Monthly State Let Construction Report For Amarillo District As Of Sep 21, 2017 Page 2 Of 2

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPOTTER
HighwayVA
FromAT VARIOUS LOCATIONS IN AMARILLO
To.
CSJ0904-00-160
Proj IDSTP 2015(649)
Work TypeCONSTRUCT CURB RAMPS
 
0.0012895601.552979359.7599.9
Work Order05-08-15
Work Began07-06-15
Work Completed
Time Computed05-24-15
Contract Working Days274
Addl Days Granted14
Working Days Charged300
Percent Time Used104
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
ONE WAY CONCRETE (56.56)
BTA SERVICES, LTD. (1.91)
W.A. ROBBINS CONSTRUCTION CO., INC. (6.35)
QLVS, INC. DBA PHASE 3 ELECTRIC (1.30)
PAVEMENT MARKINGS INC. (2.36)
Contract #03153026
Totals2895601.550.002979359.7599.9

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-164
Proj IDSTP 2017(593)
Work TypeTHERMOPLASTIC STRIPING
 
1.0001085462.591318808.0199.9
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed04-14-17
Contract Working Days72
Addl Days Granted33
Working Days Charged88
Percent Time Used83
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-164
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173034
Totals1085462.59110478.951318808.0199.9

CountyPOTTER
HighwayCR
FromON DEWEY AVE AT WEST AMARILLO CREEK
To.
CSJ0904-02-037
Proj IDBR 2014(554)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.0411220116.751369746.1899.9
Work Order06-22-16
Work Began06-28-16
Work Completed
Time Computed06-28-16
Contract Working Days56
Addl Days Granted27
Working Days Charged95
Percent Time Used114
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-02-037
BARRICADES UNLIMITED (0.31)
L. A. FULLER & SONS CONSTRUCTION, LTD. (1.87)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (13.83)
SOUTH TEXAS PAINTING COMPANY (0.62)
WOLFE CONSTRUCTION GROUP, INC. (0.27)
MCL CONTRACTING, LLC (0.77)
Contract #04163235
Totals1220116.750.001369746.1899.9

CountyPOTTER
HighwayRM 1061
FromFM 2381
To7.5 MILES NORTH OF FM 2381
CSJ1245-02-043
Proj IDSTP 1502(299)HES
Work TypeWIDEN ROADWAY FOR SAFETY
 
10.5397907537.757727976.9797.7
CountyPOTTER
HighwayRM 1061
From10.50 MILES NORTH OF FM 2381
ToOLDHAM COUNTY LINE
CSJ1245-02-044
Proj IDSTP 1502(355)
Work TypeADD PASSING LANES FOR SAFETY
 
12.8372230786.342460579.9999.9
Work Order08-20-15
Work Began02-03-16
Work Completed
Time Computed08-03-15
Contract Working Days234
Addl Days Granted19
Working Days Charged190
Percent Time Used75
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-043
BARRICADES UNLIMITED (1.85)
HJC FARMS, INC. (1.25)
W.S. CONSTRUCTION COMPANY (9.93)
WILLIS ELECTRIC CO., LP (0.46)
Contract #06153245
Totals10138324.09438401.0010188556.9699.9

CountyHEMPHILL
HighwayRM 2654
FromSH 33
ToFM 277
CSJ2612-01-011
Proj IDSSW 2612-1-11
Work TypeSAFETY WIDENING OF ROADWAY
 
8.2155653751.984464696.8378.9
Work Order09-16-16
Work Began02-01-17
Work Completed
Time Computed10-17-16
Contract Working Days272
Addl Days Granted0
Working Days Charged109
Percent Time Used40
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2612-01-011
AOC ENVIRONMENTAL, INC. (0.70)
BARRICADES UNLIMITED (0.65)
DOUBLE A CONTRACTING, L.P. (0.96)
DUSTROL, INC. (1.26)
HJC FARMS, INC. (2.76)
HODGES AND SON CONSTRUCTION COMPANY, INC. (8.74)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (13.65)
O. TREVINO CONSTRUCTION, LLC (1.34)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.87)
W.O.E. CONSTRUCTION (0.18)
WILLIS ELECTRIC CO., LP (0.39)
S & S BRIDGE PAINTING, INC. (0.74)
Contract #07163219
Totals5653751.98473807.934464696.8378.9

CountyRANDALL
HighwayLP 335
FromIH 27, E
ToBNSF RR
CSJ2635-02-022
Proj IDDMO 2012(189)
Work TypeADDITIONAL 2 LANES AND BRIDGES
 
3.00032232646.8620914679.3064.8
Work Order03-04-14
Work Began11-03-14
Work Completed
Time Computed03-20-14
Contract Working Days645
Addl Days Granted180
Working Days Charged105
Percent Time Used22
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-022
ALAMO BROTHERS CONCRETE (4.52)
BARRICADES UNLIMITED (1.36)
LONE STAR PRODUCTS (FLOWER MOUND) (0.00)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.73)
MCL CONTRACTING, LLC (0.04)
PENHALL COMPANY (AUSTIN) (0.02)
WILLIS ELECTRIC CO., LP (2.97)
Contract #12133202
Totals32232646.86305589.2920914679.3064.8

page 1 | page 2