Monthly State Let Construction Report For Amarillo District As Of Jan 11, 2016 Page 2 Of 4

Last Update: Tuesday, January 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyARMSTRONG
Highway US 287
From 0.3 MI WEST OF CLAUDE CITY LIMITS
To 0.037 MI EAST OF TRICE ST
CSJ 0042-03-040
Proj ID NH 2012(544)
Work Type REHAB EXISTING ROADWAY
 
1.461 6066806.51 0.00 5903261.46 100.0
CountyARMSTRONG
Highway US 287
From 0.037 MI EAST OF TRICE ST
To 0.146 MI EAST OF FM 1151
CSJ 0042-04-039
Proj ID NH 2012(544)
Work Type REHAB EXISTING ROADWAY
 
1.179 3713109.66 0.00 3874277.22 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-03-12
Work Began 08-02-12
Work Completed 05-07-15
Time Computed 07-19-12
Contract Working Days 386
Addl Days Granted 3
Working Days Charged 518
Percent Time Used 133
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-03-040
ALAMO BROTHERS CONCRETE(7.64%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.45%)
DUSTROL, INC.(0.05%)
WILLIS ELECTRIC CO., LP(0.53%)
TEX OP CONSTRUCTION, LP(1.53%)
Contract # 05123203
Totals 9779916.17 0.00 9777538.68 100.0

CountyARMSTRONG
Highway US 287 ETC
From FM 294
To DONLEY COUNTY LINE
CSJ 0042-05-030
Proj ID STP 2014(461)HESG
Work Type TEXTURIZE SHOULDERS
 
146.790 268557.49 0.00 349963.77 99.9
Work Order 04-15-14
Work Began 10-27-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 34
Addl Days Granted 18
Working Days Charged 31
Percent Time Used 59
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-05-030
RED SIXTEEN CONSTRUCTION, INC( 29.96%)
Contract # 03143004
Totals 268557.49 0.00 349963.77 99.9

CountyMOORE
Highway US 287
From FM 281
To SHERMAN COUNTY LINE
CSJ 0066-04-074
Proj ID NH 2013(610)
Work Type REHABILITATION
 
2.256 3826918.47 82588.10 1913480.52 50.0
Work Order 09-24-14
Work Began 07-15-15
Work Completed  
Time Computed 04-06-15
Contract Working Days 77
Addl Days Granted 5
Working Days Charged 39
Percent Time Used 47
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0066-04-074
BARRICADES UNLIMITED (1.26%)
BARRICADES UNLIMITED (1.26%)
MPB, INC.(3.18%)
HJC FARMS, INC.(1.78%)
Contract # 07143031
Totals 3826918.47 82588.10 1913480.52 50.0

CountyOLDHAM
Highway IH 40
From 6.2 MI E OF NEW MEXICO STATE LINE
To 11.2 MI E OF NEW MEXICO STATE LINE
CSJ 0090-02-052
Proj ID IM 0401(210)
Work Type OVERLAY
 
5.016 2378425.51 0.00 2316859.89 99.9
CountyOLDHAM
Highway IH 40
From 0.23 MI WEST OF FM 2858
To 0.25 MI EAST OF SH 214
CSJ 0090-03-058
Proj ID IM 0401(210)
Work Type OVERLAY
 
6.662 3012317.95 0.00 3125260.53 99.9
Work Order 04-15-14
Work Began 12-15-14
Work Completed  
Time Computed 04-15-14
Contract Working Days 115
Addl Days Granted 0
Working Days Charged 215
Percent Time Used 186
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-02-052
E. DIAZ TRUCKING (5.15%)
HOLMES CONSTRUCTION CO., L.P.(1.41%)
LANCO TURF & SEEDING, INC. (0.73%)
LONE STAR BARRIER SERVICES, LLC(2.57%)
A BROTHERS MILLING, LLC(0.98%)
BARRICADES UNLIMITED (1.57%)
COWBELL TRAFFIC SERVICES, INC. (0.52%)
Contract # 02143021
Totals 5390743.46 0.00 5442120.42 99.9

CountyDEAF SMITH
Highway US 60
From RANDALL COUNTY LINE
To HEREFORD CITY LIMITS
CSJ 0168-07-042
Proj ID NH 2013(311)
Work Type REHAB EXISTING RDWY WB LANES
 
13.103 3419940.93 0.00 3320295.65 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-13
Work Began 03-05-14
Work Completed 07-07-14
Time Computed 03-31-13
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 136
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-07-042
BARRICADES UNLIMITED (2.12%)
AMARILLO RMT ENTERPRISE(1.14%)
TEX OP CONSTRUCTION, LP(1.69%)
E. DIAZ TRUCKING (6.66%)
DUSTROL, INC.(3.06%)
Contract # 01133217
Totals 3419940.93 0.00 3320295.65 100.0

CountyRANDALL
Highway US 60
From DEAF SMITH COUNTY LINE
To US 87
CSJ 0168-08-068
Proj ID NH 2013(088)
Work Type OVERLAY
 
14.789 7931426.33 0.00 7947918.08 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-03-13
Work Began 06-24-13
Work Completed  
Time Computed 01-19-13
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 288
Percent Time Used 130
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-08-068
AMARILLO RMT ENTERPRISE(1.16%)
BARRICADES UNLIMITED (2.39%)
E. DIAZ TRUCKING (0.00%)
WEST TEXAS RUMBLE STRIP(0.25%)
Contract # 10123227
Totals 7931426.33 0.00 7947918.08 99.9

CountyRANDALL
Highway US 60
From AT CR 214 (BUFFALO STD)
To .
CSJ 0168-09-163
Proj ID BR 2014(936)
Work Type REPLACE BRIDGE
 
0.059 2174375.39 0.00 2247161.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-14
Work Began 08-28-14
Work Completed 07-01-15
Time Computed 09-05-14
Contract Working Days 84
Addl Days Granted 2
Working Days Charged 87
Percent Time Used 101
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-163
ALAMO BROTHERS CONCRETE(1.23%)
BARRICADES UNLIMITED (1.86%)
LANCO TURF & SEEDING, INC. (0.64%)
HOLMES CONSTRUCTION CO., L.P.( 19.60%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.49%)
MCL CONTRACTING, LLC (0.11%)
MCL CONTRACTING, LLC (0.42%)
HJC FARMS, INC.(2.25%)
E. DIAZ TRUCKING (0.19%)
Contract # 06143061
Totals 2174375.39 0.00 2247161.00 100.0

CountyGRAY
Highway US 60
From SH 152
To ROBERTS COUNTY LINE
CSJ 0169-07-048
Proj ID NH 2014(755)
Work Type OVERLAY
 
8.595 3148491.58 0.00 3089683.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-18-14
Work Began 08-06-15
Work Completed 11-19-15
Time Computed 08-03-14
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 100
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0169-07-048
BARRICADES UNLIMITED (1.87%)
DUSTROL, INC.(0.57%)
Contract # 06143216
Totals 3148491.58 0.00 3089683.00 100.0

CountyROBERTS
Highway US 60 ETC
From .556 MI W OF RM 748
To GRAY COUNTY LINE
CSJ 0169-08-022
Proj ID STP 2016(515)HESG
Work Type CENTERLINE TEXTURING
 
227.625 996579.09 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0169-08-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163237
Totals 996579.09 0.00 0.00 0.0

CountyDALLAM
Highway US 385
From SS 17
To SS 24
CSJ 0225-02-017
Proj ID STP 1102(299)
Work Type ADD TURN LANES
 
1.212 755030.70 0.00 768415.16 100.0
CountyDALLAM
Highway US 54
From AT SS 24
To .
CSJ 0238-03-053
Proj ID NH 1102(424)
Work Type ADD TURN LANES
 
0.492 187838.42 0.00 211736.97 100.0
CountyDALLAM
Highway SS 24
From US 385
To US 54
CSJ 1702-02-001
Proj ID STP 1102(299)
Work Type NEW LOCATION 2 LANE RDWY
 
2.183 2132735.86 0.00 2062090.55 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-04-14
Work Began 09-29-14
Work Completed 09-02-15
Time Computed 09-29-14
Contract Working Days 210
Addl Days Granted 14
Working Days Charged 201
Percent Time Used 89
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1702-02-001
(USE24847)BARRICADES UNLIMITED (2.21%)
E. DIAZ TRUCKING (1.69%)
Contract # 08133018
Totals 3075604.98 0.00 3042242.68 100.0

CountyOLDHAM
Highway US 385
From 1 MILE NORTH OF SS 233 (BOYS RANCH)
To HARTLEY COUNTY LINE
CSJ 0226-02-033
Proj ID STP 1502(295)
Work Type RESTORATION
 
5.870 2049389.64 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0226-02-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153023
Totals 2049389.64 0.00 0.00 0.0

CountyOLDHAM
Highway US 385
From CANADIAN RIVER BRIDGE
To 1 MILE NORTH OF SS 233 (BOYS RANCH)
CSJ 0226-02-035
Proj ID STP 2015(586)
Work Type OVERLAY
 
2.149 844687.60 0.00 828662.38 100.0
CountyOLDHAM
Highway US 385
From RM 1061
To CANADIAN RIVER BRIDGE
CSJ 0226-03-056
Proj ID STP 2015(586)
Work Type OVERLAY
 
1.065 450568.79 0.00 479976.51 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-11-15
Work Began 04-21-15
Work Completed 10-09-15
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 75
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0226-02-035
BARRICADES UNLIMITED (2.64%)
SCR CONSTRUCTION CO., INC. (3.49%)
DUSTROL, INC.(0.54%)
Contract # 02153217
Totals 1295256.39 0.00 1308638.89 100.0

CountyOLDHAM
Highway US 385
From B IH 40 C
To RM 1061
CSJ 0226-03-054
Proj ID STP 2014(342)
Work Type RESTORATION OF EXISTING ROADWAY
 
21.693 5497007.02 10070.09 5673200.13 99.9
Work Order 02-12-14
Work Began 06-26-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 60
Addl Days Granted 5
Working Days Charged 146
Percent Time Used 224
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0226-03-054
ALTUS TRAFFIC MANAGEMENT LLC (0.24%)
DUSTY ALLEN, INC.(3.99%)
DUSTROL, INC.(0.28%)
FLAT LINE, INC.(1.57%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.14%)
BARRICADES UNLIMITED (0.22%)
Contract # 01143218
Totals 5497007.02 10070.09 5673200.13 99.9

CountyHARTLEY
Highway US 54
From AT PUNTA DE AGUA CREEK
To .
CSJ 0238-01-030
Proj ID BR 2013(952)
Work Type REPLACE BRIDGE & APPR
 
0.277 2427731.90 0.00 2592602.27 100.0
CountyHARTLEY
Highway US 54
From AT RITA BLANCA CREEK
To .
CSJ 0238-02-035
Proj ID BR 2013(952)
Work Type REPLACE BRIDGE & APPR
 
0.124 1508289.77 0.00 1612033.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-08-13
Work Began 11-18-13
Work Completed 08-14-15
Time Computed 11-24-13
Contract Working Days 245
Addl Days Granted 27
Working Days Charged 269
Percent Time Used 98
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-01-030
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.45%)
DUSTIN ALLEN, INC. (1.54%)
GARY A. CRAIN, INC.(0.30%)
HOLMES CONSTRUCTION CO., L.P.( 13.49%)
BARRICADES UNLIMITED (1.30%)
MH CIVIL CONSTRUCTORS, INC.(0.61%)
LANCO TURF & SEEDING, INC. (0.41%)
Contract # 08133233
Totals 3936021.67 0.00 4204635.87 100.0

CountyDALLAM
Highway US 54
From DALHART CURB & GUTTER
To CHAMBERLIN
CSJ 0238-03-052
Proj ID C 238-3-52
Work Type REHAB EXIST RDWY & ADD PASSING LNS
 
23.304 6417952.72 0.00 6890828.28 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-12
Work Began 09-10-12
Work Completed 05-07-15
Time Computed 09-05-12
Contract Working Days 172
Addl Days Granted 163
Working Days Charged 358
Percent Time Used 106
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-03-052
BARRICADES UNLIMITED-USE NEW NUMBER 24847 ON NEW SUBCONTRACT (2.73%)
DUSTROL, INC.(0.34%)
E. DIAZ TRUCKING (3.00%)
Contract # 06123007
Totals 6417952.72 0.00 6890828.28 100.0

CountySHERMAN
Highway US 54
From DALLAM COUNTY LINE
To US 287
CSJ 0238-05-039
Proj ID NH 2014(226)
Work Type REHAB EXIST RDWY & ADD PASSING LANE
 
6.141 3184352.73 0.00 3191619.88 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-08-14
Work Began 07-15-14
Work Completed 05-07-15
Time Computed 03-18-14
Contract Working Days 92
Addl Days Granted 5
Working Days Charged 138
Percent Time Used 142
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-05-039
(USE24847)BARRICADES UNLIMITED (4.05%)
Contract # 11133218
Totals 3184352.73 0.00 3191619.88 100.0

CountyPOTTER
Highway IH 40
From LP 335
To COULTER ST
CSJ 0275-01-160
Proj ID NH 1402(018)
Work Type RELOCATE ENTRANCE AND EXIT RAMPS
 
0.972 5438822.45 4046.00 4148199.70 76.4
Work Order 11-04-14
Work Began 02-02-15
Work Completed  
Time Computed 11-20-14
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 85
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-160
ALAMO BROTHERS CONCRETE( 11.70%)
BARRICADES UNLIMITED (1.33%)
WILLIS ELECTRIC CO., LP(3.75%)
MICA CORPORATION (1.91%)
Contract # 08143238
Totals 5438822.45 4046.00 4148199.70 76.4

CountyPOTTER
Highway IH 40 ETC
From HELIUM ROAD
To EAST OF SL 335
CSJ 0275-01-166
Proj ID NH 1502(372)
Work Type RELOCATE ENTRANCE AND EXIT RAMPS
 
5.179 26403959.25 0.00 166915.25 0.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 560
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-166
ALAMO BROTHERS CONCRETE(4.85%)
DUSTIN ALLEN, INC. (0.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.47%)
TEXAS CONCRETE PARTNERS, L.P.(4.61%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.23%)
WEST TEXAS BARRICADE AND LIGHT CO. (0.96%)
WILLIS ELECTRIC CO., LP( 10.58%)
Contract # 07153253
Totals 26403959.25 0.00 166915.25 0.6

CountyPOTTER
Highway IH 40
From AT SL335 (LAKESIDE)
To .
CSJ 0275-01-168
Proj ID NH 1502(349)
Work Type CONSTRUCT TURNAROUNDS
 
0.340 2519584.25 101355.64 2379742.20 94.4
CountyRANDALL
Highway SL 335
From 0.13 MILES EAST OF GEORGIA ST.
To 0.26 MILES WEST OF FM 1541
CSJ 2635-02-028
Proj ID STP 2013(605)
Work Type CONVERT NON - FREEWAY TO FREEWAY
 
0.808 17821897.20 2145374.15 5496846.95 30.8
Work Order 07-31-15
Work Began 08-10-15
Work Completed  
Time Computed 08-10-15
Contract Working Days 460
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 22
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-028
TRUMBLE CRANE & RIGGING(0.07%)
DUSTIN ALLEN, INC. (0.87%)
L. A. FULLER & SONS CONSTRUCTION, LTD. ( 22.73%)
WILLIS ELECTRIC CO., LP(1.78%)
OSCAR ORDUNO, INC. (3.65%)
BARRICADES UNLIMITED (0.64%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.67%)
INDUS CONSTRUCTION, L.P. (1.22%)
MCL CONTRACTING, LLC (0.13%)
BREDA COMPANY, INC.(3.37%)
ALAMO BROTHERS CONCRETE(0.28%)
Contract # 04153057
Totals 20341481.45 2246729.79 7876589.15 38.7

CountyCARSON
Highway IH 40
From 3.0 MI EAST OF POTTER CO. LINE
To 3.7 MI WEST OF CONWAY
CSJ 0275-02-069
Proj ID IM 0401(208)
Work Type REHAB EXISTING ROADWAY
 
7.759 5177809.06 0.00 4980934.32 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-15-13
Work Began 10-28-13
Work Completed 01-26-15
Time Computed 01-31-13
Contract Working Days 85
Addl Days Granted 130
Working Days Charged 334
Percent Time Used 155
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-02-069
AMARILLO RMT ENTERPRISE(0.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.05%)
O. TREVINO CONSTRUCTION, LLC (7.18%)
TEX OP CONSTRUCTION, LP(1.36%)
WEST TEXAS RUMBLE STRIP(0.11%)
W.O.E. CONSTRUCTION(0.00%)
Contract # 11123206
Totals 5177809.06 0.00 4980934.32 100.0

page 1 | page 2 | page 3 | page 4