Monthly State Let Maintenance Report For Atlanta District As Of Aug 16, 2016 Page 1 Of 2

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCASS
Highway 0000000
From 701 EAST MAIN STREET ATLANTA, TX 75551
To 701 EAST MAIN STREET ATLANTA, TX 75551
CSJ 4704-01-645
Proj ID CBC - 470401645
Work Type RENOVATION OR REPAIR
 
0.001 379500.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
INTEGRITY ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-645
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07164219
Totals 379500.00 0.00 0.00 0.0

CountyHARRISON
Highway IH0020
From VARIOUS
To .
CSJ 6236-18-001
Proj ID RMC - 623618001
Work Type CALLOUT MILL AND INLAY
 
0.001 3484869.83 0.00 13477149.73 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-30-12
Work Began 05-30-12
Work Completed 09-30-15
Time Computed 05-30-12
Contract Working Days 114
Addl Days Granted 43
Working Days Charged 128
Percent Time Used 81
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6236-18-001
TEX OP CONSTRUCTION, LP(2.00%)
RK HALL, LLC ( 25.12%)
STRIPING TECHNOLOGY, L.P.(0.64%)
Contract # 04124027
Totals 3484869.83 0.00 13477149.73 100.0

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6245-58-001
Proj ID RMC - 624558001
Work Type INSTALLATION OF PAVEMENT MARKINGS
 
0.001 825987.47 0.00 1629489.33 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-15-13
Work Began 01-17-13
Work Completed 08-21-14
Time Computed 01-22-13
Contract Working Days 115
Addl Days Granted 115
Working Days Charged 117
Percent Time Used 50
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12124011
Totals 825987.47 0.00 1629489.33 100.0

CountyPANOLA
Highway US0059
From VARIOUS
To .
CSJ 6249-94-001
Proj ID BPM - 624994001
Work Type BRIDGE PREVENTIVE MAINTENANCE
 
0.001 689073.40 0.00 716470.06 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-24-14
Work Began 02-27-14
Work Completed 03-03-15
Time Computed 03-04-14
Contract Working Days 125
Addl Days Granted 22
Working Days Charged 132
Percent Time Used 89
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6249-94-001
ODUM SERVICES, L.P.(1.75%)
Contract # 01144031
Totals 689073.40 0.00 716470.06 100.0

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6250-35-001
Proj ID RMC - 625035001
Work Type CALLOUT PAVEMENT MARKINGS
 
0.001 345071.81 0.00 341972.12 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-14
Work Began 04-08-14
Work Completed 06-30-15
Time Computed 04-07-14
Contract Working Days 254
Addl Days Granted 41
Working Days Charged 291
Percent Time Used 98
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6250-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144018
Totals 345071.81 0.00 341972.12 100.0

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6250-36-001
Proj ID RMC - 625036001
Work Type GUIDE AND CALL - OUT SIGN INSTALLATION
 
0.001 248616.00 2500.00 274204.00 99.9
Work Order 05-13-14
Work Began 07-08-14
Work Completed  
Time Computed 05-22-14
Contract Working Days 254
Addl Days Granted 254
Working Days Charged 472
Percent Time Used 92
Contractor(s)
TIME STRIPING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6250-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144016
Totals 248616.00 2500.00 274204.00 99.9

CountyPANOLA
Highway US0059
From VARIOUS
To .
CSJ 6261-63-001
Proj ID RMC - 626163001
Work Type CALLOUT CONCRETE PAVEMENT REPAIR
 
0.001 1645916.50 0.00 2023548.94 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-03-14
Work Began 01-21-14
Work Completed 05-02-16
Time Computed 01-20-14
Contract Working Days 306
Addl Days Granted 199
Working Days Charged 548
Percent Time Used 108
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10134007
Totals 1645916.50 0.00 2023548.94 100.0

CountyCASS
Highway US0059
From VARIOUS
To .
CSJ 6264-52-001
Proj ID RMC - 626452001
Work Type TREE & STUMP REMOVAL (N) TREE TRIMMING
 
0.001 613150.00 0.00 280618.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-24-14
Work Began 03-25-14
Work Completed 04-30-15
Time Computed 04-02-14
Contract Working Days 338
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 32
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6264-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134017
Totals 613150.00 0.00 280618.00 100.0

CountyHARRISON
Highway US0059
From VARIOUS
To .
CSJ 6264-53-001
Proj ID RMC - 626453001
Work Type TREE AND STUMP REMOVAL (SOUTH)
 
0.001 403900.00 0.00 325269.12 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-20-14
Work Began 03-19-14
Work Completed 04-30-15
Time Computed 03-10-14
Contract Working Days 494
Addl Days Granted 0
Working Days Charged 137
Percent Time Used 27
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6264-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134018
Totals 403900.00 0.00 325269.12 100.0

CountyHARRISON
Highway US0059
From VARIOUS
To .
CSJ 6267-20-001
Proj ID RMC - 626720001
Work Type MILL & INLAY & PAVEMENT MARKINGS
 
1.410 1553776.49 0.00 1968988.46 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-16-14
Work Began 06-23-14
Work Completed 04-30-15
Time Computed 06-23-14
Contract Working Days 60
Addl Days Granted 12
Working Days Charged 69
Percent Time Used 95
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-20-001
PANOLA SIGN & BARRICADE, INC.(0.34%)
STRIPING TECHNOLOGY, L.P.(2.79%)
Contract # 03144015
Totals 1553776.49 0.00 1968988.46 100.0

CountyHARRISON
Highway FM0450
From VARIOUS
To .
CSJ 6267-36-001
Proj ID RMC - 626736001
Work Type CALL - OUT SPOT SEALCOAT - DISTRICTWIDE
 
15.840 949999.99 0.00 440139.92 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-14
Work Began 06-15-14
Work Completed 05-12-16
Time Computed 06-09-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 36
Contractor(s)
BLACKTOPPER TECHNOLOGY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144031
Totals 949999.99 0.00 440139.92 100.0

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6268-12-001
Proj ID RMC - 626812001
Work Type CALLOUT RAISED PAVEMENT MARKERS
 
0.001 304753.68 0.00 544866.88 99.9
Work Order 05-13-14
Work Began 10-09-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 254
Addl Days Granted 254
Working Days Charged 463
Percent Time Used 91
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02144013
Totals 304753.68 0.00 544866.88 99.9

CountyBOWIE
Highway US0059
From DISTRICTWIDE
To VARIOUS
CSJ 6269-96-001
Proj ID RMC - 626996001
Work Type INSTALLATION OF PAVEMENT MARKINGS
 
0.001 766525.36 131076.95 202533.30 26.4
Work Order 05-23-16
Work Began 05-23-16
Work Completed  
Time Computed 05-23-16
Contract Working Days 99
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 35
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6269-96-001
STRIPING SYSTEMS, INC. (1.18%)
Contract # 04164013
Totals 766525.36 131076.95 202533.30 26.4

CountyHARRISON
Highway IH0020
From VARIOUS LOCATIONS WITHIN ATL DIST
To .
CSJ 6270-45-001
Proj ID RMC - 627045001
Work Type CALLOUT MILL AND INLAY
 
0.001 2093008.00 130189.95 3213316.55 99.9
Work Order 09-28-15
Work Began 10-05-15
Work Completed  
Time Computed 10-05-15
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 35
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-45-001
RK HALL, LLC ( 52.48%)
TEXOP CONSTRUCTION (9.74%)
Contract # 09144210
Totals 2093008.00 130189.95 3213316.55 99.9

CountyHARRISON
Highway SL0281
From VARIOUS
To .
CSJ 6272-55-001
Proj ID BPM - 627255001
Work Type BRIDGE PREVENTIVE MAINTENANCE
 
0.001 886844.00 17429.38 1227225.04 100.0
Work Order 03-16-15
Work Began 03-23-15
Work Completed 08-16-16
Time Computed 03-23-15
Contract Working Days 190
Addl Days Granted 43
Working Days Charged 221
Percent Time Used 94
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-55-001
PANOLA SIGN & BARRICADE, INC.(1.29%)
ODUM SERVICES, L.P.(6.23%)
STRIPING TECHNOLOGY, L.P.( 11.12%)
Contract # 01154014
Totals 886844.00 17429.38 1227225.04 100.0

CountyBOWIE
Highway US0082
From VARIOUS
To .
CSJ 6273-39-001
Proj ID RMC - 627339001
Work Type INSTALLATION OF PAVEMENT MARKINGS
 
0.001 1148891.16 0.00 1171123.16 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-14
Work Began 11-03-14
Work Completed 08-04-15
Time Computed 11-03-14
Contract Working Days 98
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 56
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144214
Totals 1148891.16 0.00 1171123.16 100.0

CountyBOWIE
Highway FM2789
From 2.2 MI N OF US 82
To US 82
CSJ 6274-33-001
Proj ID RMC - 627433001
Work Type SEAL COAT AND PAVMENT MARKINGS
 
80.897 2626638.75 0.00 2493395.68 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-22-15
Work Began 07-13-15
Work Completed 09-29-15
Time Computed 06-22-15
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 94
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-33-001
STRIPING TECHNOLOGY, L.P.(9.48%)
BRYDL CONTRACTING, INC.(1.14%)
Contract # 01154211
Totals 2626638.75 0.00 2493395.68 100.0

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6275-68-001
Proj ID RMC - 627568001
Work Type INSTALLATION OF TRAFFIC SIGNALS
 
0.001 631703.50 14312.50 669357.86 99.9
Work Order 01-15-15
Work Began 01-27-15
Work Completed  
Time Computed 01-25-15
Contract Working Days 306
Addl Days Granted 306
Working Days Charged 368
Percent Time Used 60
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6275-68-001
BANNER SIGN & BARRICADE, INC. (TYLER)(3.79%)
CARTHAGE DRILLING, INC.(3.15%)
R & R TELCO ENTERPRISES, INC.(8.10%)
DIRECTIONAL DRILLING (6.07%)
Contract # 10144008
Totals 631703.50 14312.50 669357.86 99.9

CountyUPSHUR
Highway US0259
From VARIOUS
To .
CSJ 6276-83-001
Proj ID RMC - 627683001
Work Type TREE & STUMP REMOVAL - W & TREE TRIMMING
 
0.001 494952.00 0.00 577602.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 01-26-15
Work Completed 01-13-16
Time Computed 02-02-15
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 154
Percent Time Used 50
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-83-001
TERRY ENTERPRISES( 21.78%)
Contract # 12144007
Totals 494952.00 0.00 577602.00 100.0

CountyMARION
Highway SH0049
From INTERSECTION OF SH0049/FM0134
To INTERSECTION OF SH0049/FM0134
CSJ 6282-81-001
Proj ID RMC - 628281001
Work Type IMPROVEMENTS TO DRAINAGE ISSUES
 
0.050 232659.00 1477.00 248745.29 100.0
Work Order 02-08-16
Work Began 02-16-16
Work Completed 07-22-16
Time Computed 02-15-16
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 90
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6282-81-001
TOTAL HIGHWAY MAINTENANCE, LLC (6.01%)
Contract # 12154219
Totals 232659.00 1477.00 248745.29 100.0

page 1 | page 2