Monthly State Let Construction Report For Austin District As Of May 10, 2016 Page 2 Of 10

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway SL 275
From AT WILLIAMSON CREEK
To .
CSJ 0016-01-115
Proj ID BR 2016(633)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.080 234842.00 0.00 0.00 0.0
CountyTRAVIS
Highway SL 275
From 825 FT NORTH OF SLAUGHTER LANE
To 465 FT NORTH OF SLAUGHTER LANE
CSJ 0016-01-116
Proj ID BR 2016(633)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.068 58158.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-01-115
ENVIRONMENTAL SAFETY SERVICES, INC.( 14.09%)
Contract # 02163039
Totals 293000.00 0.00 0.00 0.0

CountyTRAVIS
Highway IH 35
From AT SLAUGHTER CREEK OVERPASS
To .
CSJ 0016-01-117
Proj ID NH 2016(386)
Work Type BRIDGE REPLACEMENT
 
2.885 9232872.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-01-117
VOGES DRILLING CO. (1.06%)
FLASHER EQUIPMENT COMPANY(0.48%)
APAC-TEXAS, INC. (7.22%)
ACU CONSTRUCTION LLC (0.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.32%)
ROADWAY SPECIALTIES, INC.(3.12%)
Contract # 12153029
Totals 9232872.16 0.00 0.00 0.0

CountyHAYS
Highway IH 35
From AT CEMENT PLANT ROAD &
To AT RM 150 & FM 1626
CSJ 0016-02-133
Proj ID C 16-2-133
Work Type WDN XSTING BRG & ADD TURNAROUND BRGS
 
5.700 6087133.07 28264.00 5941007.62 99.9
CountyHAYS
Highway IH 35
From FM 2001
To FM 1626/KYLE PKWY
CSJ 0016-02-134
Proj ID C 16-2-134
Work Type REVISE RAMPS & ADD U - TURN BR @ 2001
 
3.000 5334921.24 9096.69 5314467.02 99.6
Work Order 11-08-13
Work Began 01-07-14
Work Completed  
Time Computed 11-24-13
Contract Working Days 307
Addl Days Granted 0
Working Days Charged 425
Percent Time Used 138
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-133
AARON CONCRETE CONTRACTORS, L.P. (0.46%)
ADAY & ASSOCIATES, LLC (0.58%)
BEAIRD DRILLING(0.19%)
BMP SPECIALIST, LLC(1.29%)
FLASHER EQUIPMENT COMPANY(1.55%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(5.17%)
LAYFIELD CONSTRUCTION, INC (1.00%)
MURRAY CONSTRUCTION(0.36%)
PRIMATE CONSTRUCTION, INC. (0.19%)
RAMMING PAVING COMPANY ( 16.39%)
ROAD REPAIR, LLC ( 14.87%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (1.86%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.69%)
TEXAS HIGHWAY WALLS(1.88%)
CP REBAR AND PT INSTALLATION (0.38%)
STATEWIDE MATERIALS TRANSPORT LTD(1.21%)
SCOTT DERR PAINTING CO, LLC(0.21%)
ACE ASPHALT OF ARIZONA, INC. ( 12.65%)
Contract # 08133015
Totals 11422054.31 37360.69 11255474.64 99.8

CountyHAYS
Highway IH 35
From 2000 FEET N OF YARRINGTON RD
To 2000 FEET S OF YARRINGTON RD
CSJ 0016-02-135
Proj ID PTF 2013(927)
Work Type REPLACE BRIDGE
 
0.758 10640445.20 149103.70 8431485.14 79.6
CountyHAYS
Highway IH 35
From 2000 FEET N OF YARRINGTON RD
To 2000 FEET S OF YARRINGTON RD
CSJ 0016-02-144
Proj ID RW 16-2-144
Work Type ADJUSTMENT OF UTILITIES
 
0.758 500343.37 0.00 648265.13 99.9
CountyHAYS
Highway FM 110
From IH 35 EAST FRONTAGE ROAD
To 800 FT EAST OF IH 35 EAST FRT ROAD
CSJ 3545-02-005
Proj ID PTF 2013(927)
Work Type RECONSTRUCT & WIDEN ROAD / INTERSECT
 
0.800 837880.72 40318.09 564100.13 67.3
CountyHAYS
Highway FM 110
From IH 35 EAST FRONTAGE ROAD
To 800 FT EAST OF IH 35 EAST FRT ROAD
CSJ 3545-02-006
Proj ID RW 3545-2-6
Work Type ADJUSTMENT OF UTILITIES
 
0.800 236502.23 0.00 274756.37 99.9
Work Order 01-17-14
Work Began 06-16-14
Work Completed  
Time Computed 06-16-14
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 456
Percent Time Used 108
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-135
DUSTROL, INC.(0.37%)
GUERRA UNDERGROUND, LLC(3.44%)
THE LEVY COMPANY, L.P. (7.31%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.29%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.41%)
TEXAS HIGHWAY WALLS( 11.82%)
FARR FOUNDATION, INC.(0.23%)
FLASHER EQUIPMENT COMPANY(0.84%)
RAMMING PAVING COMPANY ( 11.39%)
RICE ENVIRONMENTAL SERVICES(1.51%)
ROADWAY SPECIALTIES, INC.(0.18%)
BEAIRD DRILLING(1.01%)
BREDA COMPANY, INC.(0.33%)
CALAME CONTRACTING, LLC(0.89%)
LIGHT IT UP ELECTRIC (0.01%)
M & M UNDERGROUND CONSTRUCTION (0.95%)
R K STEPHENS CONSTRUCTION, LLC (2.75%)
PRIMATE CONSTRUCTION, INC. (0.26%)
Contract # 10133201
Totals 12215171.52 189421.79 9918606.77 81.5

CountyHAYS
Highway IH 35
From SL 82
To YARRINGTON ROAD
CSJ 0016-02-136
Proj ID NH 2015(568)
Work Type MILL, SEAL & OVERLAY NB / SB MAINLANE
 
4.042 1672119.35 0.00 1669160.40 99.9
CountyHAYS
Highway IH 35
From SH 80
To SL 82
CSJ 0016-03-105
Proj ID NH 2015(568)
Work Type OVERLAY IH 35 MAINLANES
 
1.078 1516527.86 0.00 1466324.36 96.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-15
Work Began 05-21-15
Work Completed  
Time Computed 04-03-15
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 112
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-136
ALTUS TRAFFIC MANAGEMENT LLC (0.25%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.17%)
CHEROKEE SERVICES(1.19%)
DAN WILLIAMS COMPANY (9.38%)
FLASHER EQUIPMENT COMPANY(2.03%)
FUQUAY, INC. (0.66%)
R.P.V. CONSTRUCTION(7.86%)
WEST TEXAS RUMBLE STRIP(0.12%)
Contract # 02153008
Totals 3188647.21 0.00 3135484.76 99.9

CountyHAYS
Highway IH 35
From TRAVIS COUNTY LINE
To LP 82 NORTH IN SAN MARCOS
CSJ 0016-02-138
Proj ID STP 1502(144)HES
Work Type IMPROVE GUARDRAIL TO STANDARDS
 
24.348 1477885.00 98560.12 865090.77 59.5
Work Order 06-30-15
Work Began 09-17-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 120
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-138
BMP SPECIALIST, LLC( 30.13%)
D & D ENTERPRISES( 15.15%)
PIONEER UTILITIES, INC.(8.76%)
Contract # 05153031
Totals 1477885.00 98560.12 865090.77 59.5

CountyHAYS
Highway IH 35
From AQUARENA SPRINGS DRIVE (LP 82)
To IH 35-BL (SOUTH OLD HWY 81)
CSJ 0016-02-140
Proj ID NH 2015(352)
Work Type BASE REPAIR & OVERLAY (IH 35 SBFR)
 
6.591 1539215.60 22077.75 1521656.76 99.2
CountyHAYS
Highway IH 35
From 350 FT. NORTH OF SL 82
To 740 FT. NORTH OF SL 82
CSJ 0016-03-106
Proj ID NH 2015(352)
Work Type BASE REPAIR & OVERLAY
 
0.074 16628.54 0.00 9432.14 56.7
Work Order 01-13-15
Work Began 10-02-15
Work Completed  
Time Computed 01-29-15
Contract Working Days 33
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 124
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-140
ROADWAY SPECIALTIES, INC.(3.80%)
TRP CONSTRUCTION GROUP, LLC(2.56%)
Contract # 12143014
Totals 1555844.14 22077.75 1531088.90 98.8

CountyHAYS
Highway IH 35
From BLANCO RIVER
To RM 150
CSJ 0016-02-145
Proj ID STP 2016(388)MM
Work Type GRADING, BASE, PVMT, STRUCT & PVMT
 
5.539 8969400.82 665476.59 665476.59 7.4
Work Order 03-11-16
Work Began 04-07-16
Work Completed  
Time Computed 04-07-16
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 4
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-145
AUSTIN WOOD RECYCLING(0.19%)
ROADWAY SPECIALTIES, INC.(2.89%)
PIPE WHOLESALERS OF TEXAS, INC.(8.54%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (6.93%)
DAN WILLIAMS COMPANY ( 30.46%)
Contract # 12153211
Totals 8969400.82 665476.59 665476.59 7.4

CountyHAYS
Highway IH 35
From SL 82
To SH 123
CSJ 0016-03-096
Proj ID NH 2016(389)
Work Type MILL & INLAY FRT RDS
 
3.827 1166528.52 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-03-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163225
Totals 1166528.52 0.00 0.00 0.0

CountyHAYS
Highway IH 35
From SH 123
To RM 12
CSJ 0016-03-101
Proj ID NH 2016(895)
Work Type MILL & INLAY SBFR
 
1.183 386404.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 14
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-03-101
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163018
Totals 386404.30 0.00 0.00 0.0

CountyHAYS
Highway LP 82
From THORPE LANE
To CHARLES AUSTIN ST
CSJ 0016-09-033
Proj ID TCSP 2011(866)
Work Type CONST RAILROAD GRADE SEPARATION STR
 
0.876 19292346.00 1839888.07 7164756.22 37.1
CountyHAYS
Highway LP 82
From THORPE LANE
To CHARLES AUSTIN ST
CSJ 0016-09-035
Proj ID STP 2014(753)
Work Type ROW ACQ, RELOC & UTILITIES
 
0.001 1182226.20 0.00 1136782.97 96.1
CountyHAYS
Highway CS
From AQUARENA SPRGS DR FROM IH 35
To SESSOMS DR
CSJ 0914-33-055
Proj ID STP 2010(185)MM
Work Type CONST BIKE / PED FACILITY
 
0.631 259646.20 0.00 1056.50 0.4
Work Order 10-28-14
Work Began 06-01-15
Work Completed  
Time Computed 04-06-15
Contract Working Days 548
Addl Days Granted 0
Working Days Charged 224
Percent Time Used 40
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-09-033
N-LINE TRAFFIC MAINTENANCE, L.P. (0.56%)
ROADWAY SPECIALTIES, INC.(1.62%)
TEXAS ROAD BORING(1.17%)
AUSTIN WOOD RECYCLING(0.11%)
CHOCTAW ERECTORS, INC. (2.21%)
FLASHER EQUIPMENT COMPANY(0.52%)
PANTHER CREEK TRANSPORTATION, INC. (3.46%)
AARON CONCRETE CONTRACTORS, L.P. (1.43%)
AVERY LEE WILLIAMSON DBA AVERY"S LAWN CARE & LANDSCAPE (1.20%)
GK CONSTRUCTION, LLC (0.84%)
MCKINNEY DRILLING__(BUDA)(1.20%)
TEXAS HIGHWAY WALLS(5.59%)
VSTRUCTURAL LLC(0.43%)
THE LEVY COMPANY, L.P. (5.51%)
LONE STAR PAVING COMPANY (8.29%)
Contract # 07143004
Totals 20734218.40 1839888.07 8302595.69 40.0

CountyMASON
Highway US 87
From AT KOOCK'S BRANCH
To .
CSJ 0071-03-039
Proj ID BR 1502(306)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.053 919216.25 60838.46 813876.62 88.8
Work Order 07-30-15
Work Began 09-08-15
Work Completed  
Time Computed 08-29-15
Contract Working Days 63
Addl Days Granted 32
Working Days Charged 100
Percent Time Used 105
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0071-03-039
N-LINE TRAFFIC MAINTENANCE, L.P. (0.86%)
ROADWAY SPECIALTIES, INC.(4.64%)
FLASHER EQUIPMENT COMPANY(1.99%)
DIAMOND X CONTRACTING, INC ( 21.31%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 10.37%)
Contract # 06153049
Totals 919216.25 60838.46 813876.62 88.8

CountyMASON
Highway US 87
From RM 152
To GILLESPIE COUNTY LINE
CSJ 0071-05-029
Proj ID STP 1602(103)HES
Work Type IMPROVE GUARDRAIL & SFT TRT FXD OBJ
 
25.452 983038.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0071-05-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163208
Totals 983038.53 0.00 0.00 0.0

CountyGILLESPIE
Highway US 290
From AT PEDERNALES RIVER
To .
CSJ 0112-02-031
Proj ID BR 1502(307)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.108 1236398.66 184920.20 949013.73 78.6
Work Order 07-30-15
Work Began 09-21-15
Work Completed  
Time Computed 08-29-15
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 133
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0112-02-031
FLASHER EQUIPMENT COMPANY(2.01%)
LONE STAR PAVING (9.09%)
Contract # 06153029
Totals 1236398.66 184920.20 949013.73 78.6

CountyBLANCO
Highway US 290
From AT ROCKY CREEK
To (STR 0113-03-010)
CSJ 0113-03-027
Proj ID BR 2014(615)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.121 1347191.31 0.00 1435711.19 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-14
Work Began 08-25-14
Work Completed 04-20-16
Time Computed 07-24-14
Contract Working Days 154
Addl Days Granted 66
Working Days Charged 220
Percent Time Used 100
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0113-03-027
AUSTIN WOOD RECYCLING(0.63%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.85%)
TRP CONSTRUCTION GROUP, LLC(4.10%)
ROADWAY SPECIALTIES, INC.(4.41%)
A & R DEMOLITION (2.50%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(5.81%)
EROSION PREVENTION PRODUCTS(2.23%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.28%)
TEXAS CUTTING & CORING, INC. (0.73%)
JUST GROOVING, LTD.(0.29%)
MCL CONTRACTING, LLC (0.24%)
Contract # 05143208
Totals 1347191.31 0.00 1435711.19 100.0

CountyBLANCO
Highway US 281
From US 290
To MILLER CREEK
CSJ 0113-05-047
Proj ID STP 2016(390)
Work Type LEVEL UP, SEAL, THIN OVERLAY
 
6.552 1397340.04 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-05-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163010
Totals 1397340.04 0.00 0.00 0.0

CountyTRAVIS
Highway US 290
From 585 FT EAST OF CONVICT HILL
To 372 FT WEST OF JOE TANNER LANE
CSJ 0113-08-076
Proj ID NH 2013(403)
Work Type INNOVATIVE INTERSECTION IMPROVEMENT
 
1.176 5090960.00 0.00 6962408.02 99.9
CountyTRAVIS
Highway US 290
From 585 FT EAST OF CONVICT HILL
To 372 FT WEST OF JOE TANNER LANE
CSJ 0113-08-079
Proj ID RW 113-8-79
Work Type UTILITY ADJUSTMENTS
 
1.176 900042.50 0.00 950869.53 99.9
CountyTRAVIS
Highway US 290
From 372 FT WEST OF JOE TANNER LANE
To 800 FT EAST OF JOE TANNER LANE
CSJ 0113-09-069
Proj ID NH 2013(403)
Work Type INNOVATIVE INTERSECTION IMPROVEMENT
 
0.222 532369.00 0.00 526490.40 98.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-10-13
Work Began 09-30-13
Work Completed  
Time Computed 09-30-13
Contract Working Days 335
Addl Days Granted 0
Working Days Charged 407
Percent Time Used 121
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0113-08-076
AUSTIN WOOD RECYCLING(0.90%)
BRYANT & FREY CONSTRUCTION (0.60%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.( 10.38%)
ROADWAY SPECIALTIES, INC.(2.21%)
PANTHER CREEK TRANSPORTATION, INC. (4.22%)
APAC-TEXAS, INC. ( 20.26%)
FLASHER EQUIPMENT COMPANY(1.96%)
CUSTOM TRENCH, INC.(0.30%)
KELLYSTONE, INC(1.64%)
DUSTROL, INC.(0.28%)
Contract # 02133227
Totals 6523371.50 0.00 8439767.95 99.9

CountyTRAVIS
Highway US 290
From JOE TANNER RD.
To WESTGATE BLVD.
CSJ 0113-09-070
Proj ID NH 2014(710)
Work Type MILL, SEAL & 1.5 INCH OVERLAY
 
3.324 2002296.57 0.00 1866909.73 93.4
CountyTRAVIS
Highway US 290
From WESTGATE BLVD.
To MANCHACA ROAD
CSJ 0113-13-159
Proj ID NH 2014(710)
Work Type MILL, SEAL & 1.5 INCH OVERLAY
 
0.831 904574.31 0.00 647815.57 71.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-27-14
Work Began 05-18-15
Work Completed  
Time Computed 11-25-14
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 110
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0113-09-070
ALTUS TRAFFIC MANAGEMENT LLC (0.32%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.65%)
TEXOP CONSTRUCTION (6.52%)
TRP CONSTRUCTION GROUP, LLC(4.82%)
TEXAS TRUCKING COMPANY, INC. (3.01%)
Contract # 06143211
Totals 2906870.88 0.00 2514725.30 86.6

CountyTRAVIS
Highway SL 343
From 1500 FEET SOUTH OF PANTHER TRAIL
To PANTHER TRL
CSJ 0113-09-071
Proj ID STP 2015(877)
Work Type MILL, SEAL AND INLAY
 
0.274 320046.68 0.00 297683.38 93.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-01-15
Work Began 08-31-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 21
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 90
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-09-071
THE LEVY COMPANY, L.P. (6.81%)
FLASHER EQUIPMENT COMPANY(4.36%)
ROADWAY SPECIALTIES, INC.(3.91%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.32%)
ENVIRONMENTAL SAFETY SERVICES, INC.(3.91%)
Contract # 04153240
Totals 320046.68 0.00 297683.38 93.0

CountyTRAVIS
Highway SH 71
From EAST OF MONTOPOLIS DR
To US 183
CSJ 0113-13-149
Proj ID NH 1102(240)
Work Type CONST UNDERPASS, FRT RDS & MAIN LANES
 
1.419 33460488.85 0.00 38191177.96 99.9
CountyTRAVIS
Highway SH 71
From EAST OF MONTOPOLIS DR
To US 183
CSJ 0113-13-151
Proj ID RW 113-13-151
Work Type ROW ACQ. AND UTL. ADJ.
 
1.300 1522117.70 0.00 1606821.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-27-11
Work Began 01-26-12
Work Completed  
Time Computed 12-25-11
Contract Working Days 581
Addl Days Granted 72
Working Days Charged 653
Percent Time Used 100
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-149
RICE ENVIRONMENTAL SERVICES(0.33%)
SCOTT DERR PAINTING CO, LLC(0.14%)
HIGHWAY TECHNOLOGIES, INC. (0.22%)
AUSTIN WOOD RECYCLING(0.09%)
INDUS CONSTRUCTION, L.P. (0.39%)
PRIMATE CONSTRUCTION, INC. (0.21%)
BMP SPECIALIST, LLC(0.08%)
TEX OP CONSTRUCTION, LP(0.01%)
PERFORMANCE EQUIPMENT(0.13%)
AUSTIN FILTER SYSTEMS, INC.(3.34%)
J.D. RAMMING PAVING CO., LTD.( 11.54%)
CRAIG OLDEN, INC.( 12.42%)
MCKINNEY DRILLING__(BUDA)(0.66%)
ROYAL VISTA INC. (9.79%)
AARON CONCRETE CONTRACTORS, L.P. (4.70%)
ROADWAY SPECIALTIES, INC.(0.54%)
BOOTHE BROTHERS PAVING COMPANY, INC. (1.34%)
FLASHER EQUIPMENT COMPANY(5.73%)
RANGER EXCAVATING, L.P.(0.00%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (2.11%)
BRYANT & FREY CONSTRUCTION (0.00%)
CHAMPION SITE PREP, L.P. (0.00%)
CENTRAL TEXAS REINFORCEMENT(0.01%)
CHANDLER CONCRETE, INC.(0.57%)
MG DRILLING(0.00%)
REINFORCING STEEL SUPPLY (0.00%)
LONE STAR SITEWORK, LLC(0.57%)
KRL CONSTRUCTION INC.(0.11%)
VILLALOBOS CONCRETE, INC.(2.44%)
Contract # 08113002
Totals 34982606.55 0.00 39797999.14 99.9