Monthly State Let Construction Report For Austin District As Of Jul 13, 2015 Page 8 Of 11

Last Update: Monday, July 13, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBASTROP
Highway VA
From AT BUESCHER STATE PARK
To .
CSJ 0914-18-102
Proj ID C 914-18-102
Work Type OVERLAY
 
2.968 1227537.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-15
Work Began 00-00-00
Work Completed  
Time Computed 07-21-15
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0914-18-102
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153005
Totals 1227537.85 0.00 0.00 0.0

CountyGILLESPIE
Highway CR
From ON OLD SAN ANTONIO AT PEDERNALES
To STR AA0119002
CSJ 0914-19-022
Proj ID BR 2012(703)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.500 2659843.09 0.00 1510266.41 56.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-09-14
Work Began 05-05-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 623
Addl Days Granted 0
Working Days Charged 192
Percent Time Used 30
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-19-022
O & S TRAFFIC SUPPLIES (0.95%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.68%)
ALLEN KELLER COMPANY ( 24.37%)
J R RAMON, INC.(2.72%)
JUST GROOVING, LTD.(0.22%)
ROADWAY SPECIALTIES, INC.(4.79%)
FLASHER EQUIPMENT COMPANY(0.72%)
MESA ROD BUSTERS, INC. (0.25%)
Contract # 02143012
Totals 2659843.09 0.00 1510266.41 56.7

CountyLEE
Highway CR
From ON CR 306 AT MIDDLE YEGUA CREEK
To STR AA01-24-001
CSJ 0914-21-029
Proj ID BR 2012(236)
Work Type REPLACE BRIDGE & APPROACHES
 
0.059 255411.33 0.00 181804.10 100.0
CountyLEE
Highway CR
From ON CR 113 AT ELM CREEK
To STR AA00-34-001
CSJ 0914-21-030
Proj ID BR 2012(235)
Work Type REPLACE BRIDGE & APPROACHES
 
0.072 314588.67 0.00 305693.15 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-02-13
Work Began 08-19-13
Work Completed 08-13-14
Time Computed 08-18-13
Contract Working Days 98
Addl Days Granted 23
Working Days Charged 181
Percent Time Used 149
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-21-029
ROADWAY SPECIALTIES, INC.(3.59%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.08%)
BATTEN DRILLING, INC.(7.56%)
JIM"S SAND & GRAVEL(2.05%)
LONE STAR PAVING CO. (5.98%)
Contract # 05133025
Totals 570000.00 0.00 487497.25 100.0

CountyCALDWELL
Highway CR
From ON OAK GROVE RD AT W FORK PLUM CRK
To (STR AA02-28-001)
CSJ 0914-22-056
Proj ID BR 2013(195)
Work Type REPLACE BRIDGE & APPROACHES
 
0.155 656797.82 -2100.10 686483.13 100.0
CountyCALDWELL
Highway CR
From ON OAK GROVE ROAD (CR 127) @
To TRIBUTARY TO WEST FORK PLUM CREEK
CSJ 0914-22-062
Proj ID CC 914-22-62
Work Type REPLACE STRUCTURE & APPROACHES
 
0.051 160259.62 9868.50 161800.68 100.0
Work Order 07-10-14
Work Began 09-02-14
Work Completed 06-24-15
Time Computed 09-02-14
Contract Working Days 109
Addl Days Granted 14
Working Days Charged 116
Percent Time Used 94
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-22-056
O & S TRAFFIC SUPPLIES (0.66%)
CL CONCRETE( 12.36%)
DOUBLE S PAVING, INC.( 12.00%)
VOGES DRILLING CO. (2.04%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.60%)
FUQUAY, INC. (0.25%)
LONE STAR PAVING (3.61%)
Contract # 05143036
Totals 817057.44 7768.40 848283.81 100.0

CountyCALDWELL
Highway CS
From ON N WALNUT AVE AT SALT BRANCH CRK
To (STR C004-71-001)
CSJ 0914-22-057
Proj ID BR 2014(691)
Work Type REPLACE BRIDGE & APPROACHES
 
0.045 291669.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-22-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153060
Totals 291669.35 0.00 0.00 0.0

CountyCALDWELL
Highway VA
From WITHIN LOCKHART STATE PARK
To .
CSJ 0914-22-065
Proj ID C 914-22-65
Work Type REPAIR & RESURFACE ROADWAY
 
1.850 405128.50 26115.10 26115.10 6.4
Work Order 06-01-15
Work Began 06-24-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-22-065
N-LINE TRAFFIC MAINTENANCE, L.P. (0.46%)
TRP CONSTRUCTION GROUP, LLC(1.96%)
Contract # 04153208
Totals 405128.50 26115.10 26115.10 6.4

CountyBURNET
Highway CR
From ON CR 202 AT N FORK SAN GABRIEL RVR
To STR AA06-22-001
CSJ 0914-24-016
Proj ID BR 2014(460)
Work Type REPLACE BRIDGE & APPROACHES
 
0.036 285095.75 51868.70 322502.65 99.9
Work Order 01-05-15
Work Began 02-04-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 85
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0914-24-016
SAN-ANN-CO., INC.(2.21%)
ROADWAY SPECIALTIES, INC.(7.37%)
D. I. J. CONSTRUCTION, INC.(0.56%)
JUST GROOVING, LTD.(0.43%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.92%)
Contract # 11143007
Totals 285095.75 51868.70 322502.65 99.9

CountyLLANO
Highway CR
From ON CR 216 AT BOARD BRANCH
To STR AA0552001
CSJ 0914-25-006
Proj ID BR 2011(981)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 226113.43 322.00 233815.26 100.0
Work Order 07-18-14
Work Began 09-22-14
Work Completed 03-09-15
Time Computed 09-22-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 82
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-25-006
BXB GROUP INCORPORATION( 46.45%)
TRP CONSTRUCTION GROUP, LLC(2.17%)
Contract # 05143026
Totals 226113.43 322.00 233815.26 100.0

CountyLLANO
Highway CR
From ON CR 202 AT LITTLE LLANO
To STR AA0630001
CSJ 0914-25-007
Proj ID BR 2011(982)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 299364.78 49356.30 49356.30 16.4
Work Order 03-26-15
Work Began 06-22-15
Work Completed  
Time Computed 04-11-15
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 7
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-25-007
N LINE TRAFFIC CONTROL (3.62%)
RICE ENVIRONMENTAL SERVICES(7.82%)
Contract # 02153214
Totals 299364.78 49356.30 49356.30 16.4

CountyHAYS
Highway CR
From ON CR 266 AT SAN MARCOS RIVER
To STR AA02-24-001
CSJ 0914-33-035
Proj ID BR 2005(711)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 576253.11 0.00 559682.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-14
Work Began 10-13-14
Work Completed  
Time Computed 07-27-14
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 147
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-035
ALTUS TRAFFIC MANAGEMENT LLC (0.64%)
ENVIRONMENTAL SAFETY SERVICES, INC.( 11.82%)
FLASHER EQUIPMENT COMPANY(0.74%)
J.D. RAMMING PAVING CO./AUSTIN MATERIALS LLC (6.82%)
BAIRD DRILLING SERVICES, INC.(3.49%)
Contract # 05143214
Totals 576253.11 0.00 559682.00 99.9

CountyHAYS
Highway VA
From VARIOUS LOCATIONS IN HAYS COUNTY
To ON IH 35 AND SH 80
CSJ 0914-33-063
Proj ID STP 2012(552)
Work Type LANDSCAPE AND IRRIGATION
 
0.100 467144.80 516.60 496900.61 99.9
Work Order 06-14-12
Work Began 07-09-12
Work Completed  
Time Computed 07-09-12
Contract Working Days 72
Addl Days Granted 6
Working Days Charged 78
Percent Time Used 100
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-063
LONE STAR TRAFFIC SERVICE, INC.(1.37%)
TERRY PRATHER( 16.78%)
Contract # 05123226
Totals 467144.80 516.60 496900.61 99.9

CountyBLANCO
Highway RM 165
From SL 163
To HAYS C/L
CSJ 0954-02-016
Proj ID STP 2012(553)HRR
Work Type GUARDRAIL & SAFETY TREAT FIXED OBJCTS
 
11.900 816534.84 0.00 878235.90 99.9
CountyBLANCO
Highway RM 165
From SL 163
To BLANCO/HAYS COUNTY LINE
CSJ 0954-02-017
Proj ID STP 2012(553)HRR
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
11.949 4792086.66 0.00 5852644.62 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 10-02-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 261
Addl Days Granted 57
Working Days Charged 471
Percent Time Used 148
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0954-02-017
HIGHWAY TECHNOLOGIES, INC. (1.93%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.76%)
ABC EROSION CONTROL, INC.(0.72%)
AUSTIN WOOD RECYCLING(1.45%)
JMHP, INC. (0.85%)
Contract # 05123212
Totals 5608621.50 0.00 6730880.52 99.9

CountyWILLIAMSON
Highway FM 619
From 0.089 MI. NORTH OF BRUSHY CREEK
To 0.100 MI. SOUTH OF BRUSHY CREEK
CSJ 0986-01-042
Proj ID BR 1502(149)
Work Type REPLACE BRIDGE
 
0.189 1143838.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 0986-01-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153051
Totals 1143838.60 0.00 0.00 0.0

CountyBASTROP
Highway FM 696
From 1.165 MI N OF US 290
To 1.296 MI N OF US 290
CSJ 1073-01-020
Proj ID BR 1502(072)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.131 2191679.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 202
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1073-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153008
Totals 2191679.00 0.00 0.00 0.0

CountyGILLESPIE
Highway RM 783
From US 290
To 8.977 MI S OF US 290
CSJ 1135-01-026
Proj ID STP 2013(028)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
8.977 5106864.29 26995.87 5192717.80 100.0
Work Order 04-03-13
Work Began 04-15-13
Work Completed 01-09-15
Time Computed 04-15-13
Contract Working Days 229
Addl Days Granted 102
Working Days Charged 331
Percent Time Used 100
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1135-01-026
ROADWAY SPECIALTIES, INC.(3.51%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.40%)
RELMCO, INC. ( 31.14%)
D. I. J. CONSTRUCTION, INC.(1.16%)
VOGES DRILLING CO. (1.08%)
LONE STAR PAVING COMPANY (2.40%)
Contract # 02133212
Totals 5106864.29 26995.87 5192717.80 100.0

CountyTRAVIS
Highway FM 969
From DECKER CREEK DRIVE
To BASTROP COUNTY LINE
CSJ 1186-01-087
Proj ID STP 2015(277)HES
Work Type PROVIDE ADD'L PAVED SURFACE WIDTH
 
7.101 5894316.37 254374.12 550484.97 9.3
Work Order 01-05-15
Work Began 03-17-15
Work Completed  
Time Computed 03-17-15
Contract Working Days 398
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 13
Contractor(s)
M.A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-087
ENVIRONMENTAL SAFETY SERVICES, INC.(7.14%)
TRP CONSTRUCTION GROUP, LLC(2.30%)
LONE STAR PAVING, INC. ( 47.54%)
Contract # 11143219
Totals 5894316.37 254374.12 550484.97 9.3

CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-028
Proj ID BR 2013(930)
Work Type REPLACE BRIDGE & APPROACHES
 
1.530 11659867.54 491142.37 7114568.79 61.0
CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-048
Proj ID STP 2012(591)
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.530 2188836.25 89543.60 1556603.62 71.1
Work Order 02-13-14
Work Began 05-19-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 296
Addl Days Granted 3
Working Days Charged 194
Percent Time Used 64
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
C4 CONSTRUCTION SERVICES, LLC(0.88%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.67%)
LINDAMOOD DEMOLITION, INC. (0.95%)
MURRAY CONSTRUCTION(0.13%)
ROADWAY SPECIALTIES, INC.(1.54%)
M & M STRIPING & POWER WASHING, LLC(0.43%)
AARON CONCRETE CONTRACTORS, L.P. (0.81%)
AUSTIN WOOD RECYCLING(0.28%)
BRYANT & FREY CONSTRUCTION (1.50%)
TEX OP CONSTRUCTION, LP(0.14%)
APAC-TEXAS, INC. ( 11.02%)
CP REBAR AND PT INSTALLATION (0.46%)
PRIMATE CONSTRUCTION, INC. (0.12%)
MCKINNEY DRILLING COMPANY(2.77%)
TEXAS HIGHWAY WALLS(3.63%)
PANTHER CREEK TRANSPORTATION, INC. (0.89%)
Contract # 12133203
Totals 13848703.79 580685.97 8671172.41 62.6

CountyTRAVIS
Highway FM 973
From 0.159 MI. SOUTH OF BLAKE MANOR RD.
To 600 FT. SOUTH OF MURCHISON ST.
CSJ 1200-03-045
Proj ID CC 1200-3-45
Work Type ADD CONTINUOUS LEFT TURN LANE
 
0.312 85872.74 0.00 3400.00 3.9
CountyTRAVIS
Highway FM 973
From 0.159 MI. SOUTH OF BLAKE MANOR RD.
To DECKER CREEK
CSJ 1200-03-052
Proj ID STP 1402(058)
Work Type REHAB RDWY, ADD 6' SHOULDERS
 
4.911 3246677.62 16946.00 654483.02 20.1
Work Order 11-12-14
Work Began 01-26-15
Work Completed  
Time Computed 11-28-14
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 32
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-052
M.V. HENKE ENTERPRISES, INC. (1.13%)
ROADWAY SPECIALTIES, INC.(7.55%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.83%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.69%)
Contract # 09143236
Totals 3332550.36 16946.00 657883.02 19.7

CountyTRAVIS
Highway FM 973
From 3880 FT SOUTH OF SH 71
To FM 812
CSJ 1200-03-046
Proj ID STP 2014(621)
Work Type ADD SHOULDERS, REPAIR & OVERLAY
 
3.418 4060301.69 71383.85 2941623.54 72.4
Work Order 05-29-14
Work Began 08-07-14
Work Completed  
Time Computed 07-28-14
Contract Working Days 288
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 49
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-046
AUSTIN WOOD RECYCLING(1.13%)
CHEROKEE SERVICES(0.13%)
FLASHER EQUIPMENT COMPANY(2.42%)
ROADWAY SPECIALTIES, INC.(7.52%)
TRP CONSTRUCTION GROUP, LLC(0.43%)
RELMCO, INC. ( 13.01%)
HAYWOOD BAKER(4.07%)
THE LEVY COMPANY, L.P. (0.10%)
MURRAY CONSTRUCTION(0.53%)
VOGES DRILLING CO. (1.38%)
Contract # 04143030
Totals 4060301.69 71383.85 2941623.54 72.4

CountyWILLIAMSON
Highway FM 1466
From AT DRAW
To (STR 1200-4-6)
CSJ 1200-04-011
Proj ID BR 1502(353)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 597945.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 1200-04-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153052
Totals 597945.34 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11