Monthly State Let Construction Report For Austin District As Of Jul 13, 2021 Page 8 Of 8

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayFM 734
From0.1 M. NW OF YAGER LANE
To0.1 M. SE OF YAGER LANE
CSJ3417-03-030
Proj IDSTP 2B20(135)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
552366.52277808.8350.2
Work Order09-16-20
Work Began03-15-21
Work Completed
Time Computed03-15-21
Contract Working Days180
Addl Days Granted0
Working Days Charged59
Percent Time Used32
Contractor(s)
JOE BLAND CONSTRUCTION, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 3417-03-030
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (41.18)
TEXAS MATERIALS GROUP, INC. (15.47)
FLASHER EQUIPMENT COMPANY (3.11)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.92)
KRL CONSTRUCTION INC. (0.00)
Contract #08203254
Totals552366.52105177.18277808.8350.2

CountyHAYS
HighwayFM 110
FromFM 621
ToCALDWELL COUNTY LINE
CSJ3545-02-008
Proj IDCC 3545-2-8
Work TypeNEW LOCATION NON-FREEWAY
 
2.2957840543.507677223.7097.9
CountyHAYS
HighwayFM 110
FromFM 621
ToCALDWELL COUNTY LINE
CSJ3545-02-012
Proj IDROW 3545-2-12
Work TypeRIGHT OF WAY
 
2.295251378.38241311.2095.9
CountyCALDWELL
HighwayFM 110
FromHAYS COUNTY LINE
ToSH 80
CSJ3545-03-004
Proj IDCC 3545-3-4
Work TypeNEW LOCATION NON-FREEWAY
 
0.3465307870.134907607.7692.4
Work Order06-09-20
Work Began07-27-20
Work Completed
Time Computed07-09-20
Contract Working Days220
Addl Days Granted0
Working Days Charged200
Percent Time Used90
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3545-02-008
BEAIRD DRILLING (2.39)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.61)
AARON CONCRETE CONTRACTORS, L.P. (1.34)
BREDA COMPANY, INC. (0.41)
FLASHER EQUIPMENT COMPANY (0.57)
LONE STAR PAVING COMPANY (16.09)
SOUTHEAST GRINDING & GROOVING, LLC (0.06)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.75)
STATEWIDE MATERIALS TRANSPORT, LTD. (2.14)
MINE SERVICE, INC. (6.80)
GP7 CONSTRUCTION INC. (0.21)
TORO BRAVO CONSTRUCTION, LLC (0.39)
Contract #03203001
Totals13399792.011332006.4712826142.6695.7

CountyHAYS
HighwayFM 110
FromAT SH 123
To.
CSJ3545-02-010
Proj IDSTP 2020(761)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
0.6255092653.875569171.8599.9
Work Order05-14-20
Work Began06-01-20
Work Completed
Time Computed06-01-20
Contract Working Days188
Addl Days Granted20
Working Days Charged167
Percent Time Used80
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3545-02-010
AARON CONCRETE CONTRACTORS, L.P. (5.45)
ADCOCK 4 INVESTMENTS, LLC (5.29)
DEPENDABLE FENCE & WELDING CO. INC. (2.52)
BREDA COMPANY, INC. (0.61)
F & W ELECTRICAL CONTRACTORS, INC. (1.03)
FLASHER EQUIPMENT COMPANY (0.88)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.46)
VOGES DRILLING CO. (2.43)
Contract #04203212
Totals5092653.8746599.175569171.8599.9