AVERAGE LOW BID UNIT PRICE - MAINTENANCE - ATLANTA DISTRICT

Last Update: Friday, March 27, 2015
ITEMS 712 2005 TO 776 2035
Items Items Bid Code Range
0104 - 0132
0305 - 0361
0400 - 0496
0500 - 0544
0610 - 0690
0712 - 0776
3256 - 3288
4003 - 4003
5935 - 5935
6007 - 6834
7013 - 7224
8251 - 8942
712 2005 - 776 2035
Item No Description Units February 28, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
712 2005 JT / CRCK SEAL (RUBBER - ASPHALT) LMI     520.580 491.00000 1
720 2003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) GAL     7,500.000 55.00000 1
735 2001 DEBRIS REMOVAL (CNTR MEDIANS / MAINLANES CYC     26.000 1,193.56000 1
752 2022 TREE REMOVAL (4" - 12" DIA) EA 1,650.000 48.72727 9,250.000 56.56216 8
752 2023 TREE REMOVAL (12" - 18" DIA) EA 1,290.000 57.94574 6,030.000 81.03648 8
752 2024 TREE REMOVAL (18" - 24" DIA) EA 810.000 97.34568 4,265.000 117.93669 8
752 2025 TREE REMOVAL (24" - 30" DIA) EA 345.000 145.86957 1,770.000 193.10452 8
752 2026 TREE REMOVAL (30" - 36" DIA) EA 190.000 253.81579 1,053.000 283.64198 8
752 2027 TREE REMOVAL (36" - 42" DIA) EA 115.000 281.30435 554.000 391.46209 8
752 2028 TREE REMOVAL (42" - 48" DIA) EA 72.000 368.75000 372.000 492.95968 8
752 2029 TREE REMOVAL (48" - 60" DIA) EA 51.000 637.74510 284.000 618.22183 8
752 2030 TREE REMOVAL (60" - 72" DIA) EA 36.000 1,016.66667 155.000 807.09677 8
752 2045 STUMP REMOVAL EA 90.000 130.00000 435.000 163.79310 8
752 2049 TREE TRIMMING (20' X 30') MI 55.400 1,251.80505 236.260 1,790.58664 6
752 2057 TREE TRIMMING & BRUSH REMOVAL LF     3,000.000 4.00000 1
770 2001 REPAIR RAIL ELEMENT (W - BEAM) LF     7,500.000 8.00000 1
770 2002 REPAIR RAIL ELEMENT (THRIE - BEAM) LF     25.000 1.00000 1
770 2003 REP RAIL ELMNT (THRIE - BM TRANS TO W - BM) LF     13.000 1.00000 1
770 2004 REM / REPL TIMBER / STL POST W / O CONC FND EA     700.000 14.00000 1
770 2005 REM / REPL TIMBER / STL POST W / CONC FND EA     63.000 20.00000 1
770 2007 REPAIR OF TERMINAL ANCHORS POSTS EA     5.000 1.00000 1
770 2008 REPLACE TERMINAL ANCHOR POSTS EA     8.000 1.00000 1
770 2010 REPL SINGLE GDRAIL TERM IMPACT HEAD EA     90.000 100.00000 1
770 2011 REPLACE SINGLE GDRAIL TERMINAL RAIL LF     3,000.000 11.00000 1
770 2012 REPLACE SINGLE GDRAIL TERMINAL POST EA     300.000 38.00000 1
770 2014 REPAIR STEEL POST WITH BASE PLATE EA     25.000 10.00000 1
776 2004 REPAIR (STL POST W / DOUBLED W - BEAMS - T6) LF     150.000 4.00000 1
776 2011 REP METAL POST W / BASE PLATE (T101 RAIL EA     25.000 4.00000 1
776 2034 REPAIR (W - BEAM, TUBE & SPLICE - T101 RAIL) LF     300.000 6.00000 1
776 2035 REPAIR (W - BEAM - T101 RAIL) LF     1,500.000 3.00000 1