Monthly Local Let Maintenance Report For Atlanta District As Of Sep 15, 2014 Page 3 Of 3

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRISON
Highway IH0020
From VARIOUS
To .
CSJ 6274-55-001
Proj ID SUP - 627455001
Work Type PICNIC AREA MAINTENANCE
 
0.001 43752.00 18232.92 46876.81 99.9
Work Order 06-16-14
Work Began 00-00-00
Work Completed  
Time Computed 06-16-14
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 116
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6274-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141931
Totals 43752.00 18232.92 46876.81 99.9

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6276-53-001
Proj ID SUP - 627653001
Work Type JANITORIAL, GROUNDS, AND LANDSCAPING
 
0.001 380884.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6276-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141933
Totals 380884.80 0.00 0.00 0.0

CountyHARRISON
Highway IH0020
From VARIOUS
To .
CSJ 6277-52-001
Proj ID SUP - 627752001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 385403.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6277-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141934
Totals 385403.50 0.00 0.00 0.0

CountyCASS
Highway US0059
From VARIOUS
To .
CSJ 6277-87-001
Proj ID SUP - 627787001
Work Type PICNIC AREA MAINTENANCE - BOWIE / CASS / TITUS
 
0.001 58128.07 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-25-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6277-87-001
COMMUNITY HEALTHCORE (100.00%)
Contract # 08141931
Totals 58128.07 0.00 0.00 0.0

CountyHARRISON
Highway US0059
From VARIOUS
To .
CSJ 6277-90-001
Proj ID SUP - 627790001
Work Type PICNIC AREA MAINTENANCE
 
0.001 36770.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-25-14
Work Began 09-01-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6277-90-001
THE ARC OF HARRISON COUNTY (100.00%)
Contract # 08141932
Totals 36770.00 0.00 0.00 0.0

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6279-17-001
Proj ID SUP - 627917001
Work Type LITTER PICKUP & DISPOSAL
 
0.001 193254.76 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6279-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141935
Totals 193254.76 0.00 0.00 0.0