Monthly State Let Construction Report For Beaumont District As Of Jul 14, 2017 Page 1 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIBERTY ETC
HighwayUS 90 ETC
FromHARRIS CO LINE
ToSH 146
CSJ0028-03-100
Proj IDSTP 1502(169)HES
Work TypeSFTY TRT FXD OBJ
 
41.8542871187.103010210.6899.9
Work Order06-30-15
Work Began08-25-15
Work Completed
Time Computed07-31-15
Contract Working Days152
Addl Days Granted123
Working Days Charged290
Percent Time Used105
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0028-03-100
AMERICAN REMEDIATION OPTIONS, INC. (20.31)
COWBELL TRAFFIC SERVICES, INC. (0.43)
Contract #05153230
Totals2871187.1058457.103010210.6899.9

CountyLIBERTY ETC
HighwayUS 90 ETC
From@ FM 1409
To.
CSJ0028-03-103
Proj IDSTP 2016(932)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.300760550.60746724.6698.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-12-16
Work Began09-08-16
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged78
Percent Time Used97
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-03-103
BUYERS BARRICADES, INC. (2.36)
SPECIALTY DRILLING, LTD. (13.80)
SPRING CREEK CONSTRUCTION, INC. (1.27)
Contract #04163223
Totals760550.600.00746724.6698.1

CountyLIBERTY
HighwayUS 90
FromSH 61 IN DEVERS
To4.0 MI W OF JEFFERSON CO. LINE
CSJ0028-05-042
Proj IDSTP 2013(796)MM
Work TypeGR, BS, STR, PVMT, SIGN
 
5.44020677586.4019064421.3892.5
Work Order09-11-13
Work Began12-12-13
Work Completed
Time Computed09-27-13
Contract Working Days540
Addl Days Granted0
Working Days Charged572
Percent Time Used105
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-05-042
AMERICAN REMEDIATION OPTIONS, INC. (1.47)
BREDA COMPANY, INC. (7.31)
CPAVE, INC. (0.32)
NORMAN HIGHWAY CONSTRUCTORS, INC. (8.78)
PRIMATE CONSTRUCTION, INC. (0.07)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.64)
TEX OP CONSTRUCTION, LP (0.72)
TEXAS LAND CLEARING, INC. (1.34)
SIEMENS INDUSTRY, INC. (0.07)
HOUSTON SAWING & DRILLING (0.02)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.17)
AARON CONCRETE CONTRACTORS, L.P. (0.25)
CRABTREE BARRICADE SYSTEMS, INC. (0.07)
HEMPHILL WBE PILE DRIVING CO. (0.02)
Contract #06133002
Totals20677586.40351046.8219064421.3892.5

CountyJEFFERSON
HighwayUS 90
FromSH 326
To4.094 MILES E OF SH 326
CSJ0028-06-078
Proj IDSTP 1702(502)HES
Work TypeGR, BS,STR,PVMT
 
4.0941139171.290.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-06-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173232
Totals1139171.290.000.000.0

CountyJEFFERSON ETC
HighwayUS 90 ETC
FromLIBERTY C/L
ToMEEKER ROAD
CSJ0028-06-081
Proj IDSTP 2017(041)
Work TypeSEAL COAT
 
145.0668722487.187344595.3084.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-06-16
Work Began05-01-17
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged28
Percent Time Used62
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-06-081
INTERSTATE BARRICADES & MARKINGS, INC. (10.77)
BRYDL CONTRACTING, INC. (0.59)
Contract #09163019
Totals8722487.181490315.267344595.3084.2

CountyORANGE
HighwayIH 10
FromAT NECHES RIVER BRIDGE
To(STR 002809065)
CSJ0028-09-111
Proj IDBR 1102(477)
Work TypeSTR, LIGHTING
 
1.05558877950.0053629647.3091.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-16-12
Work Began06-25-12
Work Completed
Time Computed00-00-00
Contract Working Days1,085
Addl Days Granted504
Working Days Charged1,506
Percent Time Used94
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-09-111
AMERICAN REMEDIATION OPTIONS, INC. (0.06)
ESSARY, HART & MACWILIAM,INC. (6.77)
SCOTT DERR PAINTING CO (0.35)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (1.85)
CARTHAGE DRILLING, INC. (0.14)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.11)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.16)
INTERSTATE BARRICADES & MARKINGS, INC. (0.48)
C PAVE, INC. (0.04)
ASHTON SAWING AND DRILLING LLC (0.10)
ROADWAY CONSTRUCTION, LLC (0.03)
PENHALL COMPANY (0.05)
BORE TECH CONSTRUCTION, LLC (0.00)
Contract #02123001
Totals58877950.00450581.6253629647.3091.3

CountyORANGE
HighwayIH 10
FromFM 1442, EAST
ToUP RR
CSJ0028-11-179
Proj IDC 28-11-179
Work TypeGR, STR, BS, PVMT, SIGN
 
5.10510166446.611152264.9311.3
CountyORANGE
HighwayIH 10
FromUP RR OVERPASS, EAST
To0.54 MILES EAST OF FM 3247
CSJ0028-14-112
Proj IDC 28-14-112
Work TypeGR, STR, BS, PVMT, SIGN
 
1.9222252157.891094000.0048.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-12-16
Work Began05-01-17
Work Completed
Time Computed00-00-00
Contract Working Days275
Addl Days Granted0
Working Days Charged21
Percent Time Used7
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0028-11-179
LONESTAR TRAFFIC SAFETY, LLC (0.18)
AMERICAN REMEDIATION OPTIONS, INC. (4.60)
FARR FOUNDATION, INC. (2.66)
MESA ROD BUSTERS, INC. (1.07)
SCOTT DERR PAINTING CO, LLC (0.03)
C PAVE, INC. (0.27)
TRAF-TEX, INC. (6.10)
STRIPE LINES, INC. (3.46)
Contract #11163205
Totals12418604.50734646.572246264.9318.0

CountyORANGE
HighwayIH 10
FromKCS RR, EAST
ToCOW BAYOU
CSJ0028-11-193
Proj IDNH 1502(421)
Work TypeGR, BS, PVMT, SIGN, STRIPE
 
4.9837661803.936175662.7880.6
CountyORANGE
HighwayIH 10
FromCOW BAYOU, EAST
ToFM 1442
CSJ0028-11-199
Proj IDC 28-11-199
Work TypeGR, STR, BS, PVMT
 
1.7475427820.804893805.6490.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-10-16
Work Began03-22-16
Work Completed
Time Computed00-00-00
Contract Working Days449
Addl Days Granted0
Working Days Charged230
Percent Time Used51
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-11-193
CPAVE, INC. (0.41)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (0.92)
JMHP, INC. (1.13)
L D CONSTRUCTION (11.49)
MESA ROD BUSTERS, INC. (3.19)
RICE ENVIRONMENTAL SERVICES (0.67)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.48)
ENVIRONMENTAL ALLIES, L.P. (0.91)
FARR FOUNDATION, INC. (2.88)
A1 EROSION CONTROL (0.26)
AMERICAN REMEDIATION OPTIONS, INC. (0.75)
R. ORTIZ TRUCKING (0.00)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.32)
ROSALES TRUCKING (0.00)
Contract #11153031
Totals13089624.73283907.2111069468.4284.5

CountyORANGE
HighwayIH 10
From0.5 MILES EAST OF SH 62, EAST
ToUP RR OVERPASS (FRONTAGE ROAD)
CSJ0028-11-203
Proj IDNH 1702(093)
Work TypeBS REPAIR, ACP, STRIPE
 
0.5303360292.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days154
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0028-11-203
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173012
Totals3360292.770.000.000.0

CountyORANGE
HighwayIH 10
FromAT LITTLE CYPRESS BAYOU
To(STR 002814069)AND(STR 002814068)
CSJ0028-14-100
Proj IDBR 2013(443)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1895064499.67637263.9012.5
CountyORANGE
HighwayIH 10
FromW OF ADAMS BAYOU, EAST
ToW OF SABINE RIVER BRIDGE
CSJ0028-14-108
Proj IDIM 0108(184)
Work TypeGR, STR, BS, PVMT, SIGN
 
3.66947282929.2517310571.1236.6
CountyORANGE
HighwayIH 10
FromAT SH 87 AND T&NO RR
To(STR 002814108 & 109)
CSJ0028-14-109
Proj IDBR 2013(226)
Work TypeGR, BS, PVMT & STR
 
0.32216093789.7815844153.3398.4
Work Order03-18-14
Work Began05-30-14
Work Completed
Time Computed04-03-14
Contract Working Days679
Addl Days Granted237
Working Days Charged490
Percent Time Used53
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-14-100
A-1 EROSION CONTROL, LLC (0.16)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.08)
AMERICAN REMEDIATION OPTIONS, INC. (0.16)
BORTUNCO (0.66)
DAVIS TREE EXPERTS (0.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.23)
MESA ROD BUSTERS, INC. (7.03)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.45)
SCOTT DERR PAINTING CO, LLC (0.05)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.80)
TRAF-TEX, INC. (0.97)
ROADWAY CONSTRUCTION, LLC (0.31)
C PAVE, INC. (0.01)
NORMAN HIGHWAY CONSTRUCTORS, INC. (0.46)
CRABTREE BARRICADE SYSTEMS, INC. (0.03)
JANCO (0.98)
Contract #02143032
Totals68441218.701053439.3133791988.3549.3

CountyHARDIN
HighwayUS 69
FromCOOKS LAKE RD., SOUTH
ToJEFFERSON C/L
CSJ0065-06-063
Proj IDC 65-6-63
Work TypeINSERT FILL,MSE WALLS & BRIDGE
 
0.7456982134.450.000.0
CountyJEFFERSON
HighwayUS 69
FromHARDIN C/L, SOUTH
ToTRAM ROAD
CSJ0065-07-060
Proj IDC 65-7-60
Work TypeINSERT FILL, MSE WALLS AND BRIDGE
 
0.4593655645.740.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days262
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0065-06-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173204
Totals10637780.190.000.000.0

CountyHARDIN
HighwayUS 69
FromSH 327, SOUTH
ToELLIS DRIVE
CSJ0200-10-079
Proj IDNH 1402(092)
Work TypeGR, BS, ACP, STRIPE
 
3.8617502185.057840997.8299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-30-14
Work Began11-26-14
Work Completed
Time Computed11-14-16
Contract Working Days208
Addl Days Granted17
Working Days Charged219
Percent Time Used97
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-10-079
DUSTROL, INC. (0.20)
NORMAN HIGHWAY CONSTRUCTORS, INC. (3.62)
AMERICAN REMEDIATION OPTIONS, INC. (5.56)
CRABTREE BARRICADE SYSTEMS, INC. (1.69)
ALL AMERICAN FABRICATION, LLC. (2.69)
RAMCO SAND & GRAVEL, LLC (5.38)
MIRE TRUCKING & SERVICES (1.71)
Contract #08143025
Totals7502185.050.007840997.8299.9

CountyJEFFERSON
HighwayUS 69
From700 FT SOUTH OF LUCAS DRIVE, SOUTH
ToIH 10
CSJ0200-11-098
Proj IDNH 2013(224)
Work TypeGR, BS, PVMT, STR
 
1.51513432254.8913048145.3797.1
CountyJEFFERSON
HighwayUS 69
FromSH 105, SOUTH
To700 FT SOUTH OF LUCAS DRIVE
CSJ0200-11-100
Proj IDNH 2013(224)
Work TypeGR, BS, PVMT, STR
 
1.93213958606.7814900345.8099.9
Work Order10-07-13
Work Began01-13-14
Work Completed
Time Computed10-23-13
Contract Working Days636
Addl Days Granted43
Working Days Charged838
Percent Time Used123
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-11-098
AMERICAN REMEDIATION OPTIONS, INC. (2.07)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (7.70)
CPAVE, INC. (1.22)
CRABTREE BARRICADE SYSTEMS, INC. (1.30)
DUSTROL, INC. (2.04)
J & M CONTRACTING, COMPANY (5.49)
SCHNABEL FOUNDATION COMPANY (0.66)
WEBBER BARRIER SERVICES, LLC. (2.97)
CKORP, LLC (0.25)
RAMCO SAND & GRAVEL, LLC (0.05)
NORMAN HIGHWAY CONSTRUCTORS, INC. (0.10)
HOLES INCORPORATED (0.04)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.16)
W. W. FOUNDATION DRILLING, LTD. (0.81)
BAY CITY TRAFFIC (0.03)
PANTHER DRILLING AND FOUNDATION REPAIR (0.32)
TX DOWN UNDER CONSTRUCTION LLC (0.04)
TEXAS CUTTING & CORING, INC. (0.04)
SERVICELINE TRANSPORT (0.16)
MIRE TRUCKING & SERVICES (0.16)
WIDGEON CONSTRUCTION, INC. (0.05)
Contract #07133205
Totals27390861.67186040.9027948491.1799.9

CountyHARDIN
HighwayFM 418
From1.7 MI E OF US 69
To2.075 MI E OF US 69
CSJ0200-12-014
Proj IDSTP 1702(504)HES
Work TypeSFTY TREAT FXD OBJ
 
0.390141278.700.000.0
CountyHARDIN
HighwayFM 418
From2.075 MI E OF US 69
ToSILSBEE
CSJ0784-01-047
Proj IDSTP 1702(505)HES
Work TypeSFTY TREAT FXD OBJ
 
6.765870202.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 0200-12-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173226
Totals1011480.750.000.000.0

CountyHARDIN ETC
HighwayFM 418 ETC
From0.292 MI E OF US 69
To0.083 MILES W OF CR 162
CSJ0200-12-015
Proj IDSTP 2017(802)HES
Work TypeRUMBLE STRIPS
 
58.274134987.6892845.0768.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-17
Work Began05-19-17
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged10
Percent Time Used38
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-12-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173219
Totals134987.6836582.4292845.0768.7

CountyJEFFERSON
HighwayUS 69
From0.25 MILES NORTH OF SPUR 93 (NB)
To0.25 MILES SOUTH OF SPUR 93 (NB)
CSJ0200-14-080
Proj IDBR 1502(523)
Work TypeEMBANKMENT, GRADING, RETAINING WALL
 
0.500942740.51805541.5985.4
CountyJEFFERSON
HighwayUS 69
From0.25 MILES NORTH OF SPUR 93 (SB)
To0.25 MILES SOUTH OF SPUR 93 (SB)
CSJ0200-14-081
Proj IDBR 1502(523)
Work TypeEMBANKMENT, GRADING, RETAINING WALL
 
0.5002645969.732894181.6899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-18-16
Work Began07-21-16
Work Completed
Time Computed00-00-00
Contract Working Days206
Addl Days Granted0
Working Days Charged155
Percent Time Used75
Contractor(s)
HAYWARD BAKER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-14-080
AARON"S CONCRETE SAWING AND SEALING INC. (2.09)
CRABTREE BARRICADE SYSTEMS, INC. (4.81)
AMERICAN REMEDIATION OPTIONS, INC. (2.26)
ANGEL BROTHERS ENTERPRISES, LTD. (15.25)
TRICON PRECAST, LTD. (5.68)
BOULDERSCAPE, INC. (14.14)
J.A. GAMEZ TRUCKING SERVICES (7.52)
Contract #08153228
Totals3588710.248470.033699723.2799.9

CountyJASPER
HighwayUS 190
FromAT NECHES RIVER RELIEF
To(STR 021308068)
CSJ0213-08-077
Proj IDBR 1502(228)
Work TypeGR, BS, PVMT & STR
 
0.6027078117.165337627.1278.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-06-15
Work Began11-16-15
Work Completed
Time Computed00-00-00
Contract Working Days252
Addl Days Granted13
Working Days Charged340
Percent Time Used128
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0213-08-077
AMERICAN REMEDIATION OPTIONS, INC. (1.28)
CRABTREE BARRICADE SYSTEMS, INC. (0.92)
J & M CONTRACTING, COMPANY (4.19)
TEX OP CONSTRUCTION, LP (0.21)
CPAVE, INC. (0.34)
COASTAL PILE CUTTERS, LLC (0.40)
PRIMATE CONSTRUCTION, INC. (0.15)
Contract #06153039
Totals7078117.16198.005337627.1278.2

CountyCHAMBERS
HighwaySH 61
FromLIBERTY C/L
ToFM 1663
CSJ0242-03-074
Proj IDSTP 2016(949)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
2.285889007.06861785.6396.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-22-16
Work Began12-07-16
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged64
Percent Time Used95
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0242-03-074
CRABTREE BARRICADE SYSTEMS, INC. (2.29)
J & M CONTRACTING, COMPANY (26.00)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (4.62)
WEST TEXAS RUMBLE STRIP (0.54)
A-1 EROSION CONTROL, LLC (0.46)
Contract #04163228
Totals889007.0634135.00861785.6396.9

CountyCHAMBERS ETC
HighwaySH 61 ETC
FromIH 10
ToFM 563
CSJ0242-03-075
Proj IDSTP 2017(614)HES
Work TypeRUMBLE STRIPS
 
84.348244900.271980.000.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-10-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days31
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0242-03-075
WEST TEXAS RUMBLE STRIP (18.16)
Contract #02173032
Totals244900.270.001980.000.8

CountyJASPER
HighwaySH 62
From0.168 MILES SOUTH OF FM 253, SOUTH
To3.379 MILES NORTH OF NEWTON CO/L
CSJ0243-01-050
Proj IDSTP 1502(422)
Work TypeGR, BS, OV, STRIPE
 
9.0179416731.773101354.8032.9
CountyJASPER
HighwayFM 2246
From0.118 MILES WEST OF SH 62, EAST
ToSH 62
CSJ2120-01-027
Proj IDSTP 1502(666)
Work TypeGR, BS, OV, STRIPE
 
0.118139544.340.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-16
Work Began08-30-16
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged137
Percent Time Used68
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0243-01-050
AMERICAN REMEDIATION OPTIONS, INC. (0.76)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.95)
WEST TEXAS RUMBLE STRIP (0.11)
J & M CONTRACTING, COMPANY (6.40)
Contract #12153016
Totals9556276.11273886.893101354.8032.4

page 1 | page 2 | page 3