Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyORANGE
Highway FM1130
From FM 1130 AT ADAMS BAYOU
To FM 1130 AT ADAMS BAYOU
CSJ 6137-97-001
Proj ID BPM - 613797001
Work Type BRIDGE REPAIR
 
0.704 344188.12 0.00 351871.32 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-14
Work Began 03-24-14
Work Completed 09-25-14
Time Computed 03-25-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 93
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6137-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134020
Totals 344188.12 0.00 351871.32 100.0

CountyJEFFERSON
Highway IH0010
From ORANGE COUNTY LINE
To HARRIS COUNTY LINE
CSJ 6164-51-001
Proj ID RMC - 616451001
Work Type SWEEPING MAIN ROUTE HIGHWAYS
 
0.100 1801022.09 0.00 1859518.64 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-27-08
Work Began 06-03-08
Work Completed  
Time Computed 06-03-08
Contract Working Days 480
Addl Days Granted 60
Working Days Charged 535
Percent Time Used 99
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6164-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03084014
Totals 1801022.09 0.00 1859518.64 99.9

CountyJEFFERSON
Highway IH0010
From VARIOUS ROADS IN COASTAL DISTRICT
To VARIOUS ROADS IN COASTAL DISTRICT
CSJ 6193-72-001
Proj ID RMC - 619372001
Work Type CALL OUT DEBRIS REMOVAL AND DISPOSAL
 
0.100 1857950.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6193-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06094001
Totals 1857950.00 0.00 0.00 0.0

CountyJEFFERSON
Highway IH0010
From BRAKES BAYOU
To BRIDGE
CSJ 6221-53-001
Proj ID ABT - 622153001
Work Type HAZ - MAT
 
0.066 69000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 10
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05124021
Totals 69000.00 0.00 0.00 0.0

CountyTYLER
Highway FM0256
From FROM 2 MILES NORTH OF US 190 INTERSECT.
To NORTH 1.778 MILES
CSJ 6230-34-001
Proj ID RMC - 623034001
Work Type PAVEMENT WIDENING
 
1.778 491333.01 0.00 492842.02 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-22-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 76
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6230-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144013
Totals 491333.01 0.00 492842.02 99.9

CountyORANGE
Highway SH0087
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6243-34-001
Proj ID RMC - 624334001
Work Type SWEEPING OF ROADWAYS - DISTRICTWIDE
 
9.000 803385.71 0.00 803313.75 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-12
Work Began 10-09-12
Work Completed  
Time Computed 10-09-12
Contract Working Days 224
Addl Days Granted 0
Working Days Charged 169
Percent Time Used 75
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6243-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08124021
Totals 803385.71 0.00 803313.75 99.9

CountyJEFFERSON
Highway IH0010
From CHAMBERS/ HARRIS COUNTY LINE
To TEXAS/ LOUISIANA STATE LINE
CSJ 6247-47-001
Proj ID RMC - 624747001
Work Type ROUTINE SWEEPING OF ROADWAYS
 
0.100 1893193.18 43192.54 1401038.22 74.0
Work Order 03-08-13
Work Began 03-13-13
Work Completed  
Time Computed 03-13-13
Contract Working Days 720
Addl Days Granted 0
Working Days Charged 418
Percent Time Used 58
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6247-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134016
Totals 1893193.18 43192.54 1401038.22 74.0

CountyNEWTON
Highway FM2460
From 2.5 MI. EAST OF SH 87, EAST
To FM 1416
CSJ 6248-20-001
Proj ID RMC - 624820001
Work Type FM 2460 PAVEMENT WIDENING
 
3.660 1187970.52 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6248-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10144009
Totals 1187970.52 0.00 0.00 0.0

CountyJEFFERSON
Highway IH0010
From VARIOUS HIGHWAYS IN DISTRICT 20
To VARIOUS HIGHWAYS IN DISTRICT 20
CSJ 6253-63-001
Proj ID RMC - 625363001
Work Type CALLOUT DEBRIS REMOVAL AFTER A HURRICANE
 
0.001 1600000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04134017
Totals 1600000.00 0.00 0.00 0.0

CountyJEFFERSON
Highway US0069
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6254-54-001
Proj ID RMC - 625454001
Work Type PAVEMENT MARKINGS
 
0.001 861945.00 0.00 1921103.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-23-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 185
Percent Time Used 92
Contractor(s)
CRABTREE BARRICADE SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6254-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06134015
Totals 861945.00 0.00 1921103.00 99.9

CountyLIBERTY
Highway US0090
From VARIOUS
To VAROUS
CSJ 6254-93-001
Proj ID RMC - 625493001
Work Type MOWING OF RIGHT OF WAY
 
10.000 449516.00 67455.40 463880.60 99.9
Work Order 06-03-13
Work Began 06-03-13
Work Completed  
Time Computed 06-03-13
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 41
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6254-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134013
Totals 449516.00 67455.40 463880.60 99.9

CountyCHAMBERS
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6254-95-001
Proj ID RMC - 625495001
Work Type MOWING OF RIGHT OF WAY
 
10.000 395599.00 0.00 315897.00 79.8
Work Order 05-16-13
Work Began 05-23-13
Work Completed  
Time Computed 05-23-13
Contract Working Days 155
Addl Days Granted 0
Working Days Charged 78
Percent Time Used 50
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6254-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134014
Totals 395599.00 0.00 315897.00 79.8

CountyJASPER
Highway US0096
From VARIOUS
To VARIOUS
CSJ 6255-00-001
Proj ID RMC - 625500001
Work Type MOWING OF RIGHT OF WAY
 
256.000 437316.80 0.00 437216.80 99.9
Work Order 05-13-13
Work Began 05-13-13
Work Completed  
Time Computed 05-13-13
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 37
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6255-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134027
Totals 437316.80 0.00 437216.80 99.9

CountyJEFFERSON
Highway IH0010
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6255-67-001
Proj ID RMC - 625567001
Work Type CABLE BARRIER REPAIRS
 
0.001 272209.00 0.00 395060.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6255-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07134013
Totals 272209.00 0.00 395060.00 99.9

CountyCHAMBERS
Highway IH0010
From VARIOUS HIGHWAYS
To VARIOUS LIMITS
CSJ 6258-39-001
Proj ID RMC - 625839001
Work Type CLEAN EXIST CULVERTS, DITCH CLEAN & RESH
 
1.000 486406.67 0.00 614082.91 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-03-14
Work Began 03-12-14
Work Completed  
Time Computed 03-12-14
Contract Working Days 90
Addl Days Granted 10
Working Days Charged 75
Percent Time Used 75
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6258-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144019
Totals 486406.67 0.00 614082.91 99.9

CountyJASPER
Highway FM1007
From FM 1007, EAST OF US 96
To END OF MAINTENANCE
CSJ 6260-17-001
Proj ID RMC - 626017001
Work Type ADDING OR WIDENING PAVEMENT
 
1.766 484850.56 9052.80 1031179.48 100.0
Work Order 04-11-14
Work Began 05-05-14
Work Completed 07-07-14
Time Computed 05-01-14
Contract Working Days 43
Addl Days Granted 13
Working Days Charged 58
Percent Time Used 103
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6260-17-001
LONESTAR TRAFFIC SAFETY, LLC (0.75%)
CRABTREE BARRICADE SYSTEMS, INC. (4.03%)
J & M CONTRACTING, COMPANY ( 17.09%)
Contract # 02144014
Totals 484850.56 9052.80 1031179.48 100.0

CountyHARDIN
Highway US0096
From JEFFERSON, ORANGE, AND HARDIN COUNTIES
To JEFFERSON, ORANGE, AND HARDIN COUNTIES
CSJ 6261-40-001
Proj ID RMC - 626140001
Work Type US 69 ETC. MILL AND OVERLAY
 
0.001 797816.05 0.00 3162950.09 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-28-14
Work Began 06-16-14
Work Completed  
Time Computed 06-16-14
Contract Working Days 38
Addl Days Granted 15
Working Days Charged 47
Percent Time Used 88
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-40-001
CPAVE, INC.(0.67%)
CRABTREE BARRICADE SYSTEMS, INC. (4.09%)
DUSTROL, INC.( 18.13%)
Contract # 03144032
Totals 797816.05 0.00 3162950.09 99.9

CountyCHAMBERS
Highway IH0010
From VARIOUS LOCATIONS IN CHAMBERS COUNTY
To .
CSJ 6262-47-001
Proj ID RMC - 626247001
Work Type CONCRETE PAVEMENT REPAIR
 
1.000 423986.00 2940.00 467515.81 100.0
Work Order 02-14-14
Work Began 03-17-14
Work Completed 11-10-14
Time Computed 03-17-14
Contract Working Days 52
Addl Days Granted 12
Working Days Charged 66
Percent Time Used 103
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134019
Totals 423986.00 2940.00 467515.81 100.0

CountyCHAMBERS
Highway FM1663
From FM 1663, FM 1410,FM2626, FM1013,FM1415,
To FM1943,FM1007 AND FM 3063
CSJ 6265-36-001
Proj ID RMC - 626536001
Work Type DISTRICTWIDE SEAL COAT
 
38.410 919522.21 0.00 939749.77 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 05-19-14
Work Completed 08-08-14
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6265-36-001
STRIPE-A-ZONE, INC.( 13.61%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.03%)
Contract # 01144032
Totals 919522.21 0.00 939749.77 100.0

CountyJEFFERSON
Highway IH0010
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 6266-83-001
Proj ID RMC - 626683001
Work Type CABLE BARRIER REPAIRS
 
0.001 292731.68 14030.00 75695.00 25.8
Work Order 07-29-14
Work Began 09-10-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 24
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6266-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144210
Totals 292731.68 14030.00 75695.00 25.8