Monthly State Let Construction Report For Austin District As Of Aug 16, 2016 Page 2 Of 9

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway LP 275
From WILLIAMSON CREEK
To EBERHART LANE
CSJ 0016-01-109
Proj ID STP 2014(514)
Work Type SEAL & OVERLAY
 
1.038 453261.10 0.00 398530.96 93.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 10-26-15
Work Completed  
Time Computed 06-14-14
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 225
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-01-109
N-LINE TRAFFIC MAINTENANCE, L.P. (0.59%)
CHEROKEE SERVICES(1.68%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.73%)
FLASHER EQUIPMENT COMPANY(3.03%)
LONE STAR PAVING, INC. ( 29.49%)
Contract # 03143205
Totals 453261.10 0.00 398530.96 93.1

CountyTRAVIS
Highway IH 35
From SLAUGHTER LANE
To HAYS COUNTY LINE
CSJ 0016-01-110
Proj ID NH 2016(385)
Work Type MILL, SEAL, & OVERLAY FRTG RDS
 
4.957 2011905.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0016-01-110
N-LINE TRAFFIC MAINTENANCE, L.P. (0.29%)
TRP CONSTRUCTION GROUP, LLC(4.31%)
Contract # 01163039
Totals 2011905.84 0.00 0.00 0.0

CountyTRAVIS
Highway IH 35
From IH 35 AT SLAUGHTER LANE
To .
CSJ 0016-01-114
Proj ID NH 1502(381)
Work Type LANDSCAPING AND IRRIGATION
 
0.100 630022.00 19653.00 509635.25 80.8
Work Order 08-24-15
Work Began 12-01-15
Work Completed  
Time Computed 10-23-15
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 71
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-01-114
N-LINE TRAFFIC MAINTENANCE, L.P. (0.60%)
M & M UNDERGROUND CONSTRUCTION (1.11%)
Contract # 07153057
Totals 630022.00 19653.00 509635.25 80.8

CountyTRAVIS
Highway SL 275
From AT WILLIAMSON CREEK
To .
CSJ 0016-01-115
Proj ID BR 2016(633)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.080 234842.00 41940.25 41940.25 17.8
CountyTRAVIS
Highway SL 275
From 825 FT NORTH OF SLAUGHTER LANE
To 465 FT NORTH OF SLAUGHTER LANE
CSJ 0016-01-116
Proj ID BR 2016(633)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.068 58158.00 1367.50 1367.50 2.3
Work Order 03-15-16
Work Began 07-11-16
Work Completed  
Time Computed 04-06-16
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 23
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-01-115
ENVIRONMENTAL SAFETY SERVICES, INC.( 14.09%)
FRANK JR REINFORCEMENT LLC (0.95%)
Contract # 02163039
Totals 293000.00 43307.75 43307.75 14.7

CountyTRAVIS
Highway IH 35
From AT SLAUGHTER CREEK OVERPASS
To .
CSJ 0016-01-117
Proj ID NH 2016(386)
Work Type BRIDGE REPLACEMENT
 
2.885 9232872.16 436842.50 2191222.29 23.7
Work Order 02-16-16
Work Began 05-03-16
Work Completed  
Time Computed 05-02-16
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 11
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-01-117
VOGES DRILLING CO. (1.06%)
FLASHER EQUIPMENT COMPANY(0.48%)
APAC-TEXAS, INC. (7.22%)
ACU CONSTRUCTION LLC (0.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.32%)
ROADWAY SPECIALTIES, INC.(3.12%)
Contract # 12153029
Totals 9232872.16 436842.50 2191222.29 23.7

CountyHAYS
Highway IH 35
From AT CEMENT PLANT ROAD &
To AT RM 150 & FM 1626
CSJ 0016-02-133
Proj ID C 16-2-133
Work Type WDN XSTING BRG & ADD TURNAROUND BRGS
 
5.700 6087133.07 0.00 5942735.62 99.9
CountyHAYS
Highway IH 35
From FM 2001
To FM 1626/KYLE PKWY
CSJ 0016-02-134
Proj ID C 16-2-134
Work Type REVISE RAMPS & ADD U - TURN BR @ 2001
 
3.000 5334921.24 0.00 5314827.02 99.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-08-13
Work Began 01-07-14
Work Completed  
Time Computed 11-24-13
Contract Working Days 307
Addl Days Granted 0
Working Days Charged 425
Percent Time Used 138
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-133
AARON CONCRETE CONTRACTORS, L.P. (0.46%)
ADAY & ASSOCIATES, LLC (0.58%)
BEAIRD DRILLING(0.19%)
BMP SPECIALIST, LLC(1.29%)
FLASHER EQUIPMENT COMPANY(1.55%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(5.17%)
LAYFIELD CONSTRUCTION, INC (1.00%)
MURRAY CONSTRUCTION(0.36%)
PRIMATE CONSTRUCTION, INC. (0.19%)
RAMMING PAVING COMPANY ( 16.39%)
ROAD REPAIR, LLC ( 14.87%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (1.86%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.69%)
TEXAS HIGHWAY WALLS(1.88%)
CP REBAR AND PT INSTALLATION (0.38%)
STATEWIDE MATERIALS TRANSPORT LTD(1.21%)
SCOTT DERR PAINTING CO, LLC(0.21%)
ACE ASPHALT OF ARIZONA, INC. ( 12.65%)
Contract # 08133015
Totals 11422054.31 0.00 11257562.64 99.8

CountyHAYS
Highway IH 35
From 2000 FEET N OF YARRINGTON RD
To 2000 FEET S OF YARRINGTON RD
CSJ 0016-02-135
Proj ID PTF 2013(927)
Work Type REPLACE BRIDGE
 
0.758 10640445.20 328323.96 9282065.19 88.3
CountyHAYS
Highway IH 35
From 2000 FEET N OF YARRINGTON RD
To 2000 FEET S OF YARRINGTON RD
CSJ 0016-02-144
Proj ID RW 16-2-144
Work Type ADJUSTMENT OF UTILITIES
 
0.758 500343.37 0.00 648265.13 99.9
CountyHAYS
Highway FM 110
From IH 35 EAST FRONTAGE ROAD
To 800 FT EAST OF IH 35 EAST FRT ROAD
CSJ 3545-02-005
Proj ID PTF 2013(927)
Work Type RECONSTRUCT & WIDEN ROAD / INTERSECT
 
0.800 837880.72 14356.80 667532.93 79.6
CountyHAYS
Highway FM 110
From IH 35 EAST FRONTAGE ROAD
To 800 FT EAST OF IH 35 EAST FRT ROAD
CSJ 3545-02-006
Proj ID RW 3545-2-6
Work Type ADJUSTMENT OF UTILITIES
 
0.800 236502.23 0.00 274756.37 99.9
Work Order 01-17-14
Work Began 06-16-14
Work Completed  
Time Computed 06-16-14
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 517
Percent Time Used 123
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-135
DUSTROL, INC.(0.37%)
GUERRA UNDERGROUND, LLC(3.44%)
THE LEVY COMPANY, L.P. (7.31%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (4.29%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.41%)
TEXAS HIGHWAY WALLS( 11.82%)
FARR FOUNDATION, INC.(0.23%)
FLASHER EQUIPMENT COMPANY(0.84%)
RAMMING PAVING COMPANY ( 11.39%)
RICE ENVIRONMENTAL SERVICES(1.51%)
ROADWAY SPECIALTIES, INC.(0.18%)
BEAIRD DRILLING(1.01%)
BREDA COMPANY, INC.(0.33%)
CALAME CONTRACTING, LLC(0.89%)
LIGHT IT UP ELECTRIC (0.01%)
M & M UNDERGROUND CONSTRUCTION (0.95%)
R K STEPHENS CONSTRUCTION, LLC (2.75%)
PRIMATE CONSTRUCTION, INC. (0.26%)
Contract # 10133201
Totals 12215171.52 342680.76 10872619.62 89.9

CountyHAYS
Highway IH 35
From SL 82
To YARRINGTON ROAD
CSJ 0016-02-136
Proj ID NH 2015(568)
Work Type MILL, SEAL & OVERLAY NB / SB MAINLANE
 
4.042 1672119.35 0.00 1717209.40 99.9
CountyHAYS
Highway IH 35
From SH 80
To SL 82
CSJ 0016-03-105
Proj ID NH 2015(568)
Work Type OVERLAY IH 35 MAINLANES
 
1.078 1516527.86 0.00 1466324.36 96.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-15
Work Began 05-21-15
Work Completed  
Time Computed 04-03-15
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 112
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-136
ALTUS TRAFFIC MANAGEMENT LLC (0.25%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.17%)
CHEROKEE SERVICES(1.19%)
DAN WILLIAMS COMPANY (9.38%)
FLASHER EQUIPMENT COMPANY(2.03%)
FUQUAY, INC. (0.66%)
R.P.V. CONSTRUCTION(7.86%)
WEST TEXAS RUMBLE STRIP(0.12%)
Contract # 02153008
Totals 3188647.21 0.00 3183533.76 99.9

CountyHAYS
Highway IH 35
From TRAVIS COUNTY LINE
To LP 82 NORTH IN SAN MARCOS
CSJ 0016-02-138
Proj ID STP 1502(144)HES
Work Type IMPROVE GUARDRAIL TO STANDARDS
 
24.348 1477885.00 65122.43 1192270.17 83.9
Work Order 06-30-15
Work Began 09-17-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 171
Percent Time Used 169
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-138
BMP SPECIALIST, LLC( 30.13%)
D & D ENTERPRISES( 15.15%)
PIONEER UTILITIES, INC.(8.76%)
Contract # 05153031
Totals 1477885.00 65122.43 1192270.17 83.9

CountyHAYS
Highway IH 35
From AQUARENA SPRINGS DRIVE (LP 82)
To IH 35-BL (SOUTH OLD HWY 81)
CSJ 0016-02-140
Proj ID NH 2015(352)
Work Type BASE REPAIR & OVERLAY (IH 35 SBFR)
 
6.591 1539215.60 0.00 1536690.21 99.8
CountyHAYS
Highway IH 35
From 350 FT. NORTH OF SL 82
To 740 FT. NORTH OF SL 82
CSJ 0016-03-106
Proj ID NH 2015(352)
Work Type BASE REPAIR & OVERLAY
 
0.074 16628.54 0.00 9432.14 56.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-13-15
Work Began 10-02-15
Work Completed  
Time Computed 01-29-15
Contract Working Days 33
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 81
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-140
ROADWAY SPECIALTIES, INC.(3.80%)
TRP CONSTRUCTION GROUP, LLC(2.56%)
Contract # 12143014
Totals 1555844.14 0.00 1546122.35 99.3

CountyHAYS
Highway IH 35
From BLANCO RIVER
To RM 150
CSJ 0016-02-145
Proj ID STP 2016(388)MM
Work Type GRADING, BASE, PVMT, STRUCT & PVMT
 
5.539 8969400.82 495537.90 3120799.34 34.7
Work Order 03-11-16
Work Began 04-07-16
Work Completed  
Time Computed 04-07-16
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 27
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-145
AUSTIN WOOD RECYCLING(0.19%)
ROADWAY SPECIALTIES, INC.(2.89%)
PIPE WHOLESALERS OF TEXAS, INC.(8.54%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (6.93%)
DAN WILLIAMS COMPANY ( 30.46%)
FRANK JR REINFORCEMENT LLC (0.05%)
Contract # 12153211
Totals 8969400.82 495537.90 3120799.34 34.7

CountyHAYS
Highway IH 35
From SL 82
To SH 123
CSJ 0016-03-096
Proj ID NH 2016(389)
Work Type MILL & INLAY FRT RDS
 
3.827 1166528.52 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-23-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-03-096
FLASHER EQUIPMENT COMPANY(2.27%)
CHEROKEE SERVICES(4.23%)
Contract # 01163225
Totals 1166528.52 0.00 0.00 0.0

CountyHAYS
Highway IH 35
From SH 123
To RM 12
CSJ 0016-03-101
Proj ID NH 2016(895)
Work Type MILL & INLAY SBFR
 
1.183 386404.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 14
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-03-101
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163018
Totals 386404.30 0.00 0.00 0.0

CountyHAYS
Highway LP 82
From THORPE LANE
To CHARLES AUSTIN ST
CSJ 0016-09-033
Proj ID TCSP 2011(866)
Work Type CONST RAILROAD GRADE SEPARATION STR
 
0.876 19292346.00 737437.75 8542255.54 44.2
CountyHAYS
Highway LP 82
From THORPE LANE
To CHARLES AUSTIN ST
CSJ 0016-09-035
Proj ID STP 2014(753)
Work Type ROW ACQ, RELOC & UTILITIES
 
0.001 1182226.20 0.00 1147173.12 97.0
CountyHAYS
Highway CS
From AQUARENA SPRGS DR FROM IH 35
To SESSOMS DR
CSJ 0914-33-055
Proj ID STP 2010(185)MM
Work Type CONST BIKE / PED FACILITY
 
0.631 259646.20 0.00 28556.50 10.9
Work Order 10-28-14
Work Began 06-01-15
Work Completed  
Time Computed 04-06-15
Contract Working Days 548
Addl Days Granted 0
Working Days Charged 284
Percent Time Used 51
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-09-033
N-LINE TRAFFIC MAINTENANCE, L.P. (0.56%)
ROADWAY SPECIALTIES, INC.(1.62%)
TEXAS ROAD BORING(1.17%)
AUSTIN WOOD RECYCLING(0.11%)
CHOCTAW ERECTORS, INC. (2.21%)
FLASHER EQUIPMENT COMPANY(0.52%)
PANTHER CREEK TRANSPORTATION, INC. (3.46%)
AARON CONCRETE CONTRACTORS, L.P. (1.43%)
AVERY LEE WILLIAMSON DBA AVERY"S LAWN CARE & LANDSCAPE (1.20%)
GK CONSTRUCTION, LLC (0.84%)
MCKINNEY DRILLING__(BUDA)(1.20%)
TEXAS HIGHWAY WALLS(5.59%)
VSTRUCTURAL LLC(0.43%)
THE LEVY COMPANY, L.P. (5.51%)
LONE STAR PAVING COMPANY (8.29%)
Contract # 07143004
Totals 20734218.40 737437.75 9717985.16 46.8

CountyMASON
Highway US 87
From AT KOOCK'S BRANCH
To .
CSJ 0071-03-039
Proj ID BR 1502(306)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.053 919216.25 22503.01 981530.31 99.9
Work Order 07-30-15
Work Began 09-08-15
Work Completed  
Time Computed 08-29-15
Contract Working Days 63
Addl Days Granted 35
Working Days Charged 118
Percent Time Used 120
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0071-03-039
N-LINE TRAFFIC MAINTENANCE, L.P. (0.86%)
ROADWAY SPECIALTIES, INC.(4.64%)
FLASHER EQUIPMENT COMPANY(1.99%)
DIAMOND X CONTRACTING, INC ( 21.31%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 10.37%)
Contract # 06153049
Totals 919216.25 22503.01 981530.31 99.9

CountyMASON
Highway US 87
From RM 152
To GILLESPIE COUNTY LINE
CSJ 0071-05-029
Proj ID STP 1602(103)HES
Work Type IMPROVE GUARDRAIL & SFT TRT FXD OBJ
 
25.452 983038.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0071-05-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163208
Totals 983038.53 0.00 0.00 0.0

CountyGILLESPIE
Highway US 290
From AT PEDERNALES RIVER
To .
CSJ 0112-02-031
Proj ID BR 1502(307)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.108 1236398.66 11939.20 1179779.01 98.4
Work Order 07-30-15
Work Began 09-21-15
Work Completed  
Time Computed 08-29-15
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 160
Percent Time Used 152
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0112-02-031
FLASHER EQUIPMENT COMPANY(2.01%)
LONE STAR PAVING (9.09%)
Contract # 06153029
Totals 1236398.66 11939.20 1179779.01 98.4

CountyBLANCO
Highway US 281
From US 290
To MILLER CREEK
CSJ 0113-05-047
Proj ID STP 2016(390)
Work Type LEVEL UP, SEAL, THIN OVERLAY
 
6.552 1397340.04 354344.82 354344.82 25.3
Work Order 03-16-16
Work Began 07-20-16
Work Completed  
Time Computed 04-15-16
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 7
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-05-047
D. I. J. CONSTRUCTION, INC.(7.49%)
TRP CONSTRUCTION GROUP, LLC(0.52%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 21.54%)
Contract # 01163010
Totals 1397340.04 354344.82 354344.82 25.3

CountyHAYS
Highway US 290
From RM 165
To MCGREGOR LANE
CSJ 0113-07-067
Proj ID NH 1602(599)
Work Type OVERLAY
 
4.214 816443.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0113-07-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163241
Totals 816443.00 0.00 0.00 0.0

CountyTRAVIS
Highway US 290
From 585 FT EAST OF CONVICT HILL
To 372 FT WEST OF JOE TANNER LANE
CSJ 0113-08-076
Proj ID NH 2013(403)
Work Type INNOVATIVE INTERSECTION IMPROVEMENT
 
1.176 5090960.00 0.00 6962408.02 99.9
CountyTRAVIS
Highway US 290
From 585 FT EAST OF CONVICT HILL
To 372 FT WEST OF JOE TANNER LANE
CSJ 0113-08-079
Proj ID RW 113-8-79
Work Type UTILITY ADJUSTMENTS
 
1.176 900042.50 0.00 950869.53 99.9
CountyTRAVIS
Highway US 290
From 372 FT WEST OF JOE TANNER LANE
To 800 FT EAST OF JOE TANNER LANE
CSJ 0113-09-069
Proj ID NH 2013(403)
Work Type INNOVATIVE INTERSECTION IMPROVEMENT
 
0.222 532369.00 0.00 526490.40 98.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-10-13
Work Began 09-30-13
Work Completed  
Time Computed 09-30-13
Contract Working Days 335
Addl Days Granted 0
Working Days Charged 407
Percent Time Used 121
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0113-08-076
AUSTIN WOOD RECYCLING(0.90%)
BRYANT & FREY CONSTRUCTION (0.60%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.( 10.38%)
ROADWAY SPECIALTIES, INC.(2.21%)
PANTHER CREEK TRANSPORTATION, INC. (4.22%)
APAC-TEXAS, INC. ( 20.26%)
FLASHER EQUIPMENT COMPANY(1.96%)
CUSTOM TRENCH, INC.(0.30%)
KELLYSTONE, INC(1.64%)
DUSTROL, INC.(0.28%)
Contract # 02133227
Totals 6523371.50 0.00 8439767.95 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9