AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - ATLANTA DISTRICT

Last Update: Wednesday, July 2, 2014
ITEMS 1122 2001 TO 1122 2057
Items Items Bid Code Range
0100 - 0169
0247 - 0275
0305 - 0361
0400 - 0496
0500 - 0560
0610 - 0686
0772 - 0772
1122 - 1122
2024 - 2201
3120 - 3282
4599 - 4599
5284 - 5369
6006 - 6986
7580 - 7580
8020 - 8994
1122 2001 - 1122 2057
Item No Description Units June 30, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
1122 2001 ROCK FILTER DAMS (INSTALL) (TY 1) LF     1,250.000 25.14000 5
1122 2002 ROCK FILTER DAMS (INSTALL) (TY 2) LF     1,012.000 28.29305 9
1122 2003 ROCK FILTER DAMS (INSTALL) (TY 3) LF     152.000 43.60947 3
1122 2009 ROCK FILTER DAMS (REMOVE) LF     2,414.000 7.65269 14
1122 2011 TEMPORARY PIPE SLOPE DRAINS (12") LF     833.000 37.50000 1
1122 2016 CONSTRUCTION EXITS (INSTALL) (TY 1) SY     233.000 22.21030 2
1122 2019 CONSTRUCTION EXITS (REMOVE) SY     233.000 6.85837 2
1122 2020 EXCAV (EROS & SEDM CONT, IN PLACE) CY     19.000 50.00000 1
1122 2030 CONSTRUCTION PERIMETER FENCE LF     263.000 3.05000 1
1122 2033 SANDBAGS FOR EROSION CONTROL (12") LF     35.000 20.00000 1
1122 2037 TEMPORARY SEDIMENT CONTROL FENCE INSTL LF 940.000 3.00000 49,210.000 2.56240 19
1122 2048 BIOGRD EROSN CONT LOGS (12" DIA) INSTAL LF     320.000 6.00000 1
1122 2049 BIOGRD EROSN CONT LOGS (18" DIA) INSTAL LF     380.000 5.00000 1
1122 2056 BIODEGRADBLE EROSION CONTROL LOGS REMO LF     700.000 1.38400 2
1122 2057 TEMPORARY SEDIMENT CONTROL FENCE REMOV LF 940.000 1.00000 49,210.000 .79278 19