Monthly State Let Construction Report For Beaumont District As Of Dec 10, 2014 Page 2 Of 3

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyJEFFERSON
Highway SH 87
From AT CRANE BAYOU
To (STR 030603027)
CSJ 0306-03-120
Proj ID BR 2013(856)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 2487698.29 133693.32 1148050.70 46.1
CountyJEFFERSON
Highway SH 73
From 25 ST @ CRANE BAYOU LATERAL
To (STR 050804166)
CSJ 0508-04-155
Proj ID BR 2013(856)
Work Type STR
 
0.100 308554.08 0.00 405352.73 99.9
Work Order 10-07-13
Work Began 12-03-13
Work Completed  
Time Computed 10-23-13
Contract Working Days 356
Addl Days Granted 48
Working Days Charged 140
Percent Time Used 34
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-03-120
CRABTREE BARRICADE SYSTEMS, INC. (2.13%)
AMERICAN REMEDIATION OPTIONS, INC. (2.32%)
NORMAN HIGHWAY CONSTRUCTORS, INC.( 35.12%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.04%)
PRIMATE CONSTRUCTION, INC. (0.22%)
CERTIFIED PLACERS LLC(0.24%)
CPAVE, INC.(0.09%)
Contract # 07133024
Totals 2796252.37 133693.32 1553403.43 55.5

CountyJEFFERSON
Highway SH 73
From AT RAINBOW BRIDGE
To (STR 030603015)
CSJ 0306-03-123
Proj ID NH 2014(978)
Work Type CLEAN AND REPAINT BRIDGE
 
1.460 26599824.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-17-14
Work Began 00-00-00
Work Completed  
Time Computed 11-02-14
Contract Working Days 614
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SAFFO CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-03-123
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143202
Totals 26599824.20 0.00 0.00 0.0

CountyJEFFERSON
Highway SH 87
From AT VETERANS MEMORIAL BRIDGE
To (STR 030603030)
CSJ 0306-03-124
Proj ID NH 2014(979)
Work Type STAY CABLE MAINTENANCE
 
1.787 2318400.00 1135590.00 1135590.00 48.9
Work Order 09-22-14
Work Began 11-03-14
Work Completed  
Time Computed 10-08-14
Contract Working Days 102
Addl Days Granted 5
Working Days Charged 20
Percent Time Used 18
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0306-03-124
CRABTREE BARRICADE SYSTEMS, INC. (0.16%)
INTECH CONTRACTING LLC ( 33.42%)
ALPIN TECHNIK UND INGENIEURSERVICE GMBH( 41.16%)
Contract # 08143035
Totals 2318400.00 1135590.00 1135590.00 48.9

CountyNEWTON
Highway SH 12
From NEWTON CO/L
To SH 87
CSJ 0499-02-029
Proj ID STP 2014(593)
Work Type PLANE, SMA, STRIPE
 
3.094 1990411.83 0.00 1956705.71 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-07-14
Work Began 09-01-14
Work Completed 10-17-14
Time Computed 00-00-00
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 64
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0499-02-029
CPAVE, INC.(2.76%)
DUSTROL, INC.(9.83%)
CRABTREE BARRICADE SYSTEMS, INC. (1.56%)
Contract # 04143014
Totals 1990411.83 0.00 1956705.71 100.0

CountyORANGE
Highway SH 12
From SH 62
To NEWTON CO/L
CSJ 0499-03-057
Proj ID STP 2014(803)
Work Type PLANE, SMA, STRIPE
 
3.859 2279714.00 0.00 2181781.48 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-07-14
Work Began 10-06-14
Work Completed 11-25-14
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 68
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0499-03-057
DUSTROL, INC.( 10.11%)
CRABTREE BARRICADE SYSTEMS, INC. (1.56%)
Contract # 04143232
Totals 2279714.00 0.00 2181781.48 100.0

CountyJEFFERSON
Highway SP 215
From SH 73, EAST
To 0.794 MI W OF SH 87
CSJ 0508-06-020
Proj ID STP 2014(509)
Work Type FDR, BS, MILL, OVERLAY
 
1.371 1979708.80 354700.78 900860.83 47.2
Work Order 04-02-14
Work Began 05-02-14
Work Completed  
Time Computed 04-18-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 157
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-06-020
AMERICAN REMEDIATION OPTIONS, INC. (6.15%)
CRABTREE BARRICADE SYSTEMS, INC. (1.57%)
CPAVE, INC.( 24.56%)
DUSTROL, INC.(4.06%)
PINNACLE GRINDING & GROOVING, LLC(4.03%)
Contract # 02143031
Totals 1979708.80 354700.78 900860.83 47.2

CountyJEFFERSON
Highway SP 136
From 0.65 MILES NORTH OF SH 347
To 0.61 MILES NORTH
CSJ 0653-01-013
Proj ID CM 2014(843)
Work Type GR, BS, STR, PVMT
 
0.610 569227.19 143738.92 506682.88 89.0
Work Order 08-20-14
Work Began 09-15-14
Work Completed  
Time Computed 09-05-14
Contract Working Days 87
Addl Days Granted 8
Working Days Charged 44
Percent Time Used 55
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0653-01-013
AMERICAN REMEDIATION OPTIONS, INC. (0.36%)
CRABTREE BARRICADE SYSTEMS, INC. (6.01%)
Contract # 06143045
Totals 569227.19 143738.92 506682.88 89.0

CountyCHAMBERS
Highway IH 10
From 0.210 MI WEST OF FM 1663, EAST
To JEFFERSON CO/L
CSJ 0739-01-045
Proj ID IM 0108(176)
Work Type PLANE, MBGF, PFC
 
2.528 1179835.95 0.00 1094396.91 96.6
CountyJEFFERSON
Highway IH 10
From CHAMBERS CO/L, EAST
To 0.65 MI E OF FM 365
CSJ 0739-02-147
Proj ID IM 0108(176)
Work Type PLANE, MBGF, PFC, UPGRADE BRIDGE RAIL
 
8.022 3506970.90 0.00 3630570.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 08-04-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 218
Percent Time Used 127
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0739-01-045
WILLOW CITY SIGN & RAIL, INC.(4.20%)
CRABTREE BARRICADE SYSTEMS, INC. (2.62%)
SEMARCK LANDSCAPE SERVICES, INC. (0.09%)
CHEROKEE SERVICES(1.32%)
Contract # 02133208
Totals 4686806.85 0.00 4724967.09 99.9

CountyJEFFERSON
Highway FM 364
From DELAWARE STREET
To PHELAN BLVD.
CSJ 0786-01-080
Proj ID CM 2015(250)
Work Type CONCRETE PAVEMENT
 
1.309 647657.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-17-14
Work Began 00-00-00
Work Completed  
Time Computed 12-03-14
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WIDGEON CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0786-01-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143212
Totals 647657.70 0.00 0.00 0.0

CountyLIBERTY
Highway FM 787
From AT TARKINGTON BAYOU
To (STR 081301009)
CSJ 0813-01-096
Proj ID BR 2013(921)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 1341288.27 34918.01 1141054.16 85.0
Work Order 01-06-14
Work Began 02-14-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 184
Addl Days Granted 0
Working Days Charged 141
Percent Time Used 76
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0813-01-096
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 14.91%)
EROSION CONTROL, INC.(0.11%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.44%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.02%)
ROZCO CONTRACTING, INC.( 46.48%)
MESA ROD BUSTERS, INC. (0.30%)
JOHN REED AND COMPANY, LLC ( 40.30%)
Contract # 08133243
Totals 1341288.27 34918.01 1141054.16 85.0

CountyORANGE
Highway FM 105
From OLD HWY 90, SOUTH
To UNION PACIFIC RR
CSJ 0883-02-079
Proj ID STP 2015(463)
Work Type MILL, ACP, GR, STRIPE
 
1.588 290384.74 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0883-02-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143020
Totals 290384.74 0.00 0.00 0.0

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To .
CSJ 0920-00-111
Proj ID STP 2013(710)
Work Type LANDSCAPE
 
1.000 432659.00 0.00 379728.77 88.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-13
Work Began 12-04-13
Work Completed  
Time Computed 11-04-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 105
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-111
CRABTREE BARRICADE SYSTEMS, INC. (2.09%)
Contract # 05133223
Totals 432659.00 0.00 379728.77 88.1

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To .
CSJ 0920-00-112
Proj ID CM 2015(252)
Work Type INSTALL DYNAMIC MESSAGE SIGNS
 
1.000 319467.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-112
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143010
Totals 319467.08 0.00 0.00 0.0

CountyJEFFERSON
Highway VA
From DISTRICTWIDE
To .
CSJ 0920-00-116
Proj ID STP 2014(646)
Work Type LANDSCAPE
 
3.428 832522.01 0.00 312747.75 37.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-14
Work Began 10-20-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 219
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 27
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-00-116
CLASSIC TEJAS CONSTRUCTION, INC. (3.46%)
CRABTREE BARRICADE SYSTEMS, INC. (1.68%)
Contract # 05143219
Totals 832522.01 0.00 312747.75 37.5

CountyLIBERTY
Highway CR
From CR 2331 AT LONG JOHN CREEK
To (STR AA2331001)
CSJ 0920-02-087
Proj ID BR 2014(255)
Work Type GR, BS, STR, PVMT
 
0.100 529670.95 102554.84 216040.44 40.7
Work Order 08-20-14
Work Began 10-09-14
Work Completed  
Time Computed 09-05-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 52
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-02-087
STRIPES & STOPS COMPANY, INC.(1.13%)
FORDE CONSTRUCTION COMPANY, INC. (5.85%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.60%)
Contract # 07143229
Totals 529670.95 102554.84 216040.44 40.7

CountyHARDIN
Highway VA
From BIG THICKET VISITOR CENTER, SOUTH
To CITY OF KOUNTZE
CSJ 0920-03-073
Proj ID CM 2013(922)
Work Type GR, BS, PVMT, LNDSCP
 
6.862 2734519.40 0.00 2635373.58 97.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-25-13
Work Began 01-13-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 163
Percent Time Used 135
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-03-073
CRABTREE BARRICADE SYSTEMS, INC. (0.21%)
CLASSIC TEJAS CONSTRUCTION, INC. (5.58%)
Contract # 08133226
Totals 2734519.40 0.00 2635373.58 97.6

CountyHARDIN
Highway CS
From FM 3513
To 290' WEST OF FM 3513
CSJ 0920-03-078
Proj ID CM 2014(842)
Work Type GR, BS, STR, PVMT
 
0.055 76999.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-21-14
Work Began 00-00-00
Work Completed  
Time Computed 12-07-14
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-03-078
CRABTREE BARRICADE SYSTEMS, INC. (9.32%)
AMERICAN REMEDIATION OPTIONS, INC. (2.48%)
Contract # 10143012
Totals 76999.35 0.00 0.00 0.0

CountyHARDIN
Highway CS
From US 69/287
To WEST CHANCE ROAD
CSJ 0920-03-079
Proj ID CM 2014(841)
Work Type SIDEWALKS AND RAMPS
 
1.330 504663.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-02-14
Work Began 00-00-00
Work Completed  
Time Computed 12-18-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0920-03-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143007
Totals 504663.79 0.00 0.00 0.0

CountyNEWTON
Highway CR
From CR 2069 AT MCGRAW CREEK
To (STR AA0230001)
CSJ 0920-06-029
Proj ID BR 2014(257)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 354697.28 115004.62 265478.92 74.8
CountyNEWTON
Highway CR
From CR 2125 AT MCGRAW CRK
To (STR AA0153001)
CSJ 0920-06-030
Proj ID BR 2014(258)
Work Type GR, BS, STR, PVMT
 
0.100 306602.92 53750.00 102415.00 33.4
Work Order 08-04-14
Work Began 09-25-14
Work Completed  
Time Computed 08-20-14
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 48
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0920-06-029
LONESTAR TRAFFIC SAFETY, LLC (0.79%)
AMERICAN REMEDIATION OPTIONS, INC. (5.08%)
Contract # 06143032
Totals 661300.20 168754.62 367893.92 55.6

CountyORANGE
Highway CR
From OLD HIGHWAY 90, S.OF I10 ACCESS RD.
To EAST BANK OF NECHES RIVER
CSJ 0920-30-081
Proj ID CM 2015(253)
Work Type GR, BS, STR, PVMT, RR, SIGN
 
0.420 8977087.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0920-30-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143215
Totals 8977087.38 0.00 0.00 0.0