Monthly State Let Maintenance Report For Amarillo District As Of Apr 12, 2024 Page 2 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAM
HighwayUS0087
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6398-08-001
Proj IDRMC - 639808001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010527066.32388325.6973.6
Work Order00-00-00
Work Began10-18-22
Work Completed
Time Computed09-01-22
Contract Working Days91
Addl Days Granted91
Working Days Charged55
Percent Time Used30
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6398-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224202
Totals527066.320.00388325.6973.6

CountyMOORE
HighwayUS0287
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6398-09-001
Proj IDRMC - 639809001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010394903.00286624.2572.5
Work Order00-00-00
Work Began10-03-22
Work Completed
Time Computed09-01-22
Contract Working Days68
Addl Days Granted68
Working Days Charged48
Percent Time Used35
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6398-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224205
Totals394903.000.00286624.2572.5

CountyHUTCHINSON
HighwaySH0207
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6398-10-001
Proj IDRMC - 639810001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010380832.00558297.0099.9
Work Order00-00-00
Work Began11-21-22
Work Completed
Time Computed11-01-22
Contract Working Days40
Addl Days Granted40
Working Days Charged50
Percent Time Used62
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6398-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224003
Totals380832.000.00558297.0099.9

CountyHEMPHILL
HighwayUS0060
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6398-11-001
Proj IDRMC - 639811001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010382933.28548702.0499.9
Work Order00-00-00
Work Began10-10-22
Work Completed
Time Computed09-01-22
Contract Working Days45
Addl Days Granted45
Working Days Charged36
Percent Time Used40
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6398-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224406
Totals382933.280.00548702.0499.9

CountyCARSON
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6398-12-001
Proj IDRMC - 639812001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010519383.40450226.96100.0
Work Order00-00-00
Work Began10-25-22
Work Completed09-01-22
Time Computed09-01-22
Contract Working Days62
Addl Days Granted62
Working Days Charged33
Percent Time Used26
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6398-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224407
Totals519383.400.00450226.96100.0

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6399-53-001
Proj IDBPM - 639953001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010738738.00729763.09100.0
Work Order00-00-00
Work Began04-03-23
Work Completed05-12-23
Time Computed03-01-23
Contract Working Days40
Addl Days Granted0
Working Days Charged29
Percent Time Used72
Contractor(s)
THE TRUESDELL CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6399-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224203
Totals738738.000.00729763.09100.0

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6401-00-001
Proj IDRMC - 640100001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010407522.28708394.8499.9
Work Order00-00-00
Work Began07-01-22
Work Completed
Time Computed07-01-22
Contract Working Days365
Addl Days Granted365
Working Days Charged640
Percent Time Used87
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6401-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224209
Totals407522.2834457.64708394.8499.9

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6413-43-001
Proj IDRMC - 641343001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010547812.501046533.0099.9
Work Order00-00-00
Work Began10-01-22
Work Completed
Time Computed10-01-22
Contract Working Days365
Addl Days Granted365
Working Days Charged548
Percent Time Used75
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224231
Totals547812.50178341.001046533.0099.9

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6420-19-001
Proj IDRMC - 642019001
Work TypeCABLE MEDIAN BARRIER SYSTEM REPAIR
 
0.010285464.00438839.0099.9
Work Order00-00-00
Work Began02-01-23
Work Completed
Time Computed12-19-22
Contract Working Days365
Addl Days Granted365
Working Days Charged452
Percent Time Used61
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6420-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224004
Totals285464.0015124.00438839.0099.9

CountyCARSON
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6420-21-001
Proj IDRMC - 642021001
Work TypeCABLE MEDIAN BARRIER SYSTEM REPAIR
 
0.010355464.00368320.0099.9
Work Order00-00-00
Work Began01-31-23
Work Completed
Time Computed12-19-22
Contract Working Days365
Addl Days Granted365
Working Days Charged425
Percent Time Used58
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6420-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224203
Totals355464.0029003.00368320.0099.9

CountyMOORE
HighwayUS0087
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6429-58-001
Proj IDRMC - 642958001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010329575.00649753.0099.9
Work Order00-00-00
Work Began05-02-23
Work Completed
Time Computed03-13-23
Contract Working Days365
Addl Days Granted0
Working Days Charged346
Percent Time Used94
Contractor(s)
E.V.G. ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6429-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234203
Totals329575.000.00649753.0099.9

CountyGRAY
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6434-64-001
Proj IDRMC - 643464001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010394945.00339287.0085.9
Work Order00-00-00
Work Began05-08-23
Work Completed
Time Computed05-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234006
Totals394945.0071493.00339287.0085.9

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6434-90-001
Proj IDRMC - 643490001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101228700.001315018.0099.9
Work Order00-00-00
Work Began08-14-23
Work Completed
Time Computed05-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged232
Percent Time Used31
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234003
Totals1228700.000.001315018.0099.9

CountyCARSON
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6435-60-001
Proj IDRMC - 643560001
Work TypeMILL AND INLAY
 
0.0105263125.002673675.8850.8
Work Order00-00-00
Work Began06-21-23
Work Completed
Time Computed06-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged285
Percent Time Used78
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6435-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234202
Totals5263125.000.002673675.8850.8

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6439-64-001
Proj IDRMC - 643964001
Work TypeCRACK SEAL
 
0.0101224880.401224317.7699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-06-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged48
Percent Time Used26
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6439-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234201
Totals1224880.400.001224317.7699.9

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6441-88-001
Proj IDRMC - 644188001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010350850.00300972.0085.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6441-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234002
Totals350850.0040526.00300972.0085.7

CountyPOTTER
HighwayIH0040
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6442-14-001
Proj IDBPM - 644214001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.0101569569.00592343.4537.7
Work Order00-00-00
Work Began02-26-24
Work Completed
Time Computed01-02-24
Contract Working Days100
Addl Days Granted0
Working Days Charged11
Percent Time Used11
Contractor(s)
THE TRUESDELL CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6442-14-001
FC TRAFFIC CONTROL, INC. (7.45)
MACIAS SPECIALTY CONTRACTING LLC (24.00)
TRP CONSTRUCTION GROUP, LLC (4.19)
Contract #10234001
Totals1569569.00457185.00592343.4537.7

CountyRANDALL
HighwayIH0027
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6445-40-001
Proj IDRMC - 644540001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010315680.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed06-01-24
Contract Working Days37
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MARLANE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234202
Totals315680.000.000.000.0

CountyDEAF SMITH
HighwayUS0060
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6446-72-001
Proj IDMMC - 644672001
Work TypeASPHALT
 
0.010873670.00107092.2412.2
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed10-12-23
Contract Working Days120
Addl Days Granted120
Working Days Charged152
Percent Time Used63
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6446-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234002
Totals873670.0034650.45107092.2412.2

CountyHARTLEY
HighwayUS0054
FromVARIOUS LOCATIONS ~ SEE PLAN SHEETS
ToVARIOUS LOCATIONS ~ SEE PLAN SHEETS
CSJ6446-76-001
Proj IDMMC - 644676001
Work TypeASPHALT
 
0.0101507990.00239416.9715.8
Work Order00-00-00
Work Began10-17-23
Work Completed
Time Computed10-12-23
Contract Working Days120
Addl Days Granted120
Working Days Charged167
Percent Time Used69
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6446-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234003
Totals1507990.0017855.81239416.9715.8

page 1 | page 2 | page 3