Monthly State Let Construction Report For Austin District As Of Jul 13, 2021 Page 8 Of 8
Last Update: Friday, July 16, 2021
|
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | TRAVIS |
Highway | FM 734 |
From | 0.1 M. NW OF YAGER LANE |
To | 0.1 M. SE OF YAGER LANE |
CSJ | 3417-03-030 |
Proj ID | STP 2B20(135)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 552366.52 | | 277808.83 | 50.2 |
Work Order | 09-16-20 |
Work Began | 03-15-21 |
Work Completed | |
Time Computed | 03-15-21 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 59 |
Percent Time Used | 32 |
Contractor(s) |
JOE BLAND CONSTRUCTION, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 3417-03-030 AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (41.18) TEXAS MATERIALS GROUP, INC. (15.47) FLASHER EQUIPMENT COMPANY (3.11) ENVIRONMENTAL SAFETY SERVICES, INC. (5.92) KRL CONSTRUCTION INC. (0.00)
|
Contract # | 08203254 |
| Totals | 552366.52 | 105177.18 | 277808.83 | 50.2 |
|
County | HAYS |
Highway | FM 110 |
From | FM 621 |
To | CALDWELL COUNTY LINE |
CSJ | 3545-02-008 |
Proj ID | CC 3545-2-8 |
Work Type | NEW LOCATION NON-FREEWAY |
|
| 2.295 | 7840543.50 | | 7677223.70 | 97.9 |
County | HAYS |
Highway | FM 110 |
From | FM 621 |
To | CALDWELL COUNTY LINE |
CSJ | 3545-02-012 |
Proj ID | ROW 3545-2-12 |
Work Type | RIGHT OF WAY |
|
| 2.295 | 251378.38 | | 241311.20 | 95.9 |
County | CALDWELL |
Highway | FM 110 |
From | HAYS COUNTY LINE |
To | SH 80 |
CSJ | 3545-03-004 |
Proj ID | CC 3545-3-4 |
Work Type | NEW LOCATION NON-FREEWAY |
|
| 0.346 | 5307870.13 | | 4907607.76 | 92.4 |
Work Order | 06-09-20 |
Work Began | 07-27-20 |
Work Completed | |
Time Computed | 07-09-20 |
Contract Working Days | 220 |
Addl Days Granted | 0 |
Working Days Charged | 200 |
Percent Time Used | 90 |
Contractor(s) |
JAMES CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 3545-02-008 BEAIRD DRILLING (2.39) AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.61) AARON CONCRETE CONTRACTORS, L.P. (1.34) BREDA COMPANY, INC. (0.41) FLASHER EQUIPMENT COMPANY (0.57) LONE STAR PAVING COMPANY (16.09) SOUTHEAST GRINDING & GROOVING, LLC (0.06) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.75) STATEWIDE MATERIALS TRANSPORT, LTD. (2.14) MINE SERVICE, INC. (6.80) GP7 CONSTRUCTION INC. (0.21) TORO BRAVO CONSTRUCTION, LLC (0.39)
|
Contract # | 03203001 |
| Totals | 13399792.01 | 1332006.47 | 12826142.66 | 95.7 |
|
County | HAYS |
Highway | FM 110 |
From | AT SH 123 |
To | . |
CSJ | 3545-02-010 |
Proj ID | STP 2020(761) |
Work Type | INTERCHANGE (NEW OR RECONSTRUCTED) |
|
| 0.625 | 5092653.87 | | 5569171.85 | 99.9 |
Work Order | 05-14-20 |
Work Began | 06-01-20 |
Work Completed | |
Time Computed | 06-01-20 |
Contract Working Days | 188 |
Addl Days Granted | 20 |
Working Days Charged | 167 |
Percent Time Used | 80 |
Contractor(s) |
HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 3545-02-010 AARON CONCRETE CONTRACTORS, L.P. (5.45) ADCOCK 4 INVESTMENTS, LLC (5.29) DEPENDABLE FENCE & WELDING CO. INC. (2.52) BREDA COMPANY, INC. (0.61) F & W ELECTRICAL CONTRACTORS, INC. (1.03) FLASHER EQUIPMENT COMPANY (0.88) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.46) VOGES DRILLING CO. (2.43)
|
Contract # | 04203212 |
| Totals | 5092653.87 | 46599.17 | 5569171.85 | 99.9 |
|