTION, LP(0.58%)
SHINN & GREGORY, INC.( 10.12%)
PRIMATE CONSTRUCTION, INC. (0.28%)
LANCO TURF & SEEDING, INC. (0.27%)
HJC FARMS, INC.(2.03%)
DUSTROL, INC.(0.19%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(2.43%)
AOC ENVIRONMENTAL, INC.(1.90%)
Contract # 02133215
Totals 2716537.03 1005.29 1891158.99 69.7

CountyCARSON
Highway SH 207
From FM 293
To HUTCHINSON COUNTY LINE
CSJ 0356-02-043
Proj ID STP 2014(866)
Work Type RESTORATION OF EXISTING ROADWAY
 
19.102 8607481.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143211
Totals 8607481.82 0.00 0.00 0.0

CountyHARTLEY
Highway US 87
From EAST OF US 385 INTERCHANGE
To MOORE COUNTY LINE
CSJ 0425-01-019
Proj ID C 425-1-19
Work Type REHAB EXISTING RDWY & PASSING LANES
 
22.251 21250815.26 172405.28 10004186.57 47.5
Work Order 10-24-12
Work Began 11-19-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 370
Addl Days Granted 0
Working Days Charged 407
Percent Time Used 110
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0425-01-019
HIGHWAY TECHNOLOGIES, INC. (0.14%)
TEXAS ALTERNATIVE GRASSER, INC.(0.02%)
DUSTROL, INC.(1.94%)
HOLMES CONSTRUCTION CO., L.P.( 10.19%)
HJC FARMS, INC.(0.95%)
BALLOU PAVEMENT SOLUTIONS INC. ( 14.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.51%)
BRUSH EATERS, INC. (0.12%)
KOSS CONSTRUCTION COMPANY( 14.78%)
WILLIS ELECTRIC CO., LP(0.09%)
Contract # 08123002
Totals 21250815.26 172405.28 10004186.57 47.5

CountyROBERTS
Highway SH 70
From NORTH CANADIAN RIVER BRIDGE
To OCHILTREE COUNTY LINE
CSJ 0490-04-037
Proj ID STP 2014(579)
Work Type REHABILITATE EXISTING ROADWAY
 
5.848 5139086.58 0.00 34000.00 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143003
Totals 5139086.58 0.00 34000.00 0.6

CountyRANDALL
Highway PR 5
From AT WATER CROSS 1,2,6 AND BURNT DRAW
To IN PALO DURO CANYON STATE PARK
CSJ 0534-01-019
Proj ID C 534-1-19
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.576 3956849.00 117672.56 2479805.52 63.3
Work Order 11-04-13
Work Began 11-04-13
Work Completed  
Time Computed 11-20-13
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 178
Percent Time Used 75
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-019
ENVIRONMENTAL SAFETY SERVICES, INC.(3.98%)
HOLMES CONSTRUCTION CO., L.P.( 27.09%)
LANCO TURF & SEEDING, INC. (0.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
MH CIVIL CONSTRUCTORS, INC.(0.24%)
BARRICADES UNLIMITED (0.29%)
DAVIS CONSTRUCTION, INC. ( 27.81%)
AMARILLO RMT ENTERPRISE(1.81%)
Contract # 09133228
Totals 3956849.00 117672.56 2479805.52 63.3

CountyLIPSCOMB
Highway SH 305
From SP 188
To LIPSCOMB COUNTY LINE
CSJ 0582-02-018
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 6255144.40 2497.54 2929650.74 46.8
CountyHEMPHILL
Highway SH 305
From LIPSCOMB COUNTY LINE
To US 60
CSJ 0582-03-014
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 1439611.54 22693.75 544661.35 37.8
Work Order 11-14-13
Work Began 04-15-14
Work Completed  
Time Computed 11-30-13
Contract Working Days 130
Addl Days Granted 5
Working Days Charged 50
Percent Time Used 37
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0582-02-018
BARRICADES UNLIMITED (1.55%)
HJC FARMS, INC.(0.88%)
SCR CONSTRUCTION CO., INC. (2.06%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(0.27%)
Contract # 10133018
Totals 7694755.94 25191.29 3474312.09 45.1

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS IN AMARILLO
To (ON SYSTEM)
CSJ 0904-00-148
Proj ID STP 2012(052)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2062945.48 0.00 1679387.97 92.4
Work Order 01-03-12
Work Began 01-23-12
Work Completed  
Time Computed 01-19-12
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 459
Percent Time Used 262
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-148
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(5.28%)
RAY ELECTRIC COMPANY (7.14%)
SECRET GARDENER(1.63%)
SPEEDY PAVING(2.25%)
Contract # 10113013
Totals 2062945.48 0.00 1679387.97 92.4

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-153
Proj ID STP 2014(389)G
Work Type THERMOPLASTIC STRIPING
 
442.233 1171697.78 438459.46 1108354.12 94.5
Work Order 03-10-14
Work Began 06-16-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 96
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-153
TOTAL HIGHWAY MAINTENANCE, LLC (6.81%)
Contract # 02143220
Totals 1171697.78 438459.46 1108354.12 94.5

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To (ON SYSTEM)
CSJ 0904-00-154
Proj ID STP 2013(085)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2916208.80 0.00 2220021.00 76.1
Work Order 12-04-12
Work Began 01-08-13
Work Completed  
Time Computed 12-20-12
Contract Working Days 206
Addl Days Granted 0
Working Days Charged 204
Percent Time Used 99
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(6.11%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 14.49%)
Contract # 10123029
Totals 2916208.80 0.00 2220021.00 76.1

CountyHUTCHINSON
Highway CS
From ON ROOSEVELT ST. FROM SH 136
To SH 207
CSJ 0904-07-012
Proj ID STP 2013(490)
Work Type REHAB EXISTING ROADWAY
 
0.769 1870540.00 63026.56 923986.26 51.9
Work Order 07-31-13
Work Began 09-03-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 148
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-07-012
RAY ELECTRIC COMPANY (1.71%)
ALAMO BROTHERS CONCRETE( 26.42%)
A-1 SERVICES (0.26%)
BARRICADES UNLIMITED (3.15%)
TEX OP CONSTRUCTION, LP(0.61%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
Contract # 06133015
Totals 1870540.00 63026.56 923986.26 51.9

CountyRANDALL
Highway CS
From ON FARMERS AVE, FROM WESTERN ST
To GEORGIA ST
CSJ 0904-11-053
Proj ID STP 2013(143)
Work Type REHAB EXISTING ROADWAY
 
0.996 1400000.00 177040.06 1378618.18 99.9
Work Order 01-04-13
Work Began 06-03-13
Work Completed  
Time Computed 06-10-13
Contract Working Days 83
Addl Days Granted 10
Working Days Charged 196
Percent Time Used 210
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-053
A-1 SERVICES (0.18%)
ALAMO BROTHERS CONCRETE(8.38%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.65%)
Contract # 11123019
Totals 1400000.00 177040.06 1378618.18 99.9

page 1 | page 2 | page 3