Monthly State Let Construction Report For Beaumont District As Of Aug 12, 2014 Page 2 Of 3

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyNEWTON
Highway SH 12
From NEWTON CO/L
To SH 87
CSJ 0499-02-029
Proj ID STP 2014(593)
Work Type PLANE, SMA, STRIPE
 
3.094 1990411.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-07-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0499-02-029
CPAVE, INC.(2.76%)
DUSTROL, INC.(9.83%)
CRABTREE BARRICADE SYSTEMS, INC. (1.56%)
Contract # 04143014
Totals 1990411.83 0.00 0.00 0.0

CountyORANGE
Highway SH 12
From SH 62
To NEWTON CO/L
CSJ 0499-03-057
Proj ID STP 2014(803)
Work Type PLANE, SMA, STRIPE
 
3.859 2279714.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-07-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0499-03-057
DUSTROL, INC.( 10.11%)
CRABTREE BARRICADE SYSTEMS, INC. (1.56%)
Contract # 04143232
Totals 2279714.00 0.00 0.00 0.0

CountyJEFFERSON
Highway SP 215
From SH 73, EAST
To 0.794 MI W OF SH 87
CSJ 0508-06-020
Proj ID STP 2014(509)
Work Type FDR, BS, MILL, OVERLAY
 
1.371 1979708.80 100090.00 395991.10 20.0
Work Order 04-02-14
Work Began 05-02-14
Work Completed  
Time Computed 04-18-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 65
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-06-020
AMERICAN REMEDIATION OPTIONS, INC. (6.15%)
CRABTREE BARRICADE SYSTEMS, INC. (1.57%)
CPAVE, INC.( 24.56%)
DUSTROL, INC.(4.06%)
PINNACLE GRINDING & GROOVING, LLC(4.03%)
Contract # 02143031
Totals 1979708.80 100090.00 395991.10 20.0

CountyNEWTON
Highway FM 363
From AT THICKETY CREEK
To (STR 062703004)
CSJ 0627-03-024
Proj ID STP 2012(537)
Work Type GR, BS, OCST, ACP, STR
 
0.941 3877298.91 12338.54 3722440.63 100.0
Work Order 07-12-12
Work Began 08-15-12
Work Completed 07-14-14
Time Computed 07-28-12
Contract Working Days 237
Addl Days Granted 8
Working Days Charged 340
Percent Time Used 138
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0627-03-024
HOUSTON SAWING & DRILLING(0.09%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.00%)
DUSTROL, INC.(2.21%)
CRABTREE BARRICADE SYSTEMS, INC. (1.06%)
NORMAN HIGHWAY CONSTRUCTORS, INC.(5.72%)
AMERICAN REMEDIATION OPTIONS, INC. (3.02%)
MESA ROD BUSTERS, INC. (0.35%)
PRIMATE CONSTRUCTION, INC. (0.26%)
Contract # 05123040
Totals 3877298.91 12338.54 3722440.63 100.0

CountyJEFFERSON
Highway SP 136
From 0.65 MILES NORTH OF SH 347
To 0.61 MILES NORTH
CSJ 0653-01-013
Proj ID CM 2014(843)
Work Type GR, BS, STR, PVMT
 
0.610 569227.19 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 87
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0653-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143045
Totals 569227.19 0.00 0.00 0.0

CountyCHAMBERS
Highway IH 10
From 0.210 MI WEST OF FM 1663, EAST
To JEFFERSON CO/L
CSJ 0739-01-045
Proj ID IM 0108(176)
Work Type PLANE, MBGF, PFC
 
2.528 1179835.95 0.00 1094786.91 96.4
CountyJEFFERSON
Highway IH 10
From CHAMBERS CO/L, EAST
To 0.65 MI E OF FM 365
CSJ 0739-02-147
Proj ID IM 0108(176)
Work Type PLANE, MBGF, PFC, UPGRADE BRIDGE RAIL
 
8.022 3506970.90 0.00 3628020.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 08-04-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 216
Percent Time Used 126
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0739-01-045
WILLOW CITY SIGN & RAIL, INC.(4.20%)
CRABTREE BARRICADE SYSTEMS, INC. (2.62%)
SEMARCK LANDSCAPE SERVICES, INC. (0.09%)
CHEROKEE SERVICES(1.32%)
Contract # 02133208
Totals 4686806.85 0.00 4722807.09 99.9

CountyLIBERTY
Highway FM 787
From AT TARKINGTON BAYOU
To (STR 081301009)
CSJ 0813-01-096
Proj ID BR 2013(921)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 1341288.27 58875.00 770919.49 57.4
Work Order 01-06-14
Work Began 02-14-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 184
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 44
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0813-01-096
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 14.91%)
EROSION CONTROL, INC.(0.11%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.44%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.02%)
ROZCO CONTRACTING, INC.( 46.48%)
MESA ROD BUSTERS, INC. (0.30%)
JOHN REED AND COMPANY, LLC ( 40.30%)
Contract # 08133243
Totals 1341288.27 58875.00 770919.49 57.4

CountyORANGE
Highway FM 105
From FM 1135, SOUTH
To 0.68 MI W OF FM 408
CSJ 0883-02-074
Proj ID STP 2013(524)
Work Type GR, BS, ACP, MBGF, STR, STRIPE
 
4.189 4197094.08 0.00 4118276.74 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-01-13
Work Began 08-13-13
Work Completed 07-16-14
Time Computed 08-17-13
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 105
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0883-02-074
DUSTROL, INC.(5.85%)
NORMAN HIGHWAY CONSTRUCTORS, INC.( 17.51%)
SIEMENS INDUSTRY, INC. (0.17%)
CRABTREE BARRICADE SYSTEMS, INC. (1.10%)
AMERICAN REMEDIATION OPTIONS, INC. (2.50%)
MANSHACK & SONS, INC.(1.57%)
RAMCO GROUP, LLC (1.42%)
ALLSTATE SIGNAL & CONSTRUCTION, LLC(0.21%)
Contract # 04133023
Totals 4197094.08 0.00 4118276.74 100.0

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To .
CSJ 0920-00-105
Proj ID STP 1102(164)
Work Type LANDSCAPE
 
1.150 702815.00 0.00 618461.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-25-11
Work Began 10-24-11
Work Completed 08-05-14
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 57
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-105
CRABTREE BARRICADE SYSTEMS, INC. (1.77%)
CLASSIC TEJAS CONSTRUCTION, INC. (1.28%)
Contract # 07113230
Totals 702815.00 0.00 618461.50 100.0

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To .
CSJ 0920-00-108
Proj ID STP 2012(216)
Work Type CURB RAMPS
 
0.001 2540920.76 0.00 2180903.30 85.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-12
Work Began 04-16-12
Work Completed  
Time Computed 03-28-12
Contract Working Days 250
Addl Days Granted 104
Working Days Charged 350
Percent Time Used 98
Contractor(s)
BRYSTAR CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-108
CRABTREE BARRICADE SYSTEMS, INC. (6.14%)
AMERICAN REMEDIATION OPTIONS, INC. (2.30%)
SOUTH TEXAS ILLUMINATION, LLC( 14.61%)
TEXAS CONCRETE AND DEMOLITION, INC.( 18.53%)
BOUMANS & ASSOCIATES, INC. (1.92%)
WILLIAMSON CONSTRUCTION & EQUIPMENT(5.68%)
MARK BEAN CONSTRUCTION (6.75%)
NORMAN HIGHWAY CONSTRUCTORS, INC.(4.58%)
Contract # 01123218
Totals 2540920.76 0.00 2180903.30 85.8

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To LOCATIONS ON IH 10/US 69
CSJ 0920-00-110
Proj ID STP 2012(539)
Work Type LANDSCAPE
 
1.000 177098.00 0.00 160470.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-19-12
Work Began 10-05-12
Work Completed 08-05-14
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 82
Contractor(s)
AES CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-110
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123223
Totals 177098.00 0.00 160470.00 100.0

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To .
CSJ 0920-00-111
Proj ID STP 2013(710)
Work Type LANDSCAPE
 
1.000 432659.00 3230.75 376728.77 87.4
Work Order 08-08-13
Work Began 12-04-13
Work Completed  
Time Computed 11-04-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 105
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-111
CRABTREE BARRICADE SYSTEMS, INC. (2.09%)
Contract # 05133223
Totals 432659.00 3230.75 376728.77 87.4

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To .
CSJ 0920-00-116
Proj ID STP 2014(646)
Work Type LANDSCAPE
 
3.428 832522.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 219
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-116
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143219
Totals 832522.01 0.00 0.00 0.0

CountyLIBERTY
Highway CR
From CR 2331 AT LONG JOHN CREEK
To (STR AA2331001)
CSJ 0920-02-087
Proj ID BR 2014(255)
Work Type GR, BS, STR, PVMT
 
0.100 529670.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-02-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143229
Totals 529670.95 0.00 0.00 0.0

CountyHARDIN
Highway VA
From BIG THICKET VISITOR CENTER, SOUTH
To CITY OF KOUNTZE
CSJ 0920-03-073
Proj ID CM 2013(922)
Work Type GR, BS, PVMT, LNDSCP
 
6.862 2734519.40 0.00 2308785.94 84.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-25-13
Work Began 01-13-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 88
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-03-073
CRABTREE BARRICADE SYSTEMS, INC. (0.21%)
CLASSIC TEJAS CONSTRUCTION, INC. (3.89%)
Contract # 08133226
Totals 2734519.40 0.00 2308785.94 84.4

CountyNEWTON
Highway CR
From CR 2069 AT MCGRAW CREEK
To (STR AA0230001)
CSJ 0920-06-029
Proj ID BR 2014(257)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 354697.28 0.00 0.00 0.0
CountyNEWTON
Highway CR
From CR 2125 AT MCGRAW CRK
To (STR AA0153001)
CSJ 0920-06-030
Proj ID BR 2014(258)
Work Type GR, BS, STR, PVMT
 
0.100 306602.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-04-14
Work Began 00-00-00
Work Completed  
Time Computed 08-20-14
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0920-06-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143032
Totals 661300.20 0.00 0.00 0.0

CountyJEFFERSON
Highway CS
From CONCORD RD FROM SH 105
To LUCAS DR.
CSJ 0920-38-153
Proj ID HP 450(1)
Work Type GR, STR, BS, PVMT, STRIPE, SIGNAL
 
1.780 11284746.71 0.00 3762439.73 33.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-12
Work Began 04-23-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 364
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 3
Contractor(s)
TRADECO INFRAESTRUCTURA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-153
CRABTREE BARRICADE SYSTEMS, INC. (0.39%)
HEMPHILL PILE DRIVING CO., A CORP. (0.19%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (0.49%)
AMERICAN REMEDIATION OPTIONS, INC. (0.88%)
SOLIS TRUCKING (0.56%)
GARY WHITMAN MATERIALS, INC. (0.16%)
ACCESS DATA SUPPLY, INC. (6.52%)
VIMAC-USA, INC.(5.87%)
PREMIERE DESIGN SOLUTIONS, INC.(5.87%)
Contract # 07123217
Totals 11284746.71 0.00 3762439.73 33.3

CountyJEFFERSON
Highway CS
From AT AMELIA ELEMENTARY SCHOOL
To .
CSJ 0920-38-218
Proj ID CM 2012(281)
Work Type GR, BS, STR, SIDEWALKS
 
0.100 113854.36 0.00 112296.53 98.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-12
Work Began 06-25-12
Work Completed  
Time Computed 06-04-12
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 94
Contractor(s)
PLACO, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0920-38-218
TRIANGLE CONCRETE SERVICES, INC. ( 62.12%)
Contract # 05123031
Totals 113854.36 0.00 112296.53 98.6

CountyLIBERTY
Highway FM 1008
From 5.0 MI S OF SH 321 (N), SOUTH
To 7.3 MI
CSJ 0952-01-051
Proj ID STP 2014(056)HES
Work Type GR, BS, STR, PVMT
 
7.296 3175645.38 1242633.44 3058657.95 96.3
Work Order 01-17-14
Work Began 03-25-14
Work Completed  
Time Computed 03-19-14
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 85
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0952-01-051
WATERS CONSTRUCTION CO., INC.( 13.73%)
J & M CONTRACTING, COMPANY (1.81%)
BATTERSON,LLP(1.38%)
COWBELL TRAFFIC SERVICES, INC. (0.40%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.17%)
CEN TEX HYDROSEED, INC.(0.28%)
Contract # 10133016
Totals 3175645.38 1242633.44 3058657.95 96.3

CountyNEWTON
Highway FM 1004
From SH 87, SOUTH
To JASPER CO/L
CSJ 1274-02-013
Proj ID STP 2014(481)
Work Type MILL, BASE, ACP, STR, STRIPE
 
4.142 1507560.61 139618.46 339800.36 22.5
Work Order 04-25-14
Work Began 00-00-00
Work Completed  
Time Computed 05-11-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 60
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1274-02-013
AMERICAN REMEDIATION OPTIONS, INC. (1.95%)
CRABTREE BARRICADE SYSTEMS, INC. (2.65%)
NORMAN HIGHWAY CONSTRUCTORS, INC.( 18.12%)
Contract # 03143220
Totals 1507560.61 139618.46 339800.36 22.5